PRINCE2® Practitioner Practice Quiz - 3
Sign in to Google
to save your progress.
Learn more
* Indicates required question
In which of the following decisions is the Project Board NOT involved?
*
1 point
Authorizing a work package
Authorizing project closure
Authorizing initiation
Authorizing a stage
Which of the following represents an output?
*
1 point
New accounting procedures
Staffing costs reduced by 20%
Sales invoices processed 30% faster
£30k cost savings
The incorporation of the primary stakeholders on the project management team supports what principle?
*
1 point
Continued business justification
Defined roles and responsibilities
Manage by stages
Learn from experience
Which is a purpose of the Closing a Project process?
*
1 point
Define the procedure for handing over products
Provide a fixed point at which acceptance for the project product is confirmed
Define formal requirements for the acceptance, execution and delivery of project work
Confirm all project benefits have been achieved
Which of the following is NOT a benefit of adopting the PRINCE method
*
1 point
It can be applied to any type of project
It promotes learning and continuous improvement in organisations
It embodies established and proven best practice and governance for project management
It provides a framework to apportion blame when things go wrong
Controlling a Stage handles what part of the project?
*
1 point
Directing a Project
The implementation of Work Packages
Day to day management of the project
The closing of one stage and the planning of the next
Which of the following products are part of the Project Initiation documentation?. (1) Quality Management Strategy. (2) Project Plan. (3) Outline Business Case. (4) Communication Management Strategy
*
1 point
1, 2
2, 3
1, 3, 4
1, 2, 4
Starting Up a project is triggered by which of the following?
*
1 point
Legislation
Corporate Strategy
Risks
Mandate
Identify the missing words in the following sentence. If the Project Manager needs to know the results of a quality review, the [ ? ] will provide a summary together with the date of any follow-up meeting.
*
1 point
Stage Plan
Issue Register
Daily Log
Quality Register
Which of the following statements describes an outcome?
*
1 point
Any of the projects specialist products
A result of the change derived from using the project’s products
A measurable improvement resulting from a change
Something perceived as advantages by a stakeholder
During a Quality Review it is the responsibility of which role to request approval for the product?
*
1 point
Presenter
Chair
Reviewer
Administrator
Which is a recommended quality review team role?
*
1 point
Project Manager
Presenter
Project Support
Producer
Which is a purpose of the Change theme?
*
1 point
Prevent change to anything agreed in the Project Initiation Documentation
Ensure any potential changes to baselined products are controlled
Assess and control uncertainty
Assess changes to only the specialist products
What is the first task in Product-Based Planning?
*
1 point
Creating a Product Breakdown Structure
Creating a Product Checklist
Creating a Product Description for the final product
Creating a Product Flow Diagram
Which of the following are optional when calculating the budget?. (1) Costs of Project Management activities. (2) Risk Budget. (3) Change Budget. (4) Cost Tolerances
*
1 point
1, 2
1, 4
2, 3
3, 4
Which is a definition of risk probability?
*
1 point
Scale of the risk should it occur
Probable effect on the project delivering its objectives
Probable timeframe within which the risk may occur
A measure of the likelihood of the risk occurring
What plan identifies quality responsibilities for the project?
*
1 point
Project Plan
Project Quality Plan
Stage Quality Plan
Team Plan
Which other management product is created when the Business case is updated during Initiating a Project?
*
1 point
Post project review plan
Risk Register
Benefits Review plan
Issue Register
When Assessing a risk, which of the following estimates the result of a particular threat or opportunity actually occurring?
*
1 point
Probability
Proximity
Impact
Outcome
What should be reviewed as part of preparing a Work Package?
*
1 point
Project Board authorisation to proceed
The appropriate Product Descriptions
The Issue Log
Timesheets
Identify the missing words in the following sentence. PRINCE2 management stages relate to the [ ? ], which is a factor that differentiates them from technical stages
*
1 point
use of a particular set of technical skills
use of a specific set of Team Managers
authorization from corporate or programme management
commitment of resources
If a product were to be changed, in which order would the following occur? 1) A Work Package is created or amended; 2) The Project Board approve the change; 3) Raise a Project Issue; 4) A new version of the product is created
*
1 point
1, 2, 4, 3
2, 3, 4, 1
3, 1, 2, 4
3, 2, 4, 1
Which statement correctly describes the relationship between Project Assurance and quality assurance?
