PMP® Practice Quiz - 22
Sign in to Google to save your progress. Learn more
The product manager for the product the project is developing notifies the project manager that she has decided the product should be usable by an additional market. The BEST thing for the project manager to do would be to: *
1 point
You are the project manager for a railroad construction project. Your sponsor has asked you for a forecast for the cost of project completion. The project has a total budget of $80,000 and CPI of.95. The project has spent $25,000 of its budget so far. How much more money do you plan to spend on the project? *
1 point
You've consulted your Earned Value calculations to find out the EAC and ETC of your project. Which of the following is the BEST place to put that information? *
1 point
Benefit measurement and constrained optimization are examples of: *
1 point
You are creating a cost performance baseline for your project. In this context, all the following statements related to cost performance baseline are correct EXCEPT: *
1 point
Which of the following is NOT included in a schedule change control system? *
1 point
A project coordinator is having trouble securing programmers for her project. Every time she asks her boss to give a resource to the project he says that they are too busy to help out with her project. Which type of organization is she working in? *
1 point
Inspection includes activities such as measuring, examining, and testing undertaken to determine whether results conform to requirements. The other terms used for Inspection are all of the following EXCEPT: *
1 point
You have just been assigned as the project manager for a new telecommunications project that is entering the second phase of the project. There appear to be many risks on this project, but no one has evaluated them to assess the range of possible project outcomes. What needs to be done? *
1 point
A project manager spends time determining his company's objectives and how the project fits into them. This is an example of: *
1 point
A project manager is managing his second project. It started one month after the first and both are ongoing. Though his first project is small, this one seems to be growing in size every day. As each day passes, the project manager is beginning to feel more and more in need of help. The project manager has recently heard that there was another project in the company last year that is similar to his second project. What should he do? *
1 point
The value of work actually accomplished is also known as *
1 point
All of the following are factors in the assessment of project risk EXCEPT: *
1 point
Tom is a project manager on an industrial design project. He is always watching when his team members come into the office, when they take their breaks and when they leave. He periodically walks around the office to be sure that everyone is doing work when they are at their desks and he insists that he make every project decision, even minor ones. What kind of manager is he? *
1 point
Which of the following are ALL tools and techniques of the Manage Project Team process? *
1 point
You are creating a project charter to formally authorize the project. A project statement of work will be helpful in creation of the charter because it includes all the following EXCEPT: *
1 point
All of the following are reasons to terminate a contract EXCEPT: *
1 point
You are a project manager in an IT company. You have recently received an offer as a project manager in a construction company offering a 25% salary hike. You have excellent technical knowledge in the IT field, but do not have much exposure to the construction industry. In this context, *
1 point
The work breakdown structure is created by: *
1 point
A project team is scattered across North America, South America, and Europe. There are seven companies working on the project and 67 core team members. Which of the following would have the GREATEST impact on making the situation easier to manage? *
1 point
While working with the procurement department to create the procurement documents for a project, the project manager is told this is the ninth time similar items have been purchased by the company and each procurement was administered easily. After asking a few questions and having a few discussions about the project manager's needs, the procurement administrator produces the procurement documents quickly and calls this a commodity purchase. Instead of receiving bids from four companies as expected, the buyer receives 11 bids. A few of the bidders express interest in giving the buyer a chance to tour their facilities. Other bidders provide in their bids substantially more valuable services than were requested. The buyer's company has a policy of selecting the lowest bidder for the type of work. The bids come in, and one seller's bid is 35 percent lower than the project manager's own independent estimate. Which of the following is the MOST likely reason for this? *
1 point
You're the project manager on a software project that is planning out various approaches to technical work. There's a 20% chance that a component you are going to license will be difficult to integrate and cost $3000 in rework and delays. There's also a 40% chance that the component will save $10,000 in time and effort that would have been used to build the component from scratch. What's the EMV for these two possibilities? *
1 point
Which is NOT an example of cost of quality? *
1 point
