Execution
Project execution
Sign in to Google to save your progress. Learn more
Email *
1. You are planning communications on a new service development project. Your stakeholder list is large, but not terribly complicated. Not all stakeholders will understand the need for developing an actual communications plan, and you already have good relationships with most stakeholders on this project. What is one of the major driving forces for communication on a project? *
1 point
2. The customer has accepted the completed project scope. However, the lessons learned required by the project management office have not been completed. What is the status of the project? *
1 point
3. Your well-planned project is likely to encounter a number of change requests and approved changes during its life cycle. In the change management plan, you have outlined the processes that you and others will use to understand the impacts of changes. Getting stakeholder acceptance of the decisions related to change on this project is critical, as a failed project could impact shareholder value and the earning projections for the organization. Your attention is best focused on which of the following regarding changes on your project? *
1 point
4. The customer on a project tells the project manager they have run out of money to pay for the project. What should the project manager do first? *
1 point
5. All the following are parts of an effective change management plan except: *
1 point
6. A work authorization system can be used to: *
1 point
7. A project is plagued by requested changes to the project charter. Who has the primary responsibility to decide if these changes are necessary? *
1 point
8. Effective project integration usually requires an emphasis on: *
1 point
9. Integration is done by the: *
1 point
10. The project manager s many responsibilities include being of service to the team, integrating new team members as the project progresses, and ensuring that the project meets its objectives within scope, time, budget, and other constraints. Which of the following best describes the project manager s role as an integrator? *
1 point
11. Approved corrective actions are an input to which of the following processes? *
1 point
12. Double declining balance is a form of: *
1 point
13. At various points during project execution, the project manager reviews the project charter. Which of the following best describes what a project charter may be used for when the work is being completed? *
1 point
14. Which of the following best describes a project management plan? *
1 point
15. You have recently joined an organization that is just beginning to follow formal project management practices. In a meeting, your manager describes your next assignment, a project to select and implement a new telephone system for the customer service department. When you request a signed charter authorizing you to begin work, the manager suggests you “just draft something.” Which of the following is true about the development of a project charter? *
1 point
16. A project management plan should be realistic in order to be used to manage the project. Which of the following is the best method to achieve a realistic project management plan? *
1 point
17. You have taken over a project during project planning and have discovered that six individuals have signed the project charter. Which of the following should most concern you? *
1 point
18. The project manager is working to clearly describe the level of involvement expected from everyone on the project in order to prevent rework, conflict, and coordination problems. Which of the following best describes the project manager s efforts? *
1 point
19. All the following are parts of the Direct and Manage Project Work process except: *
1 point
20. A project manager is appointed to head a highly technical project in an area with which this person has limited familiarity. The project manager delegates the processes of Develop Schedule, Estimate Costs, Define Activities, and Estimate Activity Resources to various project team members, and basically serves as an occasional referee and coordinator of activities. The results of this approach are likely to be: *
1 point
21. You are in the middle of leading a major modification project for an existing manufactured product when you learn that the resources promised at the beginning of the project are not available. According to your plans, these resources will be needed soon, and their unavailability will affect your timeline and possibly other aspects of the project. What is the best thing to do? *
1 point
22. The primary customer of a project has requested an application change during user testing. As project manager, how should you address this issue? *
1 point
23. The project manager has just received a change request from the customer that does not affect the project schedule and is easy to complete. What should the project manager do first? *
1 point
24. You are the project manager for an existing year-long project that must be completed. Your company just won a major new project. It will begin in three months and is valued at $2,000,000. The new project has a greater starting value and is therefore likely to have a higher priority than your project. It may affect your resources. You are concerned about how you will manage your project so that both projects can be implemented successfully. What is the first thing you should do when you hear of the new project? *
1 point
25. You were just assigned to take over a project from another project manager who is leaving the company. The previous project manager tells you that the project is on schedule, but only because he has constantly pushed the team to perform. What is the first thingyou should do as the newproject manager? *
1 point
26. You are assigned as the project manager in the middle of the project. The project is within the baselines, but the customer is not happy with the performance of the project. What is the first thing you should do? *
1 point
