Q1: A project manager reviews the burndown chart that shows the progress the agile team made so far in completing the userstories in their current sprint. The horizontal axis shows the number of days in the sprint. The vertical axis shows thenumber of hours estimated by the team to complete the user stories in the sprint backlog.Based on this chart, what should the project manager recommend?
၁ မှတ်
ခေါင်းစဉ်မဲ့ပုံ
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q2: A project manager has been experiencing unnecessary delays during project execution in obtaining signatures fromsenior management due to an inadequate notification process when a signature is required. Addressing the issue onlyrequires a minor update to the communications management plan.What should the project manager do next?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q3: A project manager has just been assigned to an online gaming website development project that requires extensive andspecialized graphics and animations. The company has never needed this talent set on previous projects, so the projectmanager has to go outside for contractors.Where can the project manager look to obtain rough estimates for this work package?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q4 :You need to hire one contractor. You are leaning toward one who has an 80% chance of delivering in one month with acost of $5,000, and a 20% chance of delivering in two months with a cost of $10,000. Another contractor has a 90%chance of delivering in one month with a cost of $6,000, and a 10% chance of delivering in two months with a cost of$12,000.What technique would you use to select the contractor?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q5: During iteration planning, the project manager has assigned tasks to the agile team members. Towards the end of theiteration, one of the developers hit a roadblock and asked for help, but other team members refused since they did notwant to delay their own tasks.What is wrong with this scenario?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q6: A project manager has resigned from her position right after the execution processes of the project she managedhave been completed. You have been asked to close the project. You want to find project closure guidelines that establishthe protocols for the transfer of ownership and knowledge.Where would you find this information?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q7: You are in the process of developing approaches to involve stakeholders in your project. As you review the classificationof various stakeholders in the stakeholder register, you realize that while the project sponsor's authority is high, his levelof concern about the project's outcomes is insufficient.Where would you display the current classification of the project sponsor on the power/interest grid?(Please note that on the real PMP exam you may be asked to provide your answer by clicking the correct area in theimage. But here in the simulator, we are asking you to select the answer below.)
၁ မှတ်
ခေါင်းစဉ်မဲ့ပုံ
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q8: Which of the following integrates scope, cost, and schedule and should be updated to reflect changes to a project?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q9: Once a month, you attend a steering committee meeting to report on project status as specified in the communicationsmanagement plan. During the meeting, the committee members challenge you on the productivity of your project team,pointing out that your team has a velocity of 40 story points per sprint, while another project team is averaging 80 pointsper sprint.What is your best course of action?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q10: Due to funding related issues a few months ago, your company was forced to terminate some of its projects. Since then,one of the projects has been re-initiated, and you have been assigned to manage it. You want to find out the exactreasons for the termination of the project.Which of the following should you review to obtain this information?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q11: A project manager is leading a large project to develop a new model of smartphone. Early in project execution, to fosterthe stakeholder involvement, the project manager holds a meeting as specified in the stakeholder engagement plan.What type of meeting does the project manager likely hold?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q12:A product development project is underway. The project is using an agile lifecycle for software development and isoperating within an overarching project management plan. Despite careful planning, after two software versions havebeen released, the user's guide was not updated to reflect the latest release, causing a great deal of confusion for end-users.What should the project manager do to ensure this problem does not recur?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q13: To determine the project needs and structure, the project manager has had several meetings with the project sponsor andsome of the key stakeholders. As a result, the project manager has completed the development of a document thatdescribes the project purpose, quantifiable criteria that must be met by the project, and key deliverables.What should the project manager do next?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q14: A project manager is tracking the detailed costs of a project in a spreadsheet by listing out each task, associatedresources (human and other), the resources rates, and the hours the resource is used. The project is trackingwonderfully. However, after about two months of running the project, the finance manager approaches the projectmanager to say the actual project’s costs are much higher than the project manager is reporting.What did the project manager most likely do wrong?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q15: After losing a member of her high performing team, the project manager implements the response planned for this risk byhiring an independent contractor. However, as a result of adding the new team member, the team is thrown back to thestorming stage of team development, and the project falls behind schedule.How might the project manager have avoided this situation?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q16: A project manager is estimating the number of work periods needed to complete individual project activities withestimated staff.To complete this process, the project manager should consider all of the following factors except for:
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q17: At each iteration planning meeting, one of the project stakeholders is suggesting new product features. However, thesefeatures are not aligned with the overarching goal agreed to by all the project stakeholders. This repeating situationresults in conflicts between the stakeholder and the team.What is the best course of action for the agile project leader?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q18: A project will use an adaptive approach to prepare plans, develop the product, and monitor progress. Initiating andclosing processes, however, will have to be managed traditionally due to the constraints imposed by the organization. Inthis hybrid environment, the project manager decides to use information radiators.What is the most likely reason behind the project manager's decision?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q19: After a change request to expand the scope of the project has been submitted to the change control board (CCB), theproject manager is reassigned to another project. The CCB approves the change and communicates the status of thechange request to the newly hired project manager.What should the new project manager do first?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q20: Your project is the opening of a new retail store location. The night before the grand opening, you learn that a severestorm has caused significant damage to the building, which threatens to delay the grand opening. The storm wasidentified as a risk earlier in the project and captured, along with the response plan and the risk owner, in the risk register.What should you do immediately?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q21: A senior manager hands the project manager the business case that will be used as an input to develop the projectcharter. Several sources served as the triggers for the creation of the business case.Which of the following would not be one of those triggers?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q22: A project manager is approached by the sponsor who requests to provide an estimate as to how long will it take for theagile development team to complete the project.How should the project manager respond?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q23: A project manager is leading a project with a predictive life cycle. Detailed plans were provided by the requestingorganization before the start of the project.What will be the focus of the project manager?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q24: As part of a larger initiative involving many projects, all the activities from this and all of the other projects have to bealigned and be carried out perfectly.What is the best course of action for the project manager?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q25: A project manager is about to start the processes associated with the Initiating Process Group. The project managerneeds to know who will be responsible for ensuring that the value to the project is preserved a year after the projectdeliverables are handed over to the customer.Where will the project manager find this information?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q26: A project to renovate an old office building is underway when asbestos insulation is discovered covering some of theplumbing pipes. Given the age of the building, the possibility of finding asbestos was a known risk. The risk responsecalls for contracting with a remediation company specializing in asbestos removal. After the remediation companycompletes their work, the project team is unpleasantly surprised to discover corrosion among some of the plumbingpipes.What should the project manager do first?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q27: A construction project experienced delays from lower than anticipated worker productivity, errors in construction, as wellas worse than expected weather. Although these individual risks were previously identified, the combined effects of theserealized risks were greater than the individual risk response plans were able to address, and a critical project deadlinewas missed.What might have been done differently to plan better for the risks?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q28: On October 3(represented by the red line on the Gantt chart below), the project sponsor asks you to provide a progressreport including the CPI for a project status meeting the following morning. You update the project schedule managementtool, which produces the following chart. The method used to determine the earned value is based on percent complete.What are the project's current CPI and status?
