PMP® Practice Quiz - 11
Sign in to Google to save your progress. Learn more
To control the schedule, a project manager is reanalyzing the project to predict project duration. She does this by analyzing the sequence of activities with the least amount of scheduling flexibility. What technique is she using? *
1 point
As a project manager, you are in the process of making information promptly available to project stakeholders. Which of the following tools should you use? *
1 point
All of the following relate to controlling the schedule EXCEPT: *
1 point
A project manager has to resolve two problems. Both problems can occur in a single trial. In this situation, what is the BEST action the project manager can take? *
1 point
In a cost plus fixed fee (CPFF) contract, how can the fee change? *
1 point
The work breakdown structure can be BEST thought of as an effective aid for ______ communications. *
1 point
The Communications management plan is a document, which includes descriptions of *
1 point
You're managing an industrial design project. You've come up with the complete activity list, created network diagrams, assigned resources to each activity, and estimated their durations. What's the next thing that you do? *
1 point
Your project has the following duration estimates for three activities: Activity 1: Most likely - 9 days; Optimistic - 5 days; Pessimistic - 13 days; Activity 2: Most likely - 9 days; Optimistic - 4 days; Pessimistic - 14 days; Activity 3: Most likely - 9 days; Optimistic - 6 days; Pessimistic - 12 days. Which activity has the highest risk? *
1 point
You have been appointed manager of a project to convert multiple electronic mail systems at a major financial institution to a single platform. Your company's approach was not the client's first choice, and your firm was able to be the lowest cost alternative by using funds provided to your company for a different purpose. After the project is underway, the client specifies a new approach that has never been used before. When the project is approaching the originally scheduled end date, it becomes clear that the technological approach will have to be significantly altered. Although the client has been apprised of developments throughout the project through regular status reports, and the project management plan has been followed, the client demands that the project be continued without any increase in cost until all of the client's requirements are met. Your firm feels that it has no choice but to comply with the client's demands, although this will result in a substantial loss on the project. What is the MOST important thing that should have been done to avoid this situation? *
1 point
While staffing a project in another country, the project leader from that country comes to you with a suggested team consisting of members of the project leader's family. Your FIRST course of action should be to: *
1 point
During the executing process group of the project, a team member identifies a new risk. What should occur in light of this identification? *
1 point
You have just been assigned as project manager for a large telecommunications project. This one-year project is about halfway done. The project team consists of five sellers and 20 of your company's employees. You want to understand who is responsible for doing what on the project. Where would you find such information? *
1 point
Which of the following processes occurs in the Planning Process Group? *
1 point
Which motivational theory uses the concept of Theory Y? *
1 point
Project setup costs are an example of: *
1 point
The code development phase of a software project is nearly complete when the first code review is conducted. During the review, it is discovered that the application is missing functionality required to complete a key business process. However, the product scope never specified this functionality. What should the project manager do? *
1 point
In a normal distribution, standard deviation refers to: *
1 point
What is a GERT chart? *
1 point
During a post-mortem meeting, discussion arises about who has to take responsibility for some major failures. It has become obvious that the attendees of the meeting will not come to a jointly accepted conclusion. What is NOT an appropriate strategy for such a situation? *
1 point
After analyzing the status of your project, you determine that the project is two weeks behind schedule. You want to recover the original schedule if possible, and there is plenty of remaining budget in the current plan. What is the BEST option? *
1 point
Your project schedule is tight and in danger of falling behind when two team members start disrupting status meetings by arguing with each other. As project manager, what is the BEST thing you can do? *
1 point
All of the following are parts of the Close Project or Phase process EXCEPT: *
1 point
A project manager takes over an existing project, only to find that there are no quality standards. What part of the quality process should the project manager be in? *
1 point
A project manager needs to determine if the manufacturing process planned for the new micro-satellites will meet quality standards. Each satellite takes about three days to manufacture and costs US $125,000. The satellites are so small that inspection would destroy them. Under these circumstances, what should the project manager do? *
1 point
In creating a project management plan, how should a project manager use rewards? *
1 point
You have just started administrating a contract when management decides to terminate the contract. What should you do FIRST? *
1 point
A facilitator should… *
1 point
What is true for prototypes? *
1 point
Two of your project team members approach you with a conflict that they are having with each other over the technical approach to their work. One of the two people is very aggressive, and tries to get you to make a decision quickly. The other team member is quiet, and seems less willing to talk about the issue. The conflict is starting to cause delays, and you need to reach a decision quickly. What's the BEST approach to solving this conflict? *
1 point
All of the following are examples of projects EXCEPT: *
1 point
The scope of your project is very well defined and you have completed all the work described in the contract to your satisfaction, but you think your buyer is not happy with the work. What should you do (select the best answer)? *
1 point
Which of the following statements related to scope verification and quality control is correct? *
1 point
You are in the middle of a new product development project for your publicly traded company when you discover that the previous project manager made a US $3,000,000 payment that was not approved in accordance with your company policies. Luckily, the project cost performance index (CPI) is 1.2. What should you do? *