*
1 point
Project Assurance provides assurance to the project's stakeholders whereas quality assurance provides assurance to the wider corporate or programme organization
They are both the responsibility of the Project Board, but Project Assurance may be delegated.
They are both independent of the project
Project Assurance and quality assurance are both the responsibility of corporate or programme management
Which is NOT a responsibility of the Project Board?
*
1 point
Allocate tolerances to specialist teams
Transfer ownership of the Benefits Review Plan to corporate or programme management
Approve the Project Product Description
Confirm the required frequency of Highlight Reports
When is it confirmed if a project's objectives have been achieved?
*
1 point
During the Closing a Project process
During the final end stage assessment
During the Controlling a Stage process
During the Managing Product Delivery process
In what process is the Business Case refined and incorporated as part of the Project Initiation Documentation?
*
1 point
Controlling a Stage
Managing a Stage Boundary
Starting up a Project
Initiating a Project
Which of the following is NOT true for a PRINCE2 Plan?
*
1 point
It describes how a specific target is to be achieved.
It includes timescales and benefits for the defined targets.
It contains sufficient information to confirm the targets are achievable.
It includes named resources responsible for achieving the target.
Which is NOT a purpose of configuration management?
*
1 point
To identify products
To create products
To track products
To protect products
The principle of Learning from Experience dictates that everybody involved with the project should examine any lessons earned …. (1) … when starting a project. (2) … as the project is in progress. (3) … when closing a project. (4) … after the project has closed.
*
1 point
1, 3
1, 2, 3
1, 3, 4
4
Stage Plans need to be approved by whom?
*
1 point
Corporate/Programme Management
Project Board
Project Manager
Team Manager
Defining the stages of a project is fundamentally a process of balancing a number of parameters. Which one of the following is NOT one of the parameters?
*
1 point
How far ahead in the project it is sensible to plan
The availability of the project board for progress meetings
Too many small stages versus too few big ones
Where the key decision points need to be on the project
When is the Project Manager permitted to deviate from a Stage Plan without immediately having to report it?
*
1 point
When the deviation is within the tolerance levels set by corporate / programme management for the project.
When the deviation is only slightly beyond the tolerances set for the stage.
When the deviation is within the maximum and minimum tolerance levels set for the stage.
When the deviation is beyond minimum tolerance on cost and time for the stage.
In a PRINCE2 project, who authorises Work Packages?
*
1 point
The Executive
Project Assurance
The Team Manager
The Project Manager
Within what process are Team Plans produced?
*
1 point
Initiating a Project
Controlling a Stage
Managing a Stage Boundary
Managing Product Delivery
Which of the following is NOT a PRINCE2 management product?
*
1 point
Risk Management Strategy
Configuration Management Strategy
Communication Management Strategy
Cost Management Strategy
Which is an objective of the quality review technique?
*
1 point
Involve key interested parties to promote wider acceptance of the product
Develop and improve the specification of a product through continuous assessment
Agree any changes required to the baselined product
Update the status information in the Configuration Item Record when a product is signed-off
Which statement best explains the purpose of Tailor to suit the project environment?
*
1 point
Ensure project controls are based on project’s scale, complexity, repentance, capably and risk
To use a set of pre-defined templates for the size of project
To tailor the use of the principles to suit the project
To pick which PRTNCE2 processes to apply and which to leave out
In which of these processes is the Business Case updated?
*
1 point
Controlling a Stage
Directing a Project
Initiating a Project
Managing Product Delivery
What process enables an organization to understand the work that needs to be done to deliver a project's products before it is approved?
*
1 point
Directing a Project
Initiating a Project
Starting up a Project
Controlling a Stage
Which Role is responsible for undertaking the activities within the Managing Product Delivery Process?
*
1 point
Project Manager
Project Board
Team Manager
Project Assurance
Which of the following represents the four key characteristics a good Project board should display?
*
1 point
Authority, Credulity, Ointment, Availability
Authority, Credibility, Delegation, Availability
Authority, Availability, Connections, Delegation
Authority, Crudity, Connections, Delegation
Which 3 products are created once the authority to initiate the project has been received?
*
1 point
Risk Management Strategy, Quality Management Strategy, Communication Management Strategy
Project Plan, Configuration Management Strategy, Quality Management Strategy
Project Plan, Risk Management Strategy, Quality Management Strategy
Risk Management Strategy, Quality Management Strategy, Configuration Management Strategy
Which of the following is NOT a characteristic of a successful project organization?