၁ မှတ်
ခေါင်းစဉ်မဲ့ပုံ
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q29: Your project is a few days into execution. You are concerned because you notice that your project team members hardlyspeak to one another, aside from polite small-talk, and do not seem to be collaborating very much. As the leader of theteam, you are playing a dominant role during meetings and begin to wonder if there is something wrong with your projectteam.According to Tuckman, what stage is being described?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q30: A request for proposal (RFP) has been sent out to prospective sellers. The sellers' responses came back with a muchhigher cost than expected. However, per company policy, if the responses meet the specifications and the qualityrequirements, which the responses do, the requested service must be selected from one of these sellers.What is the best course of action for the project manager?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q31: A new team of agile practitioners meets for the first time. The agile coach is facilitating the meeting. The team memberscome from different organizations, have various backgrounds and agile experience, and used different agile methods.The meeting participants are wondering as to what agile method to use in their upcoming project and what processtailoring to apply.What should the agile coach do first?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q32: You have been assigned to lead an agile phase within an otherwise traditional waterfall project. On your first day on theproject, you conduct an introductory meeting with the development team, and it becomes apparent that some of the teammembers have gaps in their skillsets to function as generalizing specialists.What should you do first?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q33: Past projects in the organization have been managed in traditional and agile methods. There is confusion as to how manyresources to allocate to the upcoming project that anticipates using a hybrid of methods.How should the project management team estimate resources for the upcoming project?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q34: An agile project has been successfully completed. The customer is very happy with the project deliverables.Which of the following most likely contributed to the project success and customer satisfaction?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q35: The project was a tremendous success. The project exceeded expectations by coming in under budget and exactly onschedule. To celebrate the success, a party was announced and scheduled for the project team. The party will befinanced from cost savings that have been added to the contingency reserves. But as the project is closing, the projectmanager and other stakeholders are feeling it is better to use the funds allocated for the party to shore up future businesswith the customer and appease the project sponsor.What should be done with the funds allocated for the party?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q36: During a sprint review, the product owner rejects a deliverable stating that it does not meet the acceptance criteria. Thequality assurance team, who verified the deliverable as part of the Control Quality process, argues that there is nothingwrong with the deliverable and that it should be accepted. The product owner disagrees and rejects the deliverable.What is the project manager's best course of action to ensure that this type of misunderstanding does not recur?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q37: A project team is using an on-demand scheduling approach as specified in the schedule management plan. During aniteration retrospective, a conflict between team members surges around incomplete work items being passed along to thenext column on the Kanban board. As a result, the amount of rework grows, putting cost and schedule baselines at risk.How should the project manager resolve this situation?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q38: A few days before the end of the last iteration, the team informs the project manager that they will be unable to finish two work packages, A and B, because the WBS is insufficiently refined. The team thinks they might be able to complete package A on time but will need an additional week to complete package B which has a higher priority .What is the best course of action for the project manager?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q39: During a daily standup meeting, the project team raises a risk that was not identified earlier in project planning. The team discusses the risk with the project manager, who realizes that a potential response to the risk is beyond his authority. The risk management plan does not provide any guidance on how this type of risk should be managed. What is the project manager's best strategy to deal with this risk?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q40: You are assisting a project sponsor with the development of a document, which authorizes a product development project. Currently, you need to identify the project's key deliverables for inclusion in the document .What might you do to obtain this information?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q41: Once a month, you attend a steering committee meeting to report on project status as specified in the communications management plan. During the meeting, the committee members challenge you on the productivity of your project team, pointing out that your team has a velocity of 40 story points per sprint, while another project team is averaging 80 points per sprint. What is your best course of action?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q42: An agile project team begins the development of the project deliverables. The sponsor stresses the importance of having the stakeholders apprised of value gain progress as often as possible. What is the best way for the project manager to address the sponsor's request?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q43: As a new project manager, you have just been assigned to a project and asked by the project sponsor to create a draft of the project charter. The company has a project management office (PMO), which is best described as supportive .Unsure of the format the project charter should take, what should you do first?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q44: You have just been hired by a decades-old construction company to lead a custom home construction project. The project has been plagued by thefts occurring at night. You have read the project management plan and all project documents, none of which addresses the theft issue .What should you do next?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q45: A project manager begins the initial planning of a new project. After reviewing the project charter and speaking with the project sponsor and key stakeholders, the project manager selects a predictive project life cycle. How will the selection of this life cycle shape the way the project is carried out? (Choose three)
၁ မှတ်
Q46: A company has been contracted to develop software for a hydroelectric plant. The project management plan specifies Scrum as the development approach. Few sprints into the project, regulators notify the performing organization that due to new environmental laws, safety features originally not included in the scope baseline will need to be built into the software. What is the project manager's best course of action?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q47: According to the construction plan for a custom home, a standard type of concrete will be used for the patio since the patio is required to support significantly less weight than a foundation on which the patio is built. During an inspection, it was found that the concrete used for the patio is of a stronger type, the same type that was used for the foundation. Which of the following statements is true?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q48: On a project, several programmers were hired as independent consultants to supplement the in-house programmers to ensure the timely completion of the project. Towards the end of the project, the project manager has performed some analysis and determined that the CPI is 0.8 and the SPI is 1.2.What is the best course of action to bring project performance back into alignment with the project management plan?