PMP® Practice Quiz - 13
Sign in to Google to save your progress. Learn more
All of the following are characteristics of a project EXCEPT: *
1 point
A project has a critical path of twenty-three weeks. What is the impact on the duration of the critical path if the management wants you to complete the project in twenty weeks? *
1 point
The project has had some problems, but now seems under control. In the last few months almost all the reserve has been used up and most of the negative impacts of events that had been predicted have occurred. There are only four activities left and two of them are on the critical path. Management now informs the project manager that it would be in the performing organization's best interest to finish the project two weeks earlier than scheduled in order to receive an additional profit. In response, the project manager sends out a request for proposal for some work that the team was going to do, in the hopes that another company might be able to do the work faster. The project manager can BEST be said to be attempting to work with: *
1 point
All of the following are outputs of the Monitor and Control Project Work process EXCEPT: *
1 point
In which part of the cost management process is earned value (EV) used? *
1 point
All of the following are part of a communications management plan EXCEPT: *
1 point
While working on your contract, you receive a claim from the seller for additional costs for the reports the team members have requested. You know that the reports are not in the contract and you were not aware that the team needed the information. What should you do? *
1 point
A project manager wants to more extensively involve the stakeholders on the project. Which of the following would be the BEST way accomplish this? *
1 point
Which motivational theorist said that people cannot ascend to the next level until the levels below are fulfilled? *
1 point
In your project, you would like to create a document that describes the procurement item in sufficient detail so that sellers can determine if they can provide the item. This document is referred to as: *
1 point
Stakeholder analysis is used to systematically gather and analyze quantitative and qualitative information on stakeholders' level of interest in the project. In this process: *
1 point
You're managing a project that might have to contract out work, and you're comparing the relative advantages and disadvantages of finding a seller versus having your company do the work itself. Which process are you in? *
1 point
Your project sponsor has specified that you have to complete your project within 3 months with a funding limit of $ 250,000. This is an example of: *
1 point
You have completed the process of developing options and actions to enhance opportunities and to reduce threats to project objectives. What is your NEXT step? *
1 point
In the process of directing and managing the project execution, your project team may request changes to expand or modify project scope, policies, procedures, project cost, or budget. Which of the following is NOT a request for a change? *
1 point
A company is making an effort to improve its project performance and create historical records of past projects. What is the BEST way to accomplish this? *
1 point
Which motivational theory uses the concepts of esteem and self-actualization? *
1 point
Which of the following BEST describes the role of the project sponsor? *
1 point
A project manager is staying in touch with the work of project team members, managing conflicts, and requesting changes to the project management plan. What process is she involved in? *
1 point
Your top team member has performed extremely well and you want to reward her. She knows that you don't have enough money in the budget to give her a bonus, so she approaches you and requests an extra day off, even though she is out of vacation days. She asks if she can take one of her sick days, even though the company doesn't allow that. Which of the following is correct? *
1 point
All of the following are purposes of the project charter EXCEPT: *
1 point
Which of the following is NOT an output of Monitor & Control Project Work? *
1 point
A team member approaches you with a change that could cut your schedule down by a month. What is the first thing you should do? *
1 point
Which of the following BEST describes a situation where statistical sampling is appropriate? *
1 point
You are working in the vendor management department of your company and are responsible for sourcing printing machines from manufacturers. You recently visited a marketing conference of a leading printing machine manufacturer, where you were offered a gift-voucher of $ 200 for attending the conference. You should: *
1 point
A project has three critical paths. Which of the following BEST describes how this affects the project? *
1 point
A project manager is working on a project for a large technology integrator. His project calls for Java technology. He needs to supplement his technical staff with a technical consultant for one month because his company does not have this skill set due to unexpected leaves of absence in the technical team. He will manage the vendor's work since he wants to retain control. Which would be the BEST type of contract to use? *
1 point
During execution in a project to build a major road bridge, your team found a hefty flaw in the technical drawings. On an ad-hoc base, they had to find and implement a workaround to avoid delays and mitigate technical problems. What should you do next? *
1 point
During the Develop Schedule process, which of the following would BEST provide the basis for the MOST likely activity duration estimate? *