*
1 point
Should have business, user, supplier and stakeholder representation
Should have reviews of project roles throughout the project to ensure they continue to be effective
Should have a system in place to protect the project from any request for change raised by external stakeholders
Should have a effective strategy to manage communication flows to and from key external stakeholders
What is the first task in Starting up a Project?
*
1 point
Appoint the Executive and the Project Manager
Authorize the Project
Plan the initiation stage
Design and appoint the Project Management Team
What theme provides information on what is required, how it will be achieved and by whom?
*
1 point
Organization
Plans
Business Case
Quality
How does the Business Case theme support the continued business justification principle?
*
1 point
Allows projects not delivering direct benefits to proceed without a Business Case
Removes the need for a separate Business Case where a project is part of a programme
Mandates that even the simplest of projects should have a Business Case
Ensures a new Business Case is created at the end of each stage to confirm the viability of the next stage
In PRINCE2 what product is used to define the information that justifies the setting up, continuation or termination of the project?
*
1 point
Project Initiation Document
Business Case
End Stage Approval
Project Brief
Which is one of the six aspects of project performance that needs to be managed?
*
1 point
Accuracy
Reliability
Scope
Ease of use
Which is a type of issue?
*
1 point
Problem/concern
Follow-on action recommendation
Exception Report
Identified threat
Which is NOT a factor to consider when defining management stages?
*
1 point
How long the project is
When Team Managers are available
When key decisions are required on the project
The amount of risk within the project
The Project Board has four responsibilities towards the management of risk. Which of the following options is the FALSE one?
*
1 point
Identifying, recording and regularly reviewing risks
Making decisions on recommended reactions to risk
Notifying the Project Manager of any external risk exposure to the project
Striking a balance between levels of risk and potential benefits
During a work package the Team manager needs to keep the project manager informed, which management product is used for this?
*
1 point
Highlight report
Checkpoint Report
Issue Report
End Stage Report
A member of the Project Board should …. (1) … be approved by Corporate or Programme Management. (2) … have authority. (3) … have credibility. (4) … be available
*
1 point
1, 2, 3, 4
1, 2, 3
1, 3, 4
2, 3, 4
Which is a purpose of the Organization theme?
*
1 point
Set the tolerance on the cost of resources
Provide project management training to those working within the project
Define the structure of accountability and responsibilities on the project
Implement the controls required to permit management by exception
What process is used to provide an interface with corporate or programme management?
*
1 point
Managing Product Delivery
Directing a Project
Controlling a Stage
Managing a Stage Boundary
Which of the following is NOT a PRINCE2 definition of a project?
*
1 point
Has an organisation structure
Produces defined and measurable business products
Uses a defined amount of resources
Uses a defined set of techniques
According the Prince2 principles, the scope of a plan is defined by …
*
1 point
… the expected benefits.
… the quality requirements.
… the target completion dates.
… the set of products to be delivered.
Which is NOT a purpose of a Product Description?
*
1 point
Define the time and cost needed to produce the product
Define the quality skills required to check the product
Define the function and appearance of the product
Define the development skills required to produce the product
Which of the following statements is TRUE with regard to expected benefits?
*
1 point
They cannot be assented
They don’t need to follow corporate objectives
They should be measured
Tolerances cannot be set against expected benefits
Which PRINCE2 technique helps to ensure that all personnel affected by a product have the same understanding of the product's purpose?
*
1 point
Change Control
Configuration Management
Product-Based Planning
Quality Review
Which of these statements is FALSE?
*
1 point
The Project Plan is an overview of the total project.
For each stage identified in the Project Plan, a Stage Plan is required.
An Exception Plan needs the approval of the next higher level of authority.
A Team Plan needs approval by the Project Board.
Identify the missing word in the following sentence: "A PRINCE2 project is planned, monitored and ? on a stage-by-stage basis".
*
1 point
directed
controlled
justified
executed
Which process is the Quality Register created?
*
1 point
Initiating a Project
Managing Product Delivery
Controlling a Stage
Starting Up a project
Which of these is mandatory in a PRINCE2 project?
*
1 point
The use of Team Managers
The use of Exception Plans
The use of Stages
The use of Product Checklists
Submit
Clear form
This content is neither created nor endorsed by Google. -
Terms of Service
-
Privacy Policy
Does this form look suspicious?
Report
Forms
Help and feedback
Help Forms improve
Report