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q49: A scrum team is midway into a sprint when the project sponsor approaches the scrum master and requests that a new ,urgent, and potentially complex mandatory compliance-related requirement should be developed immediately in the current sprint. The sponsor stresses that if the requirement is not implemented, the entire project may be canceled .What is the scrum master’s best response?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q50: A project manager has just returned from vacation and wants to get a project update. The project team outlines severalissues and describe how each issue was addressed. The project manager is impressed with how smoothly and effectively the team has addressed the issues even in the absence of leadership. What stage of team development is being demonstrated in this scenario?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q51: You are leading a large and complex project. Due to the size and complexity of the project, you have decided that a project management team will perform most of the planning, and the remainder of the project team will be brought on when the initial planning is complete. In this scenario, when is the best time to conduct the project kick-off meeting?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q52: An agile project team begins the development of the project deliverables. The sponsor stresses the importance of having the stakeholders apprised of value gain progress as often as possible .What is the best way for the project manager to address the sponsor's request?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q53: You are leading a project to develop a point-of-sale system for a retail store chain. The system has been developed iteratively by a collocated agile team. However, training the stores' personnel is done traditionally by the team members placed at the physical retail locations across the country. With the daily standup meetings now being conducted via an audio conference call, the team members encounter misunderstandings and miscommunication .What is the best course of action?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q54: A project is looking to procure a series of products to be developed in tandem with the project. A single supplier must be able to build out the products and provide services to the project team as the team works on the multitude of other components. To best manage the quality of the long-term procurement need, what is the best practice?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q55: After having disagreements to determine the best approach to develop the product, the agile team members meet with the project manager to discuss the issue. However, after a very long meeting, the team is unable to reach a consensus .To avoid any schedule delays, it is essential that an approach be selected by the end of the meeting .What should the project manager recommend to the team?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q56: During project risk planning, the project manager and the team are trying to decide whether to invest $10 million to develop new software or to instead invest $5 million to upgrade the existing software. The team is uncertain how strong will demand be for their product and, therefore, must account for this uncertainty in their analysis .What would be the best tool for the project manager to use in this case?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q57: The project management plan calls for the use of daily standup meetings. During the meetings, impediments are surfaced by the team members, but follow up has been inconsistent. The situation worsens with each passing day as the impediments are accumulated, causing schedule delays and even risking the schedule baseline .What is the best course of action for the project manager?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q58: To develop a charter for the project you have been recently assigned to lead, you have reviewed the business document sand studied the agreements. You lack the information about the key project deliverables which should be included in the charter. What is the best way to obtain this information?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q59: A manufacturing company is considering a potential project to modernize its production process. The sponsor is concerned that the project will require a significant upfront investment and wants to ensure that the project, if approved ,begins delivering value in the form of efficiency gains as quickly as possible. The sponsor requests your help with the pre-project work .What would be your recommendation as to the first step for this initiative?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q60: AA product development project is underway. The project is using an agile lifecycle for software development and is operating within an overarching project management plan. Despite careful planning, after two software versions have been released, the user's guide was not updated to reflect the latest release, causing a great deal of confusion for end-users .What should the project manager do to ensure this problem does not recur?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q61: The sponsor has signed the project charter, and you have been assigned to manage the project. Several employees have already been selected for the project team, and you have not worked with any of them on previous projects. Which of the following will help build relationships between the team members?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q62: You are a senior project manager who is mentoring a newly promoted project manager. Your mentee states that she hasrecurring arguments with her project team and is having difficulty controlling her own temper. This situation has created atoxic environment for the project team and threatens the successful completion of the project.What is the best advice for your mentee?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q63: As the project manager, you are in the process of developing a draft of a document that authorizes a new software development project. You have reviewed the agreements and both business documents. What else should be done as part of this process?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q64:A project manager focuses on systems and structure to accomplish project goals. As a result, the project manager has as trained relationship with the project team. Although the current project is trending to meet project objectives, excessive turnover of the project team threatens the project. For self-improvement, what type of skills should the project manager spend time developing?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q65: A project manager has been chosen to lead the project to find a location for a second headquarters. The project manager wants to formalize the authority that has been assigned to her and to gain commitment and acceptance for the project .What is the best thing for the project manager to do?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q66: Your project is running behind schedule. To bring the timeline back into alignment with the project management plan, you need some of your project team members to work extra hours. In order to motivate your team, you offer each team member two tickets to a popular sporting event if they work a weekend shift. What type of power are you using in this situation?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q67: A new scrum master joins an agile team that is been through its fifth iteration. The scrum master notices that the level of trust in the team is low, the team members are guarded, and conflict often arises within the team. As a result, teamperformance suffers .What is the best course of action for the scrum master to help resolve conflict within the team?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q68: At the beginning of a project to build homes, the project manager learns that a lumber supplier wants to liquidate their inventory. The project manager implements the previously documented response for this opportunity and buys all of the lumber at a greatly reduced cost. When the project manager shares the good news with key stakeholders, some state that the company does not have the facilities to store the extra lumber .What might the project manager have forgotten in this scenario?