QUESTION NO: 301 During the development of the scope management plan, a stakeholder requests the addition ofpilot technology into the project scope to assist with product marketing. What should the projectmanager do? *
1 point
QUESTION NO: 302 An organization is awarded a large construction project. The project manager learns that it successfully completed a similar project and wants to use the lessons learned from that.What data analysis technique should the project manager use? *
1 point
QUESTION NO: 303 The sponsor has provided the project team with a high-level vision for a new product that isscheduled to be released at an industry trade show in three months. Which scheduling technique should the project manager use? *
1 point
QUESTION NO: 304 Project Y uses an agile approach. There is no Scrum Master on the project team, and the projectmanager has a strong technical background.What will the project manager’s primary role be in the project? *
1 point
QUESTION NO: 305 A company is venturing into a new scale of business operations. This environment has differentregulations, requirements, and client expectations. The company is utilizing the existing operatingmodel, in-house knowledge, and expertise to run projects in this space.What is the project manager’s next step? *
1 point
QUESTION NO: 306 One day before getting the project charter approved by all key stakeholders, the project manager found new requirements that are not in the project charter. What should the project manager do? *
1 point
QUESTION NO: 307 A company has decided to create a project management office (PMO) and hired their first projectmanager to manage an integration project. Although the company has been in business forseveral years, they do not have previous experience using project management methodologies.How should the project manager handle the potential project challenges without documented bestpractices and history? *
1 point
QUESTION NO: 308 A project manager is beginning a two-year project and conducts a risk analysis workshop with theteam. A team member identifies that the government will be enforcing a new law in three monthsthat will directly affect the schedule and cost of the project.What should the project manager do next? *
1 point
QUESTION NO: 309 A project manager is working on a critical multinational project. The project is very complex and isplanned to be completed in three years. The project manager is working with several contractorsfrom countries with unstable economies, and the contractors are afraid that they will not be able toguarantee a fixed price for their services for the life of the project.Which precautions should the project manager take into consideration? *
1 point
QUESTION NO: 310 A project manager has been given the responsibility to deliver a high-profile project. The projectmanager understands that the project has budget and time constraints. The functional managerswill not be able to supply the required human resources.What should the project manager do? *