To help the project team function more efficiently on complex and interrelated activities, the project manager decides to use a war room. What does this mean? *
1 point
A team has just gathered information and requirements for a new project that will be completed by an external company. If the project manager is just starting the procurement process, which one of the following should be done LAST? *
1 point
You are a project manager of a construction project that is financially challenged and behind schedule. A foreman fails to deliver a deliverable of the project on time as promised. You need to address the issue with the foreman. How should you approach the foreman? *
1 point
Which is NOT an input to the Create WBS process? *
1 point
Project A has had ineffective project meetings since its inception. There have been complaints that information does not get to the right people, some people are talking too much during meetings, and the right people are not there to resolve issues. What is MOST likely missing from this project? *
1 point
During which risk management process is a determination to transfer a risk made? *
1 point
As the project manager in a software company, you are determining the possible costs to complete project activities. This is done as part of: *
1 point
As a project manager, you use work authorization system to assign and allocate work to your team members. In this context, the primary purpose of the work authorization system is to: *
1 point
Your company manufactures car batteries. A research team discovers that there is a manufacturing flaw in the batteries, 25,000 of which are already sold. This flaw can cause fatal accidents, although no such accidents have been reported yet. Recalling all the batteries sold would cost the company as much as $ 25 million. What first step is your company going to take on this issue? *
1 point
You are about to take over a project from another project manager and find out the following information about the project. Activity Z has an early start (ES) of day 15 and a late start (LS) of day 20. Activity Z is a difficult activity. Cost performance index (CPI) is 1.1, schedule performance index (SPI) is 0.8. There are 11 stakeholders on the project. Based on this information, which of the following would you be the MOST concerned about? *
1 point
Perform Quality Assurance, Acquire Project Team, and Distribute Information are all parts of which process group? *
1 point
You are the project manager of a very critical project, which will impact the lives of several people in your community. To ensure the success of your project, you try to circulate accurate and truthful communication to the public through advertisements and statements published in newspapers. This demonstrates that you are good at: *
1 point
What is the BEST technique to ensure the project work is really complete? *
1 point
You are the project manager in a company, which has a balanced matrix organizational structure. Who do you report to? *
1 point
As a project manager, you estimate that, in your project, there is: 50% probability of earning $ 40,000 profit; 50% probability of incurring $ 25,000 loss; What is the expected profit/loss for the project? *
1 point
Employees who believe their efforts will lead to effective performance and expect to be rewarded for their accomplishments remain productive as rewards meet their expectations. This is called: *
1 point
In most jurisdictions, a legally required order of formal statements establishing a contract is: *
1 point
You have accepted a position at a company where you will manage a group of projects in a coordinated way. This organization specifically hired you to start a project management office to help it develop a more structured approach to project management. What should you do FIRST? *
1 point
A project manager on an industrial design project finds that the sponsor wants to make a change to the scope after it has been added to the baseline, and needs to know the procedure for managing changes. What is the BEST place to look for this information? *
1 point
Which of these is not an input to Develop Project Charter? *
1 point
Your project has two hundred and fifty people from five different countries working to create a software solution to be deployed across fifteen countries. Managing your virtual team is a challenge compared to managing a collocated project. In order to manage the virtual team, you should spend more time working on enhancing your: *
1 point
Which of the following is a benefit of an analogous project estimate? *
1 point
An output of Plan Procurements, the procurement documents are an input to all of the following EXCEPT: *
1 point
You identified a technical risk in your project and assigned a contingency for that. Planning contingency reserves is part of which risk response strategy? *
1 point
A review to determine whether of project activities comply with organizational and project policies, processes, and procedures is commonly called *
1 point
_______ are not necessarily used to establish the Cost baseline of a project. *
1 point
Your company's quality assurance department has performed a quality audit on your project. They have found that your team has implemented something inefficiently, and that could lead to defects. What's the NEXT thing that should happen on your project? *
1 point
You are managing the tools/spare parts section for an aircraft manufacturing company. Your team members have discovered some defective tools/spare parts. The probable cause for these could be materials used, defective measurement systems, inaccurate tolerances in the machines, or other factors. To determine what caused the defect, you will: *
1 point
After performing quality control using checklists, the completed checklists should become part of the: *
1 point
Which of the following is NOT a characteristic of a project? *
1 point
All of the following are advantages of GERT (graphical evaluation and review techniques) as compared to PERT (project evaluation and review technique) EXCEPT: *
1 point
During Monitoring and Controlling phase of your project, you conduct regular meetings with your team to identify new risks, reassess current risks and close outdated risks. This is done through: *
1 point
When a project manager is engaged in negotiations, nonverbal communication skills are of: *
1 point
Which of the following MUST be an agenda item at all team meetings? *
1 point
You have designed an improved system for a consumer product that could decrease repair cost for the consumer. Management is impressed with your idea, but has decided to wait until next year to implement it. What is the BEST thing to do? *
