In order to be prepared for the Site Review meeting, the following general steps must be completed in advance. B Lab will send you detailed steps of the process as you go:
Week 1. Complete the BIA.
Week 2. Provide preliminary documentation for initial evaluation.
Week 3-4. Upload Site Review supporting documentation
Week 5. Schedule the Site Review Meeting.
Week 6. Participate in the Site Review Meeting.
Week 7. Complete any follow ups requested after Site Review Meeting.
Week 8. Review the Site Review Report as provided by B Lab.
Week 9. Review Outcomes of the Site Review.
See the diagram for the Site Review Period here.
https://drive.google.com/open?id=1AwbBUoqo1QsKhvDAqCZx9EAE5MH-9rol