Originally a project has seven activities: A, B, C, D, E, F, and G. Activities A, B, and D can start anytime. Activity A takes 3 weeks, activity B takes 5 weeks, and activity D takes 11 weeks. Activities A and B must be completed before activity C can start. Activity C takes 6 weeks to complete. Activities B, C, and D must be completed before activity E can start, and activity E takes 2 weeks. Activity F can start as soon as activity C completes and has a duration of 4 weeks. Activity G takes 3 weeks and cannot start until activity E is completed. Activities F and G must be completed for the project to be completed. However, during project executing, a dependency was discovered between activities E and F. What is the BEST thing to do? *