1 point
You are trying to determine the cost and schedule trade-off, which will be most appropriate for determining the ride quality of a car. You classify factors like tire pressure, suspension, height of vehicle, etc., which have to be optimized to improve ride quality. A tool you can use to facilitate making the decision is: *
1 point
All of the following are tools of the Determine Budget process EXCEPT: *
1 point
If a data point falls outside the upper control limit of a control chart the process is said to be: *
1 point
You're planning the schedule for a highway construction project, but the final date you came up with will run into the next budget year. The state comes up with capital from a reserve fund, and now you can increase the budget for your resources. What's the BEST way to compress the schedule? *
1 point
Critical chain is a schedule network analysis technique that modifies the project schedule to account for limited resources. In this context, the non-work schedule activities that are added in the critical chain method to manage uncertainty are referred to as: *
1 point
A project sponsor requested Earned Value Data on two concurrent projects from the project managers. Both projects are regarded as equally important and strategically beneficial and have been finished by over 80%. He received the following information:Project A: PV: $1,800,000 EV: $2,300,000 AC: $2,100,000; Project B: PV: $2,000,000 EV: $1,500,000 AC: $1,600,000. The sponsor considers to shift some resources from Project A to Project B to speed up the second project which is currently behind schedule. What is the most likely outcome of such a measure? *
1 point
Who issues the project charter? *
1 point
All of the following are required to bring a project to closure EXCEPT: *
1 point
What's the main output of the Risk Management processes? *
1 point
Effective project integration usually requires an emphasis on: *
1 point
You are the project manager of a software company developing a new banking software product. You would like to obtain information from various experts about the risks associated with your project. You decide to use the Delphi technique because this keeps any one person from having undue influence on the outcome of the Identify Risks process. The Delphi technique also has the added advantage that it: *
1 point
You are monitoring the technical performance of your website. Past data on the number of users and their experience helps you forecast how your website would perform if the number of users increases in the future. This is an example of: *
1 point
Inputs to the Report Performance process include all of the following EXCEPT: *
1 point
Which of the following tools is not used in Administer Procurements process? *
1 point
A team member comes to you (the project manager) privately and informs you that an employee of your customer is making unwelcome advances. The team member has repeatedly requested that this person stop, but the advances continue. What is the BEST course of action? *
1 point
All the following are valid inputs for "Identify Stakeholder" process EXCEPT: *
1 point
You are assigned as a project manager to lead a new quality improvement project. Management is asking for a project management plan. Which of the following should you create FIRST? *
1 point
Senior management asks the project manager how the project would be affected if two resources were removed from the project. To calculate a response, the project manager should complete: *
1 point
Which of the following is an output of the Collect Requirements process? *
1 point
Seven nonrandom data points that are still within the upper and lower control limit of a control chart are: *
1 point
Which of the following sequences represents straight line depreciation? *
1 point
During the Identify Risks process, a project manager identifies a risk that, no matter what the company does, a fire could occur in the building during the testing. It would be BEST to ______ the risk. *
1 point
A review of your project team member's most recent performance reports shows a major drop in output. Which is the best approach to raise team productivity in a project? *
1 point
A watchlist is an output of which risk management process? *
1 point
A manufacturing project has a schedule performance index (SPI) of 0.89 and a cost performance index (CPI) of 0.91. Generally, what is the BEST explanation for why this occurred? *
1 point
Which of the following BEST describes the main purpose of the project charter? *
1 point
A project team is having difficulty communicating over long distances. There are 13 team members from two countries when five people from India are added to the project. How many communication channels are there? *
1 point
While doing monitoring and controlling for your project, you notice that the cost variance is negative, but schedule variance is positive. This indicates: *
1 point
You are a project manager for a US $3,000,000 product development project. Your project is well into the executing process group and remains on time, on budget, and on specification. This morning your project sponsor called to express concern about the project. Based on the schedule baseline, the project should be nearing implementation, but the sponsor does not know the current status of the project. You remind the sponsor that your team produces a detailed status report weekly and distributes it via e-mail. The sponsor indicates that e-mail is too impersonal and verbal updates are preferred. This situation suggests problems with which of the following project management processes? *
1 point
One of your team members has discovered a defect in a deliverable and has recommended that it be repaired. Which of the following is NOT true? *
1 point
A change request in a project has been rejected some weeks ago. Yesterday, the project manager found out that it nevertheless has been implemented by the team members, who knew of the change request, but not of the rejection. In order to avoid such a situation, Rejected change requests should be consistently communicated to stakeholders through which process? *
1 point
According to Herzberg's theory, all of the following are motivating factors EXCEPT: *
1 point
In your project, you feel that there is a need to delegate an important task. After selecting a reliable team member, you decide to delegate that task to him. In this context, you can hold your team member accountable for the task only if you: *
1 point