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q69:  Preorders for the new product you are developing have significantly exceeded expectations, and current production will not meet demand. This situation presents the company with a significant threat and opportunity. You need to take action to mitigate the negative impact of the risk and enhance the opportunity. You know this risk was captured during the Identify Risks process but are unsure of the risk owner and the agreed-upon risk response. What should you do next?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q70: You are acquiring the necessary resources for your project. The organization where you are employed is an international company with locations in several countries. With personnel located around the globe, you will be forming your project team as a virtual team, and the team members will be allowed to work from their home offices. What special considerations do you need to take into account while working with your team?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q71: A project manager has been communicating with 10 stakeholders regularly. Last week 2 more stakeholders were identified and added to the communications management plan.What is the number of potential communication channels?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q72: An agile coach has been nurturing and growing team members through and beyond their current roles. This helpedseveral team members to develop their personal and professional skills to the level where they felt that they outgrew theirroles. Eventually, some of them left the team to pursue new opportunities within the organization and outside of it.Was the agile coach right in her approach?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q73: You are leading a software development project, which is utilizing an agile framework. While monitoring the progress ofthe project, it is apparent that velocity is trending down, and you are aware of some setbacks that have been encounteredby the development team. You want to capture and analyze lessons learned so far during the project to improve theprocess going forward.What is the best way to achieve this goal?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q74: A project manager has been asked to create a document that formally authorizes a project to use ground-penetratingradar to map geological conditions along a proposed crude oil pipeline route. The performing organization has agreed toshare the data with a local university. The project manager has reviewed the business documents and considered anyrelevant external environmental factors to create the requested document.What might the project manager do next?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q75: Midway into project execution, a key stakeholder leaves the company. A new stakeholder fills in the vacant role. Theproject manager understands that the stakeholder engagement plan should be updated to reflect the strategies andactions required to involve the new stakeholder in the project. The project manager meets with the new stakeholder for aninterview.Which of the following questions would be the most helpful for the project manager in updating the plan? (Choose four)
၁ မှတ်
Q76: You are leading two independent teams working on the same project. The nature of the deliverables requires that oneteam takes a predictive approach, while the other uses Scrum. Due to dependencies between the teams and the variablenature of the outputs from the Scrum team, the predictive team needs to confirm their understanding of the Scrum team'sactivities with the shortest feedback loop possible.What is your best course of action?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q77: A senior executive suggests initiating a project to replace a significant portion of the company's labor force with anautomated production line. Other company executives are skeptical that this approach is the best way to increase profitmargins and wonder if they are ready to sponsor such an effort.What is the first thing that should be done in this scenario?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q78: The latest software released to the customer in the first project phase is full of defects. The customer is angry anddemands that the development of the new release, which is planned to be delivered in the second phase, is much moretransparent. The customer wants to see the team’s results more regularly and without very long development intervals in-between.Which of the following could the project team introduce in the second phase to better comply with the customer'sdemand? (Choose four) *
၁ မှတ်
လိုအပ်ပါသည်
Q79: You are in the initiation stage of a project that aims to deploy and then maintain the robotics for an automated productionline for an important client. In the project charter, you need to include the agreed mean time to recover (MTTR) in theevent of a breakdown.What should you do to find this information?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q80: As a project manager, you recently completed a project team performance appraisal, and a previously unknown competency gap in technical skills was uncovered, which needs to be addressed.What should you do next?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q81: An organization is transitioning from predictive project management to agile. As a project manager, your upcoming projectwill require compliance reporting that will need to be submitted to internal auditors due to regulatory oversight.How might you address the need for compliance reporting in this hybrid environment?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q82: You are leading a hybrid project with an agile team developing the web application and a traditional engineering team todesign the servers that will host the application. You want to determine what does your company say about the use ofsocial media tools to communicate and work with the stakeholders to meet their needs and expectations.What is your best course of action?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q83: During a sprint retrospective, the team members complain that the business analyst has been unresponsive to clarify thework package to be developed in the sprint. As a result, the work package has not been accepted by the customer. Thescrum master reaches out to the business analyst and requests them to collaborate with the team during the upcomingsprints.What else should the scrum master do?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q84: You are managing a project, and members of your project team are at odds about the tasks they are assigned.Disagreements between the team members have escalated and have created a reduction in performance across theproject.What tool or technique will you use to address the team's issues and get the project back on track?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q85: A scrum master is conducting a daily standup. Each member of the development team states that their work has beenstalled due to various blockers. As a result, the entire development team has been idled, and the schedule baseline is injeopardy.What should the scrum master do first?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q86: An agile coach joined a team that has been working on a project for the last few months. The coach noticed that the team members were struggling to remove impediments, did not have a discipline around time-boxed events, and were not using information radiators to display the project status.What is the best course of action for the agile coach to take?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q87: Customer requirements for the new application to be developed by an agile team limit the technology choices to only two approaches. The team members are not familiar with any of them and ask the scrum master for advice. Which of the following should the scrum master recommend to select the best approach?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q88: A project manager is explaining the roles and responsibilities for the quality assurance process with the project team.Who will play a role in this process?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q89: A PMO steeped in traditional waterfall project management has hired you, as an agile practitioner, to guide theorganization's transformation to agile. After completing an initial assessment of the organizational culture, you haverealized that many of the stakeholders are resistant to the change.What is your best course of action?