The customer requests a change to the project that would increase the project risk. Which of the following should you do before all the others? *
1 point
Which of the following factors is NOT considered to be a project constraint? *
1 point
The customer communicates a request for a change in your project plan. What should be your first step towards addressing the change request? *
1 point
The project manager notices that project activities being completed by one department are all taking slightly longer than planned. To date, none of the activities/work packages have been on the critical path, nor have they affected the critical chain planning that has occurred. The project manager is bothered by the problem, since four of the next five critical path activities are being completed by this department. After making three calls, the project manager is finally able to converse with the department manager to determine what is going on. The conversation is slow, because both speak different native languages and they are trying to converse in French, a shared language. To make communication easier, the project manager frequently asks the department manager to repeat back what has been said. The department manager communicates that his staff is following a company policy that requires two levels of testing. During the conversation, the department manager also makes a comment that leads the project manager to believe that the policy may include excessive work. This is the fourth time the project manager has heard such a comment. What is the BEST thing to do? *
1 point
A seller submits an invoice that is outside the funding limit reconciliation completed during project planning. What is the LEAST likely cause? *
1 point
Project Risk Management helps in maximizing the probability and impact of positive events, and minimizing the probability and impact of negative events in the project. In this context, Plan Risk Responses process: *
1 point
At the end of the closing process group, *
1 point
You are taken to lunch by one of your sellers who has become a friend. He gives you an opportunity to participate in a new venture in association with his company, unrelated to your current employment. What should you do? *
1 point
A notice sent to a sub-contractor about the contract is an example of which kind of communication? *
1 point
You are performing an audit of one of your project manager's projects and notice that she did not consider the network diagram as part of the Identify Risks process. As a result, the project manager will probably do which of the following? *
1 point
All of the following are outputs of the Close Project or Phase process EXCEPT: *
1 point
Which of the following is TRUE of inspections? *
1 point
In your project, you invest a lot of time in team development to increase the team's performance, which in turn increases the likelihood of meeting project objectives. Which of the following indicators will you NOT use to evaluate your team's effectiveness? *
1 point
Your company puts a new product into the marketplace without any reports of problems. However, your internal research indicates that there is a possibility of serious injuries that would cost US $20,000,000 to fix. What should you do? *
1 point
All of the following are inputs to the Determine Budget process EXCEPT: *
1 point
You are a project manager in a software organization. Your customer has decided to terminate the project as the need for the product does not exist anymore. As a project manager, what step would you take FIRST? *
1 point
In your new project, you have to provide a critical deliverable within five months and do not have time to go through the Conduct Procurements process. You decide to sign a contract with a supplier with whom your company has done some work in the past. The risk you are accepting in this situation is: *
1 point
Your company routinely gives out procurement contracts, and there is a dedicated procurement management division to handle this. Yet, it is observed that sometimes a few contracts had to be terminated. In this context, what could be the most common reason for such terminations? *
1 point
You are the project manager for a large installation project when you realize there are over 200 potential stakeholders on the project. Which of the following would be the BEST course of action for you to take? *
1 point
To resolve conflicts in your project, you can use all the following conflict resolution modes EXCEPT: *
1 point
A project has seven activities: A, B, C, D, E, F, and G. Activities A, B, and D can start anytime. Activity A takes 3 weeks, Activity B takes 5 weeks, and Activity D takes 11 weeks. Activities A and B must be completed before Activity C can start. Activity C requires 6 weeks to complete. Activities B, C, and D must be completed before Activity E can start. Activity E requires 2 weeks. Activity F takes 4 weeks and can start as soon as Activity C is completed. Activity E must be completed before Activity G starts. Activity G requires 3 weeks. Activities F and G must be completed for the project to be completed. What is the critical path? *
1 point
Which of the following describes the BEST use of historical records from previous projects? *
1 point
A problem occurs on an activity with free float and the project manager has extended its duration. What is MOST likely to be affected? *
1 point
You observe that two technical team members have been arguing constantly. You would like to ensure that personality clashes do not endanger your project. To resolve this issue, you should use: *
1 point
The project has been working through some difficult technical issues relating to how the work should be done. The most recent problem related to the way each test was to be completed. There have also been disagreements with two of the eight managers and the sponsor has had to intervene once. The testing work is done when the project manager discovers that one of the changes agreed to has not been adequately completed. What did the project manager NOT do? *
1 point
Your company focuses on increasing employee loyalty toward the company by providing a job for life with a strong focus on the well-being of the employees. The organization theory your company believes in is: *
1 point
Identifying alternative approaches is part of which scope management process? *
1 point
Which of the following is the BEST method to make reward systems MOST effective? *
1 point
The project manager and project sponsor are discussing the project costs and whether it is better to have their own company do part of the project or hire another company to do the work. If they asked for your opinion, you might say it would be better to do the work yourself if: *
1 point
The company has just announced that there will be a layoff in the next month, and there's a good chance it will include some of the people from your project team. The team is discussing the layoff to the exclusion of everything else. If you tell the team, "Let's calm down and get back to work, maybe our performance in the next month will help keep us from losing our jobs," which conflict resolution technique are you using? *