As the project manager of an IT project, you are directing and managing the project execution. You have been looking at information related to similar projects. Which tools will you use? *
1 point
In which project management process group is the project manager likely to be more coaching? *
1 point
A project manager is creating a risk response plan. However, every time a risk response is suggested, another risk is identified that is caused by the response. Which of the following is the BEST thing for the project manager to do? *
1 point
When the contract is halfway through, the buyer requests you to incorporate some additional requirements which were not defined in the original contract. Since satisfying the buyer is important, you go ahead and incorporate those requirements as part of the project. According to PMI, this action is a violation of which aspect of Code of Ethics and Professional Conduct? *
1 point
The buyer's project manager is meeting with the seller's project manager to discuss the seller's performance to date on this important design-build project. There have been two changes to the project caused by a change in government regulations and three perceived errors by the seller that are being discussed. What is the BEST output of such a meeting? *
1 point
Value analysis is performed to get: *
1 point
Which of the following statements describes best the relationship of quality and grade? *
1 point
Which of the following organization charts has a hierarchical format? *
1 point
The main focuses of managing a project include: identifying requirements, establishing clear and achievable objectives, and: *
1 point
In which project management process group is the detailed project budget created? *
1 point
You are working for an international construction company. Your project involves pulling together over 13 different subprojects. You are having difficulty in ensuring three subcontractors are doing their work correctly. As you review the project results you notice you have spent US $1,200,000 at the last reporting point. You know the schedule is not too bad, since your schedule performance index (SPI) is 1.1. Considering you feel you should have spent US $1,300,000 to this point, what are the cost performance index (CPI), and the schedule and cost variances? *
1 point
You read a great article over the weekend, and you think your team could really benefit from it. What should you do? *
1 point
During the Sequence Activities process, you realize that several tasks have conditional branches (e.g., a design update is only needed if the inspection detects errors). For this purpose, you may use Precedence diagramming method (PDM), which is also referred to as: *
1 point
For the last three months, a customer has been from two to four days late with her approvals on deliverables. After analyzing the situation, the project manager decides withdrawal is the best conflict resolution technique to use. Which of the following reflects withdrawal? *
1 point
Which of the following BEST describes the role of the project management office (PMO)? *
1 point
As a project manager, you have selected Project A that has an initial budget of $ 1,000 out of which $ 800 has already been spent. To complete this project, you need an additional $ 500. Project B will require $ 1200 only for completion. Which project would you prefer to manage and what will be its ETC? *
1 point
You are interviewing new project managers for your company. One of the candidates' claims to be a PMP certified project manager, but you discover that she has never taken the PMP exam. What is the BEST way to handle this situation? *
1 point
You are a project manager. You have received a request from the stakeholders to provide more features to the product. Which tools and techniques do you use to process the request through "Perform Integrated Change Control" process? *
1 point
You are managing a project with 23 team members and six key stakeholders. Two team members identify a problem with the current approach. Addressing that problem will require changes to the project plan and its subsidiary plans. One of the stakeholders previously indicated that any delays are unacceptable, and your team members tell you that it's possible the change could cause the team to miss at least one critical deadline. What is the BEST way to deal with this situation? *
1 point
To what does the following sentence refer? "The point where the benefits or revenue to be received from improving quality equals the incremental cost to achieve that quality." *
1 point
A project manager is forced to dip into his management reserve. Which of the following is the MOST LIKELY cause of this? *
1 point
Your project team has identified dependencies on six related projects that are providing major deliverables to your project. Some of these projects have a very similar scope and may overlap with your deliverables. In light of this, which of the following processes should you be MOST concerned about? *
1 point
In your project, you want to define variance thresholds at the designated time points over the duration of a project. So, you should use: *
1 point
Which of the following is an output of the Define Activities process? *
1 point
As a project manager, you understand the importance of identifying and documenting project risks. In this context, which of the following statements is true: *
1 point
A project manager runs into a problem with her project's contractors, and she isn't sure if they're abiding by the terms of the contract. Which knowledge area is the BEST source of processes to help her deal with this problem? *
1 point
You are a project manager starting a new project. Your manager warns you that previous projects ran into trouble. Which of the following would be BEST for you to rely on to help plan your project? *
1 point
Your project is nearing completion, when the customer requests you to include an additional feature in the project's final product. The BEST course of action is to: *
1 point
While the project is being completed, management requests a change. What is the FIRST thing the project manager should do? *
1 point
The calculated duration of a project is 28.166. The standard deviation is 5.5. What technique would you use to compute the probability of completing a project on a specific day? *
1 point
A change in your project schedule has resulted in increased cost and risk. It has also impacted your resource plan. To coordinate changes across the entire project, you will need to rely on which of the following: *
1 point
What are the project management process groups? *
1 point