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q90: Two project team members have had frequent clashes, which have at times resulted in shouting matches during teammeetings. The project manager has intervened, asked them to resolve their differences, and even facilitated a meetingbetween them, but things have gotten worse. The project manager is concerned that the situation is negatively affectingteam cohesion and is placing the successful completion of the project at risk.What should the project manager do next?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q91: To engage the newly identified stakeholders in the project at the earliest opportunity, the scrum master suggests invitingthem to the upcoming sprint review meeting to demonstrate to the stakeholders that the team is moving in the rightdirection and get feedback from the stakeholders about what the team has accomplished.Which of the following is another reason for inviting the stakeholders to this meeting?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q92: You are attempting to coordinate activities between your project, another related project, and operations, all of which arebeing managed as a group. A conflict has arisen over control of a key resource that is vital to both projects as well asoperations. The conflict has reached an impasse and needs to be resolved by a higher authority.What is your best course of action?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q93: Your project team functions as a well-organized unit. The team members are interdependent and work through issuessmoothly and effectively.What is your best course of action?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q94: A company is experiencing exponential growth and will soon run out of space in their current production facility. A needsassessment has been completed to evaluate alternatives. One of the options to support future growth is to build anexpansion on to their existing production facility.What should the company do next?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q95: An agile coach is leading an iteration planning meeting, which is being dominated by a highly respected senior developer. The agile coach is concerned that the senior developer might be exerting too much influence and overcommitting theteam.What is the best course of action for the agile coach?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q96: You are leading a software development project using agile methodologies. If the project is successful, it will open up vastopportunities for future revenue and growth. The project has a high risk of failure, but the potential benefits outweigh therisks. These risks and rewards must be considered when selecting the content of each iteration.Which features should be prioritized and developed first in this scenario?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q97: Midway into an iteration, an agile team faces a minor technical issue. One of the team members recalls that the agilecoach is an expert in the field from her past experience as a senior developer. The team requests that the coach helpresolve the issue.What should the agile coach do first?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q99: Near the end of an iteration, the project team is ready to lead a product review with the product manager.What is the objective of the review?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q99: You have been assigned to lead an initiative for which the business case has not been sufficiently made to get approvalto initiate a hybrid project. In some of the past projects, teams realized too late into project execution that no one in thecompany had the skills needed to build some of the features, so it was developed by a contractor, resulting in costoverruns.What would you do differently in your assignment to avoid cost overruns?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q100: A project has short iterative planning and executing cycles where the requirements are progressively elaborated. The keystakeholders are continuously involved and provide frequent feedback allowing the team to respond to changes morequickly.What is the best way for the project manager to manage quality in this type of project environment?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q101: A project manager is estimating the length of time the project will take. The project manager worked on a comparableproject two years ago that installed 10 miles of guardrails at a rate of one mile a day in similar weather conditions, usingthe same size crew on the same type of highway.What estimating technique would be the appropriate option for the project manager to use for his duration estimate? *
၁ မှတ်
Q102: The project manager is 6 months into a multi-million-dollar project. The latest analysis shows a CPI of 1.5 and an SPI of0.6.What should she do?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q103: At the daily scrum meeting, one of the team members brings up a problem accessing a database that impedes hisprogress. Another team member offers a possible solution, which begins a conversation between the two team members.After a few minutes, the scrum master cuts off their conversation, reminding them that the daily scrum is not theappropriate venue for their discussion.What should the scrum master do next?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q104: The project you are leading is supposed to upgrade the application developed by your company on desktop computersand mobile devices. Last week, a major supplier of electronics unexpectedly released a new mobile device. You realizethat your application, with a little bit of modification, can run much faster and more securely on the new device.What should you do next in regards to this opportunity?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q105: You are leading a software development project for a client. The change control board (CCB) has been inundated withchange requests from the client throughout the project as the product has evolved. This situation drives the team crazyand makes controlling the project scope extremely challenging and time-consuming.Which of the following tailoring considerations might you have missed earlier in the project?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q106: ThePMBOKGuidedefines project charter as a document that "formally authorizes the existence of a project andprovides the project manager with the authority to apply organizational resources to project activities."Developing project charters on agile projects:
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q107: A project manager is analyzing the communication needs of stakeholders in order to develop the communications management plan for a project that will use a hybrid project management framework. The project manager understands that the plan should accommodate the needs of both predictive and agile aspects of the project .How should the plan accommodate the agile aspects of this project?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q108: The project manager and a stakeholder get into a heated debate about the stakeholder's idea requiring a scope change to the project. The project manager says the change will not be implemented and that the stakeholder must drop the idea .The project manager emphasizes that she is the project manager and the decision is final .Should the project manager have responded differently to resolve the conflict?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q109: Unlike traditional managers, agile leaders:
