Strasbourg Road: Grenoble to Marseille Public Comment Form

This project consists of the reconstruction of the existing roadway with new pavement, curb & gutter, sidewalk, ADA-compliant curb ramps, signage, pavement markings, and minor drainage improvements, water, and wastewater utilities. 

Sign in to Google to save your progress. Learn more
Email *
PROJECT FACTS

Project Consultant Architect: Urban Engineering / Jerry Eckert, P.E.

City Project Manager: Bryan Carter

Contractor: Ortiz Construction & Paving, Inc.

City Inspector: Alex Mortera (361) 460-8790

Anticipated Award Date: November 2022   

Anticipated Construction Start:  January 2023        

Anticipated Completion:  September 2023

Total Project Value:   $2.2M