Project management knowledge assessment
Přihlaste se do Googlu, abyste mohli uložit dosavadní postup. Další informace
E‑mail *
1) Which of the following is not true about projects?
1 bod
Zrušit výběr
2) Project manager is responsible for the success and failure of the project.
1 bod
Zrušit výběr
3) A project is considered as successful, when...
1 bod
Zrušit výběr
4) Pareto analysis is based on...
1 bod
Zrušit výběr
5) A project manager spends maximum time in....
1 bod
Zrušit výběr
6) Of the following projects, which is the best project for execution?
1 bod
Zrušit výběr
7) Project charter is prepared during which phase of the project?
1 bod
Zrušit výběr
8) Project plan is prepared during which phase of the project?
1 bod
Zrušit výběr
9) Project charter gives authority to the project manager
1 bod
Zrušit výběr
10) Which of the following is not true about work breakdown structures (WBS)?
1 bod
Zrušit výběr
11) A project has just 10 tasks. The duration of five of these tasks are 20 days each, and the balance five tasks takes 10 days each. These tasks are sequential in nature. What is the duration of the critical path of this project?
1 bod
Zrušit výběr
12) Can a project have multiple critical paths?
1 bod
Zrušit výběr
13) The amount of time an activity can be delayed without affecting the late start of the subsequent activity is known as........
1 bod
Zrušit výběr
14) Activities on the critical path will have zero float
1 bod
Zrušit výběr
15) Can the critical path can change during project execution?
1 bod
Zrušit výběr
16) Early start of a task is 1, Early finish is 10, Late start is 11, Late finish is 20. How much is the duration of the task?
1 bod
Zrušit výběr
17) Early start of a task is 1, Early finish is 10, Late start is 11, Late finish is 20. How much is the float?
1 bod
Zrušit výběr
18) After pouring concrete, there is a waiting time of 8 days for curing, and the subsequent activity can start after 8 days time only. This is an example of.......
1 bod
Zrušit výběr
19) Last time when I traveled from Bangalore to Mysore, it took me 5 hours. I am again traveling to Mysore this week on a Friday and I anticipate heavy traffic. Because of this I plan for 6 hours for the trip. This is an example of...
1 bod
Zrušit výběr
20) Last time when I traveled from Bangalore to Mysore, it took me 5 hours. I am again traveling to Mysore and I plan for 5 hours. This is an example of...
1 bod
Zrušit výběr
21) The flexibility matrix of my project says cost is  negotiable, time is moderately negotiable and scope is least negotiable. There is a slippage in the schedule. Which of the following is best to recover from the schedule slippage?
1 bod
Zrušit výběr
22) The schedule performance index (SPI) of the project is -1, and the cost performance index is +2.  Which of the following is best to recover from the schedule slippage?
1 bod
Zrušit výběr
23) The schedule performance index (SPI) of the project is -1, and the cost performance index is also -1.  Which of the following is best to recover from the schedule slippage?
1 bod
Zrušit výběr
24) The customer is not very clear about the scope of the project. In this case, which is the best contract type to be used?
1 bod
Zrušit výběr
25) You want to buy 100 lap top computers for your project team. Which of the following is the best contract type?
1 bod
Zrušit výběr
26) When the team is in the storming state, what should be the style of the project manager?
1 bod
Zrušit výběr
27) When apple started their outlets in China, they could not cope up with the demand. This is an example of....
1 bod
Zrušit výběr
28) In a delayed project, if I add more resources it may reduce the progress further due increased communication complexities. This is an example of....
1 bod
Zrušit výběr
29) You are the project manager and you have 9 team members reporting to you. What is the number of communication channels in this project?
1 bod
Zrušit výběr
30) The best form of power which no one can take away from you is..
1 bod
Zrušit výběr
Odeslat