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q110: You have just been assigned to an upcoming agile project. As part of pre-project work, you review all of the organization's policies and procedures regarding compliance. You realize that only some of them may be applicable to your project .What should you do first?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q111: The quality management has been perfect for the project up to this point. Suddenly, the quality assurance (QA) lead who developed and performed most of the quality activities for the project has been temporarily reassigned to help another project .What should the project manager do?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q112: A project manager is currently in the process of determining, documenting, and managing stakeholder needs and requirements. Due to the sensitive nature of the project, there is a concern that some stakeholders will not provide candid feedback unless confidentiality is maintained. What is the project manager's best course of action?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q113: You are the project manager for the initial design phase of a new ergonomic pen. You have conducted multiple interviews with pen users and have tested various design concepts. Your most recent design has been verified and accepted by key stakeholders. The pen design is ready to transition to the team managing the next phase .Which of the following should you consult to find out who will take ownership of the pen design?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q114: You and the project management team have been vigilant about observing different aspects of the project to ensure the project is progressing as planned. Currently, you are using performance data generated during project execution to determine if the status of overall project risk has changed, if the project assumptions are still valid, if contingency reserves for cost or schedule require modification, and if project strategy remains valid. What process are you performing?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q115: You are leading a software development project, which requires knowledge of several programming languages. During project execution, one of the developers has been pulled out of the project by her functional manager. The manager provided you with another developer instead .What should you do first?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q116: As a scrum master, you are facilitating a retrospective for a sprint that failed to meet all of its objectives. Members of the development team and the product owner are arguing over who is responsible for the failure. After performing a root cause analysis, you uncover the source of the conflict .Of the following, what did you most likely discover?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q117: A project manager is determining the budget for a software development project where the product will be built incrementally. Since the project is subject to a strict budget, the project manager has to ensure that scope and schedule baselines stay within cost constraints. The project manager includes budgetary requirements in the release plan .How can the information in the release plan help the project manager with determining the project budget?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q118: The deliverables of a two-year-long project have just been accepted. It is four months late, but the customer is pleased to have it. The project manager is glad to be done with the deliverables but is concerned about the cost and schedule overruns. He decides to re-run the initial cost-benefit analysis using the actual project costs. Where should the project manager obtain the initial cost-benefit analysis?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q119: You and your project team have just completed the development of the project management plan for your agile project .You have requested one of the team members to schedule a meeting to present the finalized project management plan .The team member has asked who should be invited to the meeting .How should you respond?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q120: A scrum master is working with stakeholders to develop the project vision for inclusion in the project charter and wants to ensure that regulatory compliance measures are incorporated into the project requirements. How might the scrum master analyze the consequences of non-compliance?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q121: A project manager is assigned to an agile software development project for a large banking corporation. With the project just getting underway, the project manager has learned about new hacking tactics that present a potential threat to regulatory compliance for the project .What should the project manager do next?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q122: An agile project to develop a new application has just finished its first iteration. To better assess marketing and support needs, the company's management has requested that the scrum master provide a date for when the application can be launched .What is the best course of action for the scrum master?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q123: You are leading a project to develop a product that will be sold through an existing nationwide dealer network. The product will be built incrementally by a virtual team, while the dealer training and product rollout processes will be well-defined upfront. You want the dealers to provide the team with regular feedback throughout product development ?What is the best strategy to achieve your goal?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q124: A new developer joins the project. However, her productivity is limited since she lacks the competency in one of the programming languages. This language is not only used on this project but will also be required on future projects. Training costs were not included in the project budget, and the project CPI is 0.75.What is the best course of action for the project manager?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q125: A project manager has just received a signed formalized document as an output from one of the initiation processes in her project. This document was prepared by someone external to the project and will be utilized as a catalyst for the project to move forward. Which of the following describes this document?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q126: You are leading a software development project for a client. Due to unstable requirements, you have elected to use a change-driven life cycle. You are currently facilitating an iteration planning meeting with the product owner and the development team .What should you do as part of the meeting?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q127: You are preparing for an upcoming software development project. The project will be initiated and planned using a predictive approach, while the development team will use Kanban. A budget has been established for training, and you need to determine how to allocate those funds. What is your best course of action?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q128: You are managing a virtual project team across multiple time zones. As the project progresses, the team members learn to trust one another and adjust their work routines to accommodate the different time zones, work habits, and culture .What stage of team development is being demonstrated in this situation?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q129: You are leading a project to be developed incrementally in small releases. Requirements have been established for the initial release. Feedback from a focus group will determine the scope of each subsequent release. The client has established a strict budget for the entire project .In this adaptive environment, which is the best way to proceed?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q130: During the development of the stakeholder engagement plan, the project manager realizes that a key stakeholder is resistant to the project. Without the support of this stakeholder, the project may fail. What is the best course of action for the project manager to identify the reason for the stakeholder being resistant?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q131: During project execution of a high priority project, a previously identified risk is realized. The project manager sends an email to the risk owner and receives an automated response indicating that this individual will be out of the country on vacation for the next two weeks. The risk owner did not disclose a backup contact to use during the interim. What should the project manager do first?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q132: You have been requested to fill in for a project manager who has called in sick. As you get yourself familiar with the project team, you notice that the team members do not collaborate well, and there are a lot of disagreements and conflicts going on. You feel that the overall environment is counterproductive .Based on your observations, where is the team on the Tuckman ladder?(Please note that on the real PMP exam you may be asked to provide your answer by clicking the correct area in the image. But here in the simulator, we are asking you to select the answer below.)
၁ မှတ်
ခေါင်းစဉ်မဲ့ပုံ
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q133: A project manager is in the process of creating the stakeholder register. He has just completed the stake holder classifications and needs to update the project roles. According to the partial stakeholder register below, which individual is most likely to be the project sponsor?