You are given a new project to manage and a brief project scope statement. The project sponsor tells you that there is no required completion date for the project. The BEST thing to do is to: *
1 point
Management by objectives works only if: *
1 point
You have asked your programmer to give you an estimate of how long she will take to complete a software program. She mentions that she would most probably get the job finished in 2 hours. But if she runs into some issues with doing unit-testing for the program, it could take her as long as 7 hours. On the other hand, she may be able to pick up a similar program from the organization process assets, in which case it will take her only 1 hour. What is the standard deviation? *
1 point
A contract which includes features of cost reimbursable and fixed price types of contract is a: *
1 point
Which of the following payments on an international project is unacceptable? *
1 point
What does the term Best practice often refer to? *
1 point
Change requests are an output of which processes? *
1 point
As a PMI Certified project manager, you are responsible for all of the following EXCEPT: *
1 point
Which of the following is done during the Create WBS process? *
1 point
Your company has sent out an RFP, and your brother wants to bid on it. What's the BEST thing for you to do? *
1 point
As a project manager, you have identified the stakeholders of your project. What should you do NEXT? *
1 point
During which project management process group are budget forecasts created? *
1 point
Your project is facing attrition of project resources, and you would like to document processes carefully to ensure business continuity. Certain costs have to be incurred for this purpose. These costs are known as: *
1 point
A project is seriously delayed. Earned value analysis shows that the project needs to be completed 10 percent faster than the work has been going. To get the project back on track, management wants to add 10 people to an activity currently assigned to one person. The project manager disagrees, noting that such an increase will not produce an increase in speed. This is an example of: *
1 point
Your project will go through many phases to produce a high-priced product that will be sold to the public. You are currently starting the design phase. The price will include the product and scheduled maintenance. The team includes representatives from the engineering department, who will help determine the design of the project, the marketing department, who will determine the shape of the container for the product of the project and the accounting department who will help make sure the cost of the project allows ample profit margin. The project charter has been completed and signed by sponsors from all these departments. The product scope was completed in an earlier project that was two months delayed due to arguing over the scope. The team is now functioning well and past team building efforts have produced an effective team for this new project. Which of the following is the BEST thing to include that has not been included in planning? *
1 point
You are the project manager of a new project, tasked with construction of a bridge on the River Nile in Egypt. While initiating the project, you should: *
1 point
A ranking of risks and a list of risks for additional analysis are outputs of which process of risk management? *
1 point
You are a project manager. At the executing stage of the project, all the following statements are correct EXCEPT: *
1 point
A market demand, a business need and a legal need are ALL: *
1 point
The project manager has performed schedule network analysis, compressed the schedule, and completed a Monte Carlo analysis. What time management activity should be done NEXT? *
1 point
Product acceptance criteria should be laid down in which document? *
1 point
During project executing, a large number of changes are made to the project. The project manager should: *
1 point
The project is calculated to be completed four days after the desired completion date. You do not have access to additional resources. The project is low risk, the benefit cost ratio (BCR) is expected to be 1.6, and the dependencies are preferential. Under these circumstances, what would be the BEST thing to do? *
1 point
Which statement describes best the meaning of Leadership? *
1 point
Project performance must be monitored and measured regularly to identify variances from the plan. All the following processes belong to monitoring and controlling EXCEPT: *
1 point
Once ground rules are established and communicated to the project team, the responsibility of enforcing these rules lies with the: *
1 point
What does a staffing management plan describe? *
1 point
Being the project manager in a high risk electronics project with a lot of new technologies, you developed a Risk management plan and identified risks which you documented in a Risk register. Then, the risks were analyzed and response planned. It is getting obvious during Risk monitoring and control meetings: The documents which you created are not very helpful. What have you probably done wrong? *
1 point
A project has seven activities: A, B, C, D, E, F, and G. Activities A, B, and D can start anytime. Activity A takes 3 weeks, Activity B takes 5 weeks, and Activity D takes 11 weeks. Activities A and B must be completed before Activity C can start. Activity C requires 6 weeks to complete. Activities B, C, and D must be completed before Activity E can start. Activity E requires 2 weeks. Activity F takes 4 weeks and can start as soon as Activity C is completed. Activity E must be completed before Activity G starts. Activity G requires 3 weeks. Activities F and G must be completed for the project to be completed. Which activities have float available? *