27. In the middle of the project, the project manager is informed by her scheduler that the project control limits are secure. That same morning, she receives a note from a team member about a problem he is having. The note says, “This activity is driving me crazy, and the manager of the accounting department won’t help me until the activity’s float is in jeopardy.” In addition, the project manager has emails from a minor stakeholder and 14 emails from team members. While she is reading the emails, a team member walks into the project manager’s office to tell her a corrective action was implemented by a team member from the project management office, but was not documented. What should the project manager do next? *
1 point
28. The client demands changes to the product specification that will add only two weeks to the critical path. Which of the following is the best thing for the project manager to do? *
1 point
29. During executing, the project manager determines that a change is needed to material purchased for the project. The project manager calls a meeting of the team to plan how to make the change. This is an example of: *
1 point
30. The project was going well when all of a sudden there were changes to the project coming from multiple stakeholders. After all the changes were determined, the project manager spent time with the stakeholders to find out why there were changes and to discover any more.The project work had quieted down when a team member casually mentioned to the project manager that he added functionality to a product of the project. “Do not worry,” he said, “I did not impact schedule, cost, or quality!” What should the project manager do first? *
1 point
31. You are asked to prepare a budget for completing a project that was started last year and then shelved for six months. All the following would be included in the project budget except: *
1 point
32. Which of the following sequences represents straight-line depreciation? *
1 point
33. A project is chartered to determine new ways to extend the product life of one of the company’s medium-producing products. The project manager comes from the engineering department, and the team comes from the product management and marketing departments.The project scope statement and project planning are completed when a stakeholder notifies the team that there is a better way to complete one of the work packages. The stakeholder supplies a technical review letter from his department proving that the new way to complete the work package will actually be faster than the old way.The project manager has had similar experiences with this department on other projects, and was expecting this to happen on this project. What is the first thing the project manager should do? *
1 point
34. Project A has an internal rate of return (IRR) of 21 percent. Project B has an IRR of 7 percent. Project C has an IRR of 31 percent. Project D has an IRR of 19 percent. Which of these would be the best project? *
1 point
35. An output of the Close Project or Phase process is the creation of: *
1 point
36. All the following occur during the Close Project or Phase process except: *
1 point
37. Which of the following is included in a project charter? *
1 point
38. A project manager is trying to convince management to use more formal project management procedures and has decided to start improving the company’s project management by obtaining a project charter for each of his projects. Which of the following best describes how a project charter would help the project manager? *
1 point
39. Linear programming is an example of what type of project selection criteria? *
1 point
40. You have been involved in creating the project charter, but could not get it approved. Your manager and his boss have asked that the project begin immediately. Which of the following is the best thing to do? *
0 points
41. The engineering department has uncovered a problem with the cost accounting system and has asked the systems department to analyze what is wrong and fix the problem. You are a project manager working with the cost accounting program on another project. Management has issued a change request to the change control board to add the new work to your project.Your existing project has a cost performance index (CPI) of 1.2 and a schedule performance index (SPI) of 1.3, so you have some room to add work without delaying your existing project or going over budget. However, you cannot see how the new work fits within the project charter for your existing project. After some analysis, you determine that the new work and existing work do not overlap and can be done concurrently. They also require different skill sets. Which of the following is the best thing to do? *
1 point
42. All technical work is completed on the project. Which of the following remains to be done? *
1 point
43. The project manager can help to influence the processes that affect change on projects by creating and using the most appropriate planning strategies and tools. Assuming the project manager has created and is executing the best possible project management plan, the project sponsor should help the project manager to protect the project against unnecessary changes. Which of the following best reflects the phrase, “influencing the factors that affect change?” *
1 point
44. The organization is about to begin a series of similar projects. The projects will be managed consecutively. Each project involves developing an online cooking video focused on foods appropriate to the month in which they will be released. For example, the summer videos will include picnic food and cool treats, and the December video will feature holiday foods for Hanukkah, Christmas, and Kwanzaa. The project sponsor is adamant that the management plan for each project includes an emphasis on making the best possible use of the lessons learned register. He believes that other projects have not been successful because they failed to take advantage of lessons learned from previously completed projects. The lessons learned register should be updated: *
1 point
45. Knowledge management is a key responsibility of the project manager. This responsibility includes managing two kinds of knowledge on a project: tacit and explicit. Which of the following definitions are correct? *
1 point
Submit
Clear form
This content is neither created nor endorsed by Google. Report Abuse - Terms of Service - Privacy Policy