1 point
Scope decomposition involves subdividing the major project deliverables into smaller pieces to: *
1 point
You are managing the project when you discover an estimated completion date will occur after the desired date. What should you do FIRST? *
1 point
A seller has failed to make delivery on a major item for your project. What is likely to be the LEAST effective thing to do? *
1 point
When you look at a control chart that measures defects in the product produced by your project, you find that seven values are showing up below the mean on the chart. What should you do? *
1 point
A project manager for a large information technology consulting firm was assigned to manage a software integration project for a large client. The schedule was already established. Management at the client site responsible for the project explained to the project manager that the project duration was too long. Changing market pressures require the project to be brought in one month earlier than scheduled. He has already reviewed the scope of the project and nothing can be cut. He requested that the project manager cut each activity by 10 percent duration to accomplish the goal. What would be the MOST appropriate thing for the project manager to do in this situation? *
1 point
A dependency requiring that design be completed before manufacturing can start is an example of a: *
1 point
You are managing a project in a foreign country, where you realize you will have to pay a fee to some government agencies to get your work done. You should: *
1 point
In your project, you are coordinating people and resources as well as integrating and performing activities of the project in accordance with the project management plan. This is performed during: *
1 point
You are the project manager of a pharmaceutical company responsible for releasing a new drug in the market. While managing the project, you have created several documents (e.g., project management plan, risk registers, cost, schedule, and quality baselines). All these documents should be stored in: *
1 point
You want to perform active risk acceptance. What should you do? *
1 point
Developing alternative activity sequences is an example of: *
1 point
When control charts are being used, outliers are… *
1 point
From the project perspective, quality attributes: *
1 point
You are working on one of the first financial projects your company has attempted, and you have learned a lot about how to manage the project along the way. Your company is targeting financial companies for new projects next year. What's the BEST thing for you to do? *
1 point
During the execution of the project, a new ISO version of standard 9000 is issued and the project team is meeting with the quality department to determine how the standard will apply to the project. This is part of which quality process? *
1 point
Which of the following BEST describes the project manager's role regarding project changes? *
1 point
A project manager had a complex problem to solve and made a decision about what needed to be done. A few months later, the problem resurfaced. What did the project manager MOST likely not do? *
1 point
The ________ is a document which describes how the project management team will implement the performing organization's quality policy. *
1 point
In your project, you have conducted a communication requirements analysis to determine the total number of possible communication channels in the project. While conducting the analysis, you learn that the number of communication channels: *
1 point
You are the project manager of a car manufacturing company. You understand that there are costs associated with improvement in quality parameters. To justify costs required to improve quality, you find out the incremental increase in benefits for an incremental improvement in quality. This is an example of : *
1 point
Your boss has asked you for a cost baseline for the project, but it is early in the project management process and there is very little project information. In this circumstance, what is the BEST way to estimate this project? *
1 point
Tom is the project manager on a construction project. Midway through his project, he realizes that there's a problem with the lumber they've been using in a few rooms and they're going to have to tear down some of the work they've done and rebuild. One of his team members suggests that the defect isn't bad enough to cause all of that re-work. Tom says that he's worked on a project that made this same mistake before and they ended up having to redo the work when inspectors looked at the house. He convinces the team member that it's probably better to fix it now than later. What kind of power is he using to make the decision? *
1 point
The amount of funds available for a company to invest in projects is called: *
1 point
A stakeholder complains that the project did not increase the department's knowledge of Java programming and therefore, the project is not complete. The customer has accepted the project. The project manager determines that all stated requirements and deliverables have been met. He does not find evidence that Java programming was a requirement. A review of project correspondence shows no mention of the deliverable. The project manager should: *
1 point
You recently went on an official trip to another country to discuss a business proposition with a potential vendor. The vendor took you out for lunch and offered you gifts, as it is customary in that country. You must: *
1 point
Which of the following is the BEST thing to do when a project activity will take longer than planned and the project can no longer be completed on time? *
1 point
A project manager for the seller is told by her management that the project should do whatever possible to be awarded incentive money. The primary objective of incentive clauses in a contract is to: *
1 point
As a project manager, you are responsible for managing changes to the project scope. If, at the end of the project, a customer wants a major change in the scope of work, you should: *
1 point
Which of the following statements relating to product-oriented processes and project management processes is accurate? *
1 point
Important aspects of a product include the ongoing operations and maintenance. Which of the following BEST describes how operations and maintenance activities impact a project? *
1 point
Which of the following BEST describes when additional risk responses are documented? *
1 point
You are the project manager for a new project, and you want to save time creating the WBS. Which is the BEST way to do this? *
1 point
The client demands changes to the product specification that will add only two weeks to the critical path. Which of the following is the BEST thing for the project manager to do? *
1 point