1 point
You would like to provide incentives to seller in the contract to: *
1 point
A project manager has been overwhelmed with problems on his project. He would like to identify the root cause of the problems in order to determine where to focus his attention. Which of the following tools would be BEST for the project manager to use? *
1 point
Which of the following is a TRUE statement about a risk rating matrix? *
1 point
You are the project manager of a high priority project, which will require more than 1,000 team members. During human resource planning, you would like to apply proven principles to shorten the time needed to create a human resource plan and make it effective. In this context, you will benefit if you consult an expert in the field of: *
1 point
In your company, you have a practice of preparing your own estimates of the items to be procured or services to be availed. This helps you conduct procurements to select seller. This can also be referred to as: *
1 point
At what stage of the project are factors like probability of successfully completing the project, cost of changes, cost of error correction, etc., the highest: *
1 point
Which of the following is NOT part of the quality management plan? *
1 point
After a status meeting, one of your team members, John, pulls you aside and tells you that he was insulted by a comment from another team member. He felt that the comment was racist. You meet with the team member who made the comment, Suzanne, but she says that the other team member's performance has been very poor. She has never made a comment like this before at the company. You review the records, and see that she is correct – he has consistently delivered lower quality work than any other team member. What is the BEST way to handle this situation? *
1 point
Keith, the project manager of a large publishing project, sends an invoice to his client. Which communication type is he using? *
1 point
This is the process of identifying quality requirements and/or standards for the project and product, and documenting how the project will demonstrate compliance. *
1 point
You are managing a project where you work with 7 other team members and two sponsors. How many lines of communications are there between stakeholders on this project? *
1 point
The project manager is in the process of staffing the project. Available resources are as follows: Mary always works overtime. Whitney works very hard. Laurie meets the project requirements. Jess is very enthusiastic about the project and will work overtime if necessary. Who is the MOST appropriate resource for this project? *
1 point
In your project, you have established tools to ensure that appropriate information is available to project stakeholders in a timely manner. In this context, if there is a conversation taking place using a sender-receiver model, which of the following statements is NOT correct: *
1 point
Risk tolerances are determined in order to help: *
1 point
In which of the following contract types does the seller have the most cost risk? *
1 point
At the beginning of a project, a software team project manager is given a schedule with everyone's vacations on it. She realizes that because the software will be delivered to the QA team exactly when they have overlapping vacations, there is a serious risk of quality problems because there won't be anyone to test the software before it goes into production. What BEST describes the constraint this places on the project? *
1 point
Evaluating overall project performance regularly is part of: *
1 point
In your project, you create project documents which will help you when managing the project. Which of the following is NOT an example of project documents? *
1 point
A new store development project requires the purchase of various equipment, machinery, and furniture. The department responsible for the development recently centralized its external purchasing process and standardized its new order system. In which document can these new procedures be found? *
1 point
It is the middle of the project when the project manager is informed by her scheduler that the project control limits are secure. That same morning she receives a note from a team member about a problem he is having. The note says, "This activity is driving me crazy and the manager of the accounting department won't help me until the activity's float is in jeopardy." In addition, the project manager has e-mails from a minor stakeholder and 14 e-mails from team members. While she is reading the e-mails, a team member walks in to the project manager's office to tell her a corrective action was implemented by a team member from the project management office, but was not documented. What should the project manager do NEXT? *
1 point
You are working for a semi-conductor company. There have been several instances in the past week when a few circuits have not been giving accurate results. You have been assigned the task of determining the probable cause for the variations. Which tool would you use? *
1 point
You have eight people in your project, and one more person will be joining next week. Once the new person joins, the number of communication channels will increase by: *
1 point
You have acquired a team and assigned tasks for the selected team members of your project. This activity is performed during: *
1 point