1 point
One of the project objectives for your company was to acquire additional expertise completing a large scale design project. The project is mostly completed when your client terminates the contract. A change in their business means the work is no longer needed. What is the MOST effective thing to do? *
1 point
You are a project manager working on a project. Your sponsor wants to know who a certain work package is assigned to, what control account to bill it against, and what work is involved. What document do you refer her to? *
1 point
You're using a qualified seller list. Which process are you in? *
1 point
While making presentations, the difference between a milestone chart and a bar chart is that unlike bar charts, milestone charts: *
1 point
You are conducting a status meeting and monitoring your risk register when you discover a risk that remains even after you implement all of your response strategies. What kind of risk is this and what should you do about it? *
1 point
Which of the following tools is used to document the lessons that were learned when the contract was administered? *
1 point
You are in the build phase of a Build-Operate-Transfer (BOT) project, which has run into several unanticipated problems. Several risks have surfaced which you had not anticipated earlier. The project is over-budget and significantly behind schedule. What should you do? *
1 point
You are the project manager for one part of a new program in your organization. You are four months into a three-year project when your project team makes significant discoveries on your project. What is the BEST thing to do? *
1 point
Your company is undergoing a change in ownership and the new owners are looking at the total cost of a new product. Which of the following would BEST provide that information? *
1 point
Which of the following would be the MOST appropriate thing to do during the executing process group? *
1 point
In your project, the project manager believes in the superiority of his own race or ethnic background. This is an example of: *
1 point
A project manager is appointed to head a highly technical project in an area with which this person has limited familiarity. The project manager delegates the processes of Develop Schedule, Estimate Costs, Define Activities, and Estimate Activity Resources to various project team members, and basically serves as an occasional referee and coordinator of activities. The results of this approach are likely to be: *
1 point
Based on the chart, if you needed to shorten the duration of the project, which activity would you try to shorten? *
1 point
Captionless Image
The project manager is asked to assist the procurement manager in giving some sellers a tour of the facilities where the project work will be done. What part of the project management process are they in? *
1 point
In your project, you are using Report Performance process to organize and summarize the information gathered. Later, you present the results of the analysis as a comparison to the performance measurement baseline. Some common formats for performance reports that you could use are: *
1 point
The project life cycle differs from the product life cycle in that the project life cycle: *
1 point
You're planning an IT project to set up a development environment, including designing and building a computer room, installing the operating systems and software, and performing a security evaluation. Your project includes three different activities that involve three different network technicians splicing ends onto wires in order to build their own Ethernet cables, because that's less expensive than buying pre-packaged ones. Every Ethernet cable must be tested using a qualification tester. That's an expensive piece of equipment, and there are only a few of them that must be shared between all of the technicians in the company. You need to plan your schedule based on the availability of the testing equipment. What's the BEST place to find that information? *
1 point
Develop Project Charter is the process of developing a document that formally authorizes a project or a phase and documenting initial project requirements. In this context, which of the following statements relating to Business Need and Business Case for a project is correct? *
1 point
In your project, you would like to use the 'Conduct Procurements' process to obtain quotations for subcontracting your work. All the following tools can be used to facilitate this process EXCEPT *
1 point
Three calls were received today inquiring whether one of your resources could be released from your project. There were nine such calls last week. The project is going well and its risk rating is low. Activity R has an early start of 4 and a late start of 45 and an early finish of 14. The project has a cost performance index (CPI) of 1.05 and a schedule performance index (SPI) of 0.893. The project float is zero and even through tough times, you believe the reward system you put in place during project planning is working. What is the BEST thing to do? *
1 point
Your management announced that they want to put you on a Stretch assignment. In this situation, you should consider that… *
1 point
You are in the middle of project executing and find that you are running out of money due to unanticipated changes. What is the BEST thing to do? *
1 point
In your project, you wish to identify and document the specific actions to be performed to produce the deliverables. This is done as part of: *
1 point
Decomposition is a valuable tool for Create WBS process. However, decomposition may not be possible for a deliverable or subproject if: *