Together with your team, you applied three-point estimation on a Critical path which consists of two activities. The following duration uncertainties are all calculated assuming a ±3sigma Confidence interval. The duration uncertainty—defined as pessimistic minus optimistic estimate—of the first activity is 18 days; the second estimate has an uncertainty of 24 days. Applying the PERT formula for paths, what is the duration uncertainty of the entire path? *
1 point
Which parts of the risk management process do not generally use organizational process assets as an input? *
1 point
A project manager has received activity duration estimates from his team. Which of the following does he need in order to complete the Develop Schedule process? *
1 point
All the following are components of cost management EXCEPT: *
1 point
Which project will be selected from the following options? *
1 point
During project planning in a matrix organization, the project manager determines that additional human resources are needed. From whom would he request these resources? *
1 point
What risk management process MOST affects the project management plan? *
1 point
You are the project manager of a construction company planning to build a water treatment plant close to a residential locality. The project owner and sponsor have obtained all the legal clearances for the project. Some of the residents of the locality have approached you with concerns on the probable impact of the project on the environment. In this case, you must: *
1 point
A project manager and her team worked together to develop a work breakdown structure. However, it seems project team members are doing work that is not included in the work breakdown structure. The purpose of a work breakdown structure is to: *
1 point
All of the following are used in estimating EXCEPT: *
1 point
You are a project manager for a $ 50 million project that is highly complex and involves more than 100 people. To successfully execute the project, you decide to break it down into smaller manageable units. Which of the following processes will you use? *
1 point
You are working on implementing your communication plan during project execution. Some of the things you can do to enhance team buy-in and cohesion include: *
1 point
A discussion came up during a meeting: To which degree does your project have to be compliant to the processes enumerated in the PMBOK ® Guide. What should be the guiding principle to answer this question? *
1 point
The concepts of "Zero Defects" and "Right First Time" were formulated by: *
1 point
A project manager knows that she can delay the start of certain activities within the project schedule to coincide with the mitigation of a known risk. She knows exactly the work and duration needed, should the risk event occur. She is confident that the finish date will not be impacted by the time delay. Which of the following aspects of schedule development has the project manager used in this situation? *
1 point
You are part of a team that has been told by your management that they require you to take and pass the PMP exam by the end of the year. After studying, you are the first of the group to take the actual exam. When you return to work to tell everyone you passed, you are bombarded with questions. Management tells you that since everyone else is so worried about the exam, they want you to write out all the questions you can remember from the exam and provide copies to the rest of the team. In this situation, you could do all of the following EXCEPT: *
1 point
Which of the following is NOT typically found in a project charter? *
1 point
What might historical records from previous projects used as an input to the Define Activities process include? *
1 point
During execution of a project which is performed for a customer on a T&M (Time and Material) contract base, a new project manager is taking over the assignment. He discovers that two members assigned to the project have charged time without performing any work for the project customer. Upon further investigation, he determines that this occurred because there have been no other project assignments open for these employees. The customer is unaware of these facts. What should the project manager do? *
1 point
What is the purpose of a Project charter? *
1 point
Which of the following is not a tool or technique of the Perform Quality Control process? *
1 point
You recently took over the responsibilities of a project manager from another person. While reviewing the project cost, you realize there has been an item of $ 100,000 waiting to be paid, which, you think, is a disputed item. Your project CPI is 1.2. In this case: *
1 point
If project A has a net present value (NPV) of US $30,000 and project B has an NPV of US $50,000, what is the opportunity cost if project B is selected? *
1 point
What does a benefit cost ratio (BCR) of 2.1 mean? *
1 point
Which of the following needs to be completed before resources can be finalized for the project? *
1 point
Which of the following is generally the MOST CORRECT use of a project network diagram? *
1 point
A particular stakeholder has a reputation for making many changes on projects. What is the BEST approach a project manager can take at the beginning of the project to manage this situation? *
1 point
In which project management process group is the project manager likely to do more directing? *
1 point
Your company primarily uses benefits cost ratio as a project selection criterion. All the following statements related to benefit cost ratio (BCR) are correct EXCEPT: *
1 point
During the first half of the project, five team members left for other projects without being replaced, two team members went on vacation without informing you, and other team members expressed uncertainty about the work they were to complete. In this situation, it is BEST if you create a __________ for the second half of the project? *
1 point
In your project, a team member suggested the addition of a functionality, which she thinks, will improve customer satisfaction. Your approach would be to: *
1 point
A project customer and a contractor agreed on regular Quality audits during execution by a third party audit team, which is working on an assignment for the customer. What should the contractor have prepared for the audits? *
1 point
As a project manager, which one of the following will you undertake in the Monitoring and Controlling process of your project? *
1 point
Your business partner is ready to invest $ 110,000 in your company one year from now. The interest rate used in your company to calculate Present Value (PV) of expected yearly benefits and costs is 10%. What is the PV of this investment? *
1 point
The seller tells you that your activities have resulted in an increase in their costs. You should: *
1 point
In your project, you wish to estimate the type and quantities of resources required for each activity. For this purpose, which of the following techniques will you use? *
1 point
Determining and delivering the required levels of quality for the project is the responsibility of: *