Jackfish Avenue: Park Road 22 to Aquarius Public Comment Form

The City of Corpus Christi classifies Jackfish Avenue as a residential street with a project area consisting mainly of residential, public/semi-public areas, parks, and vacant lots. The reconstruction of Jackfish Avenue will include full-depth concrete pavement. The construction will incorporate minor utility improvements as well as curb and gutter repair, sidewalk installation in front of Ulberg Park, some driveways, signage, and pavement markings.

Sign in to Google to save your progress. Learn more
Email *
PROJECT FACTS

Project Consultant Architect: Lockwood, Andrews & Newnam Inc.

Design Engineer Contact: Scott Harris, P.E.

City Project Manager: Mai-Theresa Bernal, P. E.

Contractor: JE Construction Services

Construction Inspector: Goeffrey Mayer (361) 446-3015

Anticipated Construction Start: August 2023        

Anticipated Completion: September 2024  

Estimated Construction Cost: $1.8M        