1 point
The seller on the project has presented the project manager with a formal notification that the seller has been damaged by the buyer's activities. The seller claims that the buyer's slow response to sending the seller approvals has delayed the project, and has caused the seller unexpected expense. The FIRST things the project manager should do are: *
1 point
You are being hired to manage a highway construction project for a contractor working for Smith County. The sponsor is a project officer who works for the Smith County municipal government. You have three separate teams working all three shifts, with a separate foreman for each team. Each team has members from two different unions, and each union has its own representative. Who is the BEST person to approve the project charter? *
1 point
In your organization, all big technical projects go through Initiate, Analyze, Design, Implement, Test, and Closeout. In this context, a project life cycle: *
1 point
Which of the following statements BEST describes how stakeholders are involved on a project? *
1 point
The seller's project manager is managing a fixed price (FP) contract. She thinks that a large customer-requested change might impact the schedule of the project. What should she do FIRST? *
1 point
Which of the following documents is not used as input for the Verify scope process? *
1 point
To-complete performance index (TCPI) is represented by which of the following? *
1 point
You are the project manager of a construction company planning to build a water treatment plant close to a residential locality. The project owner and sponsor have obtained all the legal clearances for the project. Some of the residents of the locality have approached you with concerns on the probable impact of the project on the environment. In this case, you must: *
1 point
Your company is involved in the activity of identifying and documenting the norms for rating or scoring proposals at the organization level. From a project management perspective, this can be referred to as: *
1 point
A project manager holds a meeting with his manager to explain that an activity has been delayed and the project manager will need additional resources to complete the project. The manager stops the meeting because the project manager has forgotten something. What might it have been? *
1 point
You have just finished most of the work on a new systems integration project when the buyer comes to you with detailed procedures to be used to close the contract. The contract included closure procedures. What should you do? *
1 point
You're a project manager on a construction project. The electrician has started laying out the wiring, when the client comes to you with a change request. He needs additional outlets, and you think that will increase the cost of the electrical work. What is the first thing you do? *
1 point
In your project, if the benefit cost ratio is greater than 1, it means that *
1 point
A project team budgeted US $3,000 for the work performed and has spent US $4,000, to date. If they budgeted US $5,000 for the work scheduled, what is the cost variance (CV)? *
1 point
You are a project manager for a new product development project that has four levels in the work breakdown structure and has been sequenced using the precedence diagramming method. The activity duration estimates have been received. What time management activity would you do NEXT? *
1 point
You are the project manager at an aircraft manufacturing company, where you use a wind tunnel to test how changes in different parameters like wind speed, temperature, humidity, etc. will impact the flight parameters of a prototype aeroplane. So, the project model is computed many times (iterated), with the input values chosen at random for each iteration from the probability distributions of these variables. The technique used is: *
1 point
A project management plan should be realistic so that it can be used to manage a project successfully. Which of the following is the BEST method to prepare a realistic project management plan? *
1 point
You are managing a two-year project involving staff from several departments. The project is on schedule and within budget. A key team member leaves for a four-week vacation without completing a highly technical and specialized activity assigned to him (activity A). The project team cannot begin activity B or activity E (a critical path activity) until activity A is completed. Activity A has three days float and is not on the critical path. A team member, a vendor, and a nonteam member work overtime to complete activity A within its float time. You need to reimburse the nonteam member's department and pay the vendor at an overtime rate. What action should you take? *
1 point
Your employee is three days late with a report. She walks into a meeting where the report is to be discussed and hands you a copy five minutes before the topic is to be discussed. You notice some serious errors in the report. How could this have been prevented? *
1 point
Your project management plan results in a project schedule that is too long. If the project network diagram cannot change but you have extra personnel resources, what is the BEST thing to do? *
1 point
An estimation has been made that the construction of a residential home will cost a certain amount per square foot of living area. This is an example of what type of estimating? *
1 point
You have geographically dispersed team members, from whom you would like to anonymously obtain expert opinion on the project you are managing. Which information gathering technique should you use? *