၁ မှတ်
ခေါင်းစဉ်မဲ့ပုံ
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q134: During an initial project planning meeting, the project team decides to save a portion of cost estimates in the work package to offset the potential risk of advances in technology, which would make their current equipment obsolete .What is the best course of action for the project manager?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q135: A project manager creates a procurement statement of work (SOW) from the project scope baseline. The scope of the SOW, however, is not yet well defined, therefore the project manager decides to contract with a vendor to provide an agile team of programmers. The contract is structured with fixed-price increments based on user stories. How might the project manager verify that the vendor has met the contractual obligations?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q136: You have been assigned to lead an agile project. You want to ensure that project information is shared within and across the organization, so that any misalignments, dependencies, or other issues related to the frequently changing requirements are surfaced as quickly as possible. How could this goal be best achieved?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q137: Four vendors have responded to a bid request on your project .Which of the following vendors should you select based on the expected monetary value (EMV)?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q138: You are leading a project that was supposed to be managed using agile methods. Every week, however, the product owner holds a five-hour backlog refinement meeting with the project team where she presents the project scope broken down to the work package level. After three iterations, the project team's velocity is slower than expected. What is your best course of action?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q139: You are managing a project with stakeholders from many different departments including marketing, engineering, and information technology. As you are monitoring stakeholder engagement, it becomes clear to you that stakeholders from the marketing department who used to be supportive appear to be neutral. After researching the reasons for the gap, you discover the marketing department views the project communications to be too technical, leading them to lose interest in the project .What might be your next step?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q140: You have joined a project in which requirements are elaborated at periodic intervals during delivery, and the delivery is divided into subsets of the overall product. Change is incorporated at periodic intervals, and risk and cost are controlled by progressively elaborating the plans with new information. Key stakeholders are regularly involved .What development approach is used on your project?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q141: You are managing a project to build 100 site towers, and you have just completed building the 50th tower. To mark the successful completion of this first significant milestone, you hold a celebration where you share the developments ,challenges, and lessons learned so far on the project .In what process will you use this information and knowledge gained so far to improve the future performance of the project?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q142: A project manager is executing the quality management plan of a project to develop a prototype medical device. Given the nature of the project, the quality standards are very stringent. With no known cause, it becomes apparent that the product quality does not meet project requirements .What is the best course of action for the project manager to take in this situation?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q143: You are a project manager conducting a meeting with your project team. The goal of the meeting is to improve the overall team environment to enhance project performance. The meeting becomes contentious with team members interrupting each other and being disrespectful to each other's suggestions. You attempt to return civility to the meeting by establishing ground rules for acceptable behavior, but working relationships may already be damaged .What might you have missed that could have prevented this situation?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q144: You are leading an agile project to develop a computer game, which will be broken down into four releases. After the first release, the initial online reviews are poor, and the early adopters have provided detailed feedback about what they don' t like about the game. You are concerned about the impact of the poor reviews on future releases. What is the best course of action?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q145: The project requires ongoing stakeholder engagement and needs to respond to high levels of change. The project manager has chosen an adaptive life cycle for the project. The backlog contains an ordered list of requirements and work .At the beginning of each iteration, the team determines how many of the items on the backlog can be delivered within the next iteration. Which process(e s) will the project team need to repeat with each iteration?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q146: A project has to procure goods and services from a seller. Some aspects of the procurement are well-defined up-front while others will be known only after initial deliverables are validated and accepted .What contracting technique would work best for this procurement?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q147: A project manager is drafting a charter for a software development project. In support of this process, the project manager has scheduled a brainstorming meeting to gather relevant information. Which of the following activities is the project manager least likely to conduct?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q148: A scrum master is leading an agile project in which the development team has failed to achieve the sprint goal for the past three iterations. During the sprint retrospective, the team decides to implement several changes to improve velocity. How might the scrum master verify any performance improvement?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q149: Following is an illustration of a project network activity node that includes some information about activity B. Assuming that work starts on day one (not day zero) and given the information provided, what is the late start of activity B?
၁ မှတ်
ခေါင်းစဉ်မဲ့ပုံ
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q150: Your company has been contracted by a client for a software development project. The project will use agile methods to deliver product increments. For the client, however, this project will be their first experience with agile. You want to make sure that the client gains the full benefit of early and continuous delivery of software .What is your best course of action?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q151: You are the project manager for a project that is in its early stages. During a meeting, your boss informs you that senior management would like you to include a particular staff member on your project team because of their necessary expertise. You have not recruited any other team members, and the project has not even been formally authorized yet .How should you handle senior management's request?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q152: A project manager has just calculated the project performance measurements, and the project's current cost performance index (CPI) is 0.9 while the schedule performance index (SPI) is 1.1.Which of the following is correct regarding the project's performance status?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q153: You are creating the schedule to deploy a new ERP software in your company. The company is currently undergoing an agile transformation, so it was decided to develop the new ERP iteratively. The first release of the ERP should be rolled out in four months, and you know that another project, a company-wide operating system upgrade, is scheduled in three months .With the upgrade project affecting your schedule, an impact on which of the following should you assess to determine the number of iterations until rollout?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q154: To comply with the customer's contract, the project must use a certified agile practitioner to lead and coach the project team. However, the only certified agile practitioner employed by the company was just assigned to another project. The project manager must now hire an independent contractor to serve as the agile coach, which delays the start of project execution. Which of the following may have helped to avoid the delay in executing the project?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q155: The first phase of a software development project that was conducted using a predictive project management approach is over. The project enters its second phase which will require the project team to utilize an e Xtreme Programming (XP)method to develop the rest of the product .How might the team ground rules need to be updated?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q156: You and your team are currently developing the stakeholder engagement plan. A project team member has al ready created the stakeholder engagement assessment matrix below. Which answer choice represents the most important element to be included in the stakeholder engagement plan?
