A project manager is working on a technical project with a technical lead who is experienced, highly knowledgeable and works well with the team. The technical lead is usually on time with deliverables but their documentation often requires rewriting for formatting and contextual quality. How should the project manager address this?
1 point
Clear selection
To increase the likelihood of project success, project manager A interviews project manager B, who completed a similar project. However project manager B is unable to recall the details. What should project manager A do now to obtain this information?
1 point
Clear selection
A project manager creates an internet project repository available to all stakeholders. The expectation is that all updated documents will be shared via this repository. What type of communication does this describe?
1 point
Clear selection
A project manager is working on a project will components supported by two teams in two different regions. The project manager schedules a call with both teams to solicit estimates for a new requirement. Upon receipt of the two estimates, the project manager is surprised to see that they deviate from what was expected. What should project manager have done to avoid this?
1 point
Clear selection
The implementation of a business requirement for an IT project impacts several applications. The application owner notices that changes to a function in application x can be only upon completion of the development of a new feature in application Y. This is an example of what dependency?
1 point
Clear selection