This process is concerned with determining the engagement levels of the stakeholders, understanding their needs and interests, and understanding how they might impact the project or how the project may impact them:
1 point
Clear selection
During a project review meeting, a team member disagrees with a collage on the project’s status. Key millstones are dependent upon the completion of these two team members’ tasks. The conflict is negatively influencing other team members, who now doubt their own. What should the project manager do?
1 point
Clear selection
You are a project manager tasked with a project of constructing six similar buildings in sequence. The project is estimated to cost $250,000 with a project timeline of four months. During a review after two months, you found that only two buildings are ready. The Actual Cost is $100,000. The project status is:
1 point
Clear selection
After your last status meeting, your customer has come to you with a complaint in one of the deliverables that will cause the final product to be delayed. You look at his complaint and feel that it's not justifiable and that the product really does meet its requirements. What's the first thing that you do?
1 point
Clear selection
A project manager is working on a critical project for the company. Expert team members indicate that they are also assigned to work on other initiatives and can no longer devote any time to their assignment activities? What should the project manager do first to resolve this issue?
1 point
Clear selection
A government-initiative project has a strict deadline for completion A kick-off meeting is a requirement but one critical stakeholder is unavailable to attend Postponing this meeting will delay the project. What should the project manager do?
1 point
Clear selection