1 point
The activity list should include descriptions of activities. This is required to: *
1 point
In the last project status meeting, a team member criticized some of his teammates and undermined the status of work done by them. The role that was played by the person was that of: *
1 point
Based on the chart, what activities must be completed before activity H can start? *
1 point
Captionless Image
A project manager is leading an effort to analyze waste and non-value-added activity on the project. One team member reports that two processes in use require work he believes is unnecessary. Another team member reports that a process is not well understood. The project manager must be leading which of the following? *
1 point
A resource assigned to your project contacts you, trying to get off the team. He knows that an important project in his department is going to be approved and will take place at the same time as yours. He wants to work on the other project. Under the circumstances, what is the BEST thing to do? *
1 point
Though you have tried to plan the project to accommodate all major contingencies, you are now asked for the fifth time to decrease the length of time the project will take to complete. The person completing activity C is no longer talking to you because of the added work she needed to do to accommodate previous decreases in time. She has already told you she cannot shorten her activity any more. The person doing activity D has been replaced by a new and less tested resource. The risk of crashing activity F is small. Based on this and the chart, what is the BEST thing to do? *
1 point
Captionless Image
You're managing a construction project to install several hundred air conditioner panels in a new office building. Every floor has identical panels. The customer, a construction contracting company, has provided specifications for the installations. The team is using a process to install and verify each panel. As the team completes each panel, your team's quality control inspector measures it and adds a data point to a control chart. You examine the control chart and discover that the process is out of control. Which of the following BEST describes what you found on the control chart? *
1 point
After collecting requirements, one of your tasks as a project manager is to prepare a scope statement for your project. The scope statement provides: *
1 point
In your project, you want to extend the project schedule to reduce the threat that your project may not get the resources in time to complete the project. This is an example of: *
1 point
A project manager's scope management efforts are being audited. The cost performance index (CPI) on the project is 1.13, and the benefit cost ratio (BCR) is 1.2. The project scope was created by the team and stakeholders. Requirements on the project have been changing throughout the project. No matter what the project manager has tried to accomplish in managing the project, which of the following is he MOST likely to face in the future? *
1 point
What is NOT true for project deliverables? *
1 point
In your project, you use control charts to monitor cost and schedule variances. In this context, you would call the process "out of control" in all the following EXCEPT: *
1 point
A large, one-year telecommunications project is about halfway done when you take the place of the previous project manager. The project involves three different sellers and a project team of 30 people. You would like to see the project's communications requirements and what technology is being used to aid in project communications. Where will you find this information? *
1 point
In your project, you create a document to record the code of account identifier, description of work, responsible organization, and a list of schedule milestones. This document can be referred to as: *
1 point
The project is being completed faster than planned. Which of the following would NOT account for why this has occurred? *
1 point
In your company, you are in the process of deciding whether to buy a product or to make it in-house. All the following statements related to make-or-buy analysis are correct EXCEPT: *
1 point
Which of the following is a common problem in the Close Project or Phase process? *
1 point
The precedence diagramming method (activity-on-node) is different from the arrow diagramming method (activity-on-arrow) because a precedence diagram: *
1 point
You're managing a project, when your client tells you that an external problem happened, and now you have to meet an earlier deadline. Your supervisor heard that in a situation like this, you can use schedule compression by either crashing or fast-tracking the schedule, but he's not sure which is which. What do you tell him? *
1 point
There are 17 people on a project. How many lines of communication are there? *
1 point
Frequent heated discussions with your colleague over an issue are creating a hostile environment. To ease this situation, you agree with your colleague's point of view. The conflict resolution mode that you are using is: *
1 point
Bidder conferences can have a negative effect on the project if the project manager does NOT remember to make sure: *
1 point
Which of the following is NOT a Project Constraint? *
1 point
You want to identify quality requirements and standards relevant to your project and product. For this, you will: *
1 point
You have just been assigned as the project manager for a sizeable engineering project, and you want to quickly review the project's procedures for managing risk. What would be the MOST helpful in finding this information? *
1 point