You are managing a project laying underwater fiber optic cable. The total cost of the project is $52/meter to lay 4 km of cable across a lake. It's scheduled to take 8 weeks to complete, with an equal amount of cable laid in each week. It's currently week 5, and your team has laid 1,800 meters of cable so far. What is the SPI of your project? *
1 point
Total float is the amount of time an activity can be delayed without delaying the: *
1 point
Your organization has to follow some guidelines and policies while recruiting people. From your project perspective, these guidelines and policies will be classified as: *
1 point
During Identify Stakeholder process, the project manager identifies all people or organizations impacted by the project, and documents relevant information regarding their interests, involvement, and impact on project success. In this context, all the following statements are true EXCEPT: *
1 point
A project manager receives a deliverable from one of the team members to provide to the customer. While looking at the deliverable, the project manager notices that the document is smaller than what he expected and does not contain what he thought it should. The project manager should FIRST: *
1 point
The project you are working on has an increase in cost effectiveness, increased productivity, and increased morale. What might be the reason for these changes? *
1 point
For your project, find the to-complete performance index (TCPI) based on the given data: Budget at completion of the project = 700,000; Cost variance of the project = 25,000; Earned value of the project = 200,000; Estimate to Complete has now been revised to 425,000. *
1 point
A team member comes to you to tell you that there is a problem on her activity. It cannot be started on the day it is scheduled to start. A manager overhears this conversation and reports that the project will be late. Later the project manager completes his own report saying "the project is still scheduled to be completed on time." Which of the following could be the reason the project manager made such a statement? *
1 point
In the procurement, the buyer has required the seller to provide at least two PMP certified project managers on the team, in addition to meeting additional selection criteria. The buyer creates an evaluation team that will evaluate the seller' proposals using a system to minimize personal prejudice. Any major difference in the evaluations will be negotiated. The project is using which of the following proposal evaluation techniques? *
1 point
You are managing a project with AC = $25,100, ETC = $45,600, VAC = -$2,600, BAC = $90,000 and EAC = $92,100. Your sponsor asks you to forecast how much money you expect to spend on the remainder of the project. Which is the BEST estimate to use for this forecast? *
1 point
A project team member is talking to another team member and complaining that many people are asking him to do things. If he works in a functional organization, who has the power to give direction to the team member? *
1 point
A project manager wants to make sure his plans for meeting the training needs of resources, and plans for releasing resources are complete. All of the following are inputs to this activity EXCEPT: *
1 point
If AC (ACWP) is greater than your EV (BCWP), what does this mean? *
1 point
Your company has a projectized organization structure. As your project nears completion, you notice that your team members are more interested in trying to find new positions rather than properly discharging their duties. Their motivation is: *
1 point
Which statement is FALSE? Progressive elaboration of project scope… *
1 point
A non-governmental agency authorizes a project to provide potable water systems, latrines, and sanitation education to low-income communities. The need for the project arose due to: *
1 point
A team member who does not have the required skills or knowledge was assigned to a team. Who is responsible for ensuring that he receives the proper training? *
1 point
In which document will you find the code of account identifier, description of work, responsible organization, and list of schedule milestones? *
1 point
Please refer to the diagram (all units are in days). What is the project float if management wants to complete this project within 13 days? *
1 point
Captionless Image
A project manager is having trouble securing programmers for her project. Every time she asks the programming manager for resources for her project, he says they're all assigned to other work. So she is constantly having to go over his head to overrule him. Which type of organization is she working for? *
1 point
As a project manager you can assign any one of two team members to a highly coveted task. Both are equally capable, but one of them is a member of your in-group. To the other one, you have far more distance. How should you behave? *
1 point
At the beginning of Project execution, you notice different opinions between team members relating to project work and deliverables and to the level of overall complexity. What should you do right now? *
1 point
Which motivational theory says that what motivates people is the work itself, including such things as responsibility, self-actualization, and professional growth? *
1 point
Which of the following would be the MOST appropriate thing to do during the planning process group? *
1 point
You have recently appointed a project manager to handle a critical project in your organization. You want to give her the authority to apply organizational resources to project activities. Which document should you use? *
1 point
Submit
Clear form