Which is NOT an event-driven control? *
1 point
What is the PRINCE2 term for a deliverable? *
1 point
Which is not a principle of PRINCE2? *
1 point
On which environment is PRINCE2 based? *
1 point
The decision on whether a project's solution will be contracted to third parties is recorded in a specific PRINCE2 management product? *
1 point
Which of the following quality measures is covered in the process "Initiating a Project".  (IP)? *
1 point
Which of the following is not one of the four elements of the structure of PRINCE2? *
1 point
In which process does the Project Manager ask the Project Board where the authority for making change lies? *
1 point
What provision in Planning can be made for implementing Requests for Change? *
1 point
Which of the following can be described as "partitions of the project with decision points?" *
1 point
Which is a recommended quality review team role? *
1 point
In the PRINCE2 document management structure, how many types of file are recommended? *
1 point
When should a Product Description be baselined? *
1 point
If there were a need to know the current and previous versions of a product, what element of PRINCE2 would most help us? *
1 point
Which is a true statement regarding stages? *
1 point
If a Work Package is forecast to exceed its tolerances, how should a Team Manager inform the Project Manager? *
1 point
Which document contains the planned and actual dates for product approval and hand­over? *
1 point
Which of the following activities is one of the responsibilities of a Team Manager? *
1 point
Which of the following is an input to the "Plan the Next Stage" activity in the "Managing a Stage Boundary" process? *
1 point
If a product fails its quality check, what product should always be updated? *
1 point
Which of the following are a purpose of the Benefits Review Plan?  1) Define how a measurement of the achievement of the project's benefits can be made;  2) Define what benefits assessments need to be undertaken;  3) Define the project, in order to form the basis for its management and an assessment of its overall success;  4) Define the activities required to measure the expected project's benefits *
1 point
Which of the following is an input to the Project Board with a request to authorise the project? *
1 point
If, after a Quality Review Follow-up Action, an error is still not resolved, what action should be taken? *
1 point
Closure of the project can only be authorised in one process. Which one? *
1 point
Which of the following is NOT a PRINCE2 theme? *
1 point
Which is NOT a PRINCE2 integrated element? *
1 point
Which process covers overall direction and decision-making of the project? *
1 point
Which of the following statements is False regarding the Risk Management Strategy? *
1 point
How does the Business Case support the continued business justification principle? *
1 point
The person responsible for carrying out the agreed response to a risk is called? *
1 point
As part of sub-process Assessing Progress the Project Manager would look at which of the following?  1) Checkpoint Reports;  2) The Business Case;  3) The Quality Log;  4) Work Package status *
1 point
Which of the following supports the PRINCE2 principle of Management by Exception? *
1 point
Which of the following is established within the Initiating a Project process? *
1 point
Which of the following is NOT part of the Communication Plan? *
1 point
New versions of the Project Plan are produced at the end of each stage to reflect updated information in three of the four areas listed below. Identify which option does NOT belong to the Project Plan. *
1 point
The information gathered in the Starting up a Project process should answer what basic question? *
1 point
Which role can the Project Manager also perform? *
1 point
Complete the following sentence - A project issue is anything that could have an …… effect on the project *
1 point
Which of the following risk responses involves allowing a third party to take on part of the risk? *
1 point
Which is a purpose of the Project Product Description? *
1 point
Which process can be carried out without using PRINCE2? *
1 point
Which document is used to record issues and risks in the Starting up a Project process if the appropriate registers have not yet been created? *
1 point
Identify the missing words in the following sentence.  The purpose of the [ ? ] process is to establish solid foundations for the project, enabling the organization to understand the work that needs to be done to deliver the project's products. *
1 point
What is the PRINCE2 definition of a project? *
1 point
At what point is the Stage Plan produced? *
1 point
In which process are decisions made on Exception Reports? *
1 point
What does PRINCE2 suggest may assist in the ultimate acceptance of the project? *
1 point
Having completed designing the plan, in which order should the next steps take place to produce a plan?  1) Prepare Estimates;  2) Define and analyze Products;  3) Prepare the schedule;  4) Identify activities and dependencies *
1 point
There are two time driven controls in PRINCE2 which are they? *
1 point
Which is NOT a purpose of the Plans theme? *
1 point
In what process are the project's risk management techniques and standards defined? *
1 point
A PRINCE2 project should minimally have how many stages? *
1 point
How is the Configuration Management Strategy used in the Closing a Project process?  1) Reviewed for its effectiveness in controlling and protecting all products;  2) Examined to confirm how all project files are to be archived;  3) Referenced to establish how all products need to be handed over into the relevant operational environment(s);  4) Updated to incorporate any corporate or programme policies and processes that applied to the project *
1 point
A Change Authority is responsible for … *
1 point
The purpose of what theme is to establish mechanisms to monitor and compare actual achievements against those planned? *
1 point
Which is a purpose of a Daily Log? *
1 point
The Project Board keeps a control of the project through:  1) Highlight Reports  2) Checkpoint Reports  3) Exception assessment  4) Quality Log *
1 point
When does PRINCE2 say the project management team should be considered for updating? *
1 point
What environment does PRINCE2 assume? *
1 point
Which is an objective of the Managing a Stage Boundary process? *
1 point
Which of the following statements is true about a PRINCE2 project? *
1 point
What other product is reviewed at the end of each stage apart from the Business Case and Project Plan? *
1 point
Which of the following is NOT a type of Issue? *
1 point
Which of these is NOT a specific objective of an end stage assessment? *
1 point