၁ မှတ်
ခေါင်းစဉ်မဲ့ပုံ
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q157: A client completed a walkthrough of the deliverables and formally accepted the work. The next day, the project manage returns to the project site to pick up company equipment and make arrangements for final payment. What should the project manager do when meeting the client as part of project closure?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q158: A vendor has been contracted by a buyer to develop a new device. The vendor insisted that the contract thoroughly captures the device specifications. The buyer does not have clear requirements upfront and, therefore, requested that the vendor develop the device using agile. The vendor delivers as per the contract, but the buyer is not satisfied with the outcome .Which Agile Manifesto's value was most likely not appropriately applied?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q159: The project management plan and the performance measurement baseline have been approved. As you monitor the project's progress, you realize the approved budget is limiting the project and will affect the targeted completion date. This constraint could affect the company's success in the new venture. What is your best course of action?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q160: As you execute the quality management plan for a project to develop a new autopilot feature for a vehicle, you havecreated the diagram below, which compares the vehicle speed with uncommanded lane departures.What can be said about this diagram?
၁ မှတ်
ခေါင်းစဉ်မဲ့ပုံ
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q161: During project execution, the new state-of-the-art technology that is used on the project to produce the deliverables isunstable, which puts the whole project at risk of failure. Your sponsor is on vacation and cannot be reached. To getimmediate attention to the issue, you want to know what is the escalation procedure.What should you do next?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q162: Monthly audits were performed to determine if project activities comply with corporate policies, procedures, and bestpractices. Throughout the project, the results of the monthly audits indicated that the team was in compliance. However,at the end of the project, it was determined that some of the project activities did not comply with organizational policies.What most likely caused these compliance gaps to be missed during the audits?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q163: After reviewing proposals for a large-scale product development project, vendors X and Y are equally qualified to deliverboth the hardware and software. The project manager believes the hardware should be developed with a traditionalproject management approach, but the software might be better suited to an agile framework.What is the best course of action?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q164: An agile team member encounters a technical issue while developing one of the user stories she selected for the currentsprint. After multiple unsuccessful attempts to resolve the issue, the team member approaches the scrum master foradvice.What is the best course of action for the scrum master? *
၁ မှတ်
Q165: As your project progresses, a team member suggests a minor modification to one of the project deliverables, saying thatthe modification will improve the overall performance of the final product. You believe that the modification constitutes aminor change to the project scope, schedule, and budget, and should be approved without going to the change controlboard.What should you do next?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q166: An agile team is trying to determine the ideal iteration length. The team members are having a long and intense argumentabout it, but no one is willing to compromise. The scrum master is called in to help resolve the conflict.What is the best course of action for a scrum master?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q167: You are leading a project in a small startup company with decentralized purchasing. A supplier informs you that they haveexcess inventory that can be purchased at a reduced price. You review the project's inventory needs and find that most ofthe excess inventory offered by the supplier can be used for the project What is your best course of action?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q168: Planning is underway for a project to develop a new online collaboration tool. The team will use eXtreme Programming(XP) method to develop the tool, while the deployment to the customers will be managed using a waterfall approach. Theagile coach would like to gather early customer feedback to ensure the new tool is aligned with the product vision.What is the best course of action?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q169: The agile project team members are all working in an open office space arrangement. There are many conversations happening concurrently throughout the day.Which of the following is the best option for the project manager?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q170: Up until now, your project team has allowed the use of flextime where project team members may take time off duringregular business hours and make up the time during the evening hours or weekends. Recently, excessive use of flextimehas become a roadblock as some team members are not available when needed. The team feels they should set astandard that flextime is only to be used for personal emergencies.How should you handle this situation?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q171: The project team has just completed its fourth sprint. As part of the Control Costs process, you determine that the team's average velocity is 25 points per sprint, and the team has earned 1/3 of the total number of story points required to complete the entire project. The average cost per story point is $575.What is the estimate to complete the remaining work?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q172: As a project manager, you are leading a colocated project team that will create deliverables in an agile fashion, followedby a rollout phase that will use a predictive approach. You are concerned that the transition from agile to waterfall maycause friction within the project team.With the development phase complete, how might the team's working agreements need to change in this situation?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q173: All of the below options are inputs to Determine Budget process except?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q174: Gold plating had been an issue with your current software development project. However, you found that ever sinceinstituting daily stand-up meetings, no more features or functionalities that the customer did not request have beenintroduced into the project.What is your best course of action to prevent gold plating for the remainder of the current project and on future projects?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q175: A project manager is facilitating a sprint retrospective meeting where the team members discuss customer dissatisfactionfrom the product increment they delivered during the sprint. The discussion reveals some issues with the remote teammembers who were primarily using email to communicate with the rest of the team.What was the most likely cause the product increment did not meet customer expectations?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
Q176: A new smartphone will be developed by two teams: a hardware team that will use a predictive project management approach and a software team that will use an agile framework. Each team is colocated but resides in two different partsof the country. The teams will need to coordinate their activities very closely, but bringing them together in one location isnot an option.What should the project manager do to create the most collaborative environment?
၁ မှတ်
ရွေးချယ်မှုကို ဖယ်ရှားရန်
ပေးပို့ရန်
ဖောင်ကို ရှင်းထုတ်ရန်
ဤပုံစံကို Talent Connected WorldWide အတွင်းတွင် ပြုလုပ်ထားပါသည်။ အလွဲသုံးစားမှု တိုင်ကြားရန်