1 point
The MOST likely result of communication blockers is that: *
1 point
Which of the following is the BEST thing to do at a bidder conference? *
1 point
Which is NOT an output of a scope management process? *
1 point
To get the work done, the supervisor threatens punishment and strictly supervises the work. The supervisor believes in: *
1 point
You are considering creating a project management office (PMO) at your firm and have solicited the opinions of some of the senior management in your company. The first representative recommends that the PMO should manage all projects in the firm. The second believes that the PMO should handle large projects budgeted over a defined dollar amount. The third thinks a PMO should simply provide support to the department project managers. What should you do? *
1 point
A project manager is concerned about the amount of gold plating that has occurred on past projects. All the following would NOT be of use in controlling gold plating EXCEPT: *
1 point
Project performance appraisals are different from team performance assessments in that project performance appraisals focus on: *
1 point
What should you avoid when you are organizing documents as Lessons learned? *
1 point
The Situational leadership model as defined by Paul Hersey and Ken Blanchard consists of the stages: *
1 point
In your project, you wish to use rank-ordering to determine the causes for defects. In this context, the appropriate tool to use is: *
1 point
Originally a project had four team members. Now the scope has expanded, and there are a total of six people on the project team. How many communication channels does the project have? *
1 point
A project manager is in a meeting with the customer when the customer starts to yell about the fact that a change she requested will result in a delay to the project schedule. Interestingly, yelling is not a common practice in the client's culture. The project manager starts to explain why the change affected the schedule when the project manager's boss stops the meeting and carefully removes the project manager from the room. Which of the following would BEST describe what is going on? *
1 point
_________ are/is usually not a manifestation of unique organizational cultures and styles. *
1 point
You have been assigned as the project manager on a new project. The organization uses a strong matrix structure. Computers needed to complete the project are an example of: *
1 point
Which of the following are ALL tools and techniques of the Plan Procurements process? *
1 point
You had earlier worked as a project manager in a firm specializing in manufacturing semi-conductor chips. Now that you are working with a competitor, *
1 point
You are the project manager on a network engineering project. Two weeks ago, your team began executing the project. The work has been going well, and you are now a day ahead of schedule. Two stakeholders just approached you to tell you that they have an important change that needs to be made. That change will put you behind schedule. What do you do? *
1 point
During which process group does authorization to start a new phase of the project occur? *
1 point
You are the project manager in a software company. In your project, you want to ensure that all the operational departments in your organization (e.g. information integrity, data architecture group, servers group, etc.) clearly visualize their project responsibilities. Which one of the following helps you achieve this objective: *
1 point
Management gives the project manager a preliminary project scope statement and tells him that he is not sure it is complete. The preliminary project scope statement should include: *
1 point
In your project, you use the Develop Project Team process to improve the competencies and interaction of team members to enhance project performance. The output from this process is: *
1 point
A project manager has completed the Plan Risk Responses process. She was planning to go on to the Monitor and Control Risks process when she found out from another project manager that she forgot to do something important in this step. Which of the following did she forget? *
1 point
A work breakdown structure numbering system allows the project staff to: *
1 point
All of the following must be performed during project initiating EXCEPT: *
1 point
In your project team, you have developed a rule of thumb that scarce resources will have to be allocated first to the critical path. This rule of thumb can also be referred to as: *
1 point
In a project life cycle, the least number of conflicts occur over: *
1 point
Performance reporting is important during administrative closure in order to: *
1 point
Your department is currently working on four urgent projects when it is assigned a major new project. To staff the new project, one of the four urgent projects needs to be terminated. The benefit cost ratios (BCRs) for the four projects are listed. Which would you select for termination? *
1 point
In your project, you have established tools to ensure that appropriate information is available to project stakeholders in a timely manner. In this context, if there is a conversation taking place using a sender-receiver model, which of the following statements is NOT correct: *
1 point
What does the critical chain method focus on? *
1 point
In your project, you are in the process of developing the human resource plan. The enterprise environmental factors that cannot influence this process is: *
1 point
You have just been authorized to manage a new project for your company. Which of the following BEST describes your first action? *
1 point
During a routine walkthrough, you discover that a seller has neglected to properly produce a major component of a deliverable. The seller tells you that the component is not included in the contract. What should you do FIRST? *
1 point
Which of the following would be the MOST appropriate thing to do during the closing process group? *
1 point
Management wants to be sure that the project is following defined quality standards. Which of the following should they look at? *
1 point
Which of the following is NOT a responsibility of a project manager? *
1 point
The person who should be in control of the project during project planning is the: *
1 point
You are the project manager responsible for manufacturing a particular variety of soap. You decide to do a statistical sampling for this project, because surveying the entire population involves all the following problems EXCEPT: *
1 point
In your project, you are preparing a process improvement plan for the manufacture of a new drug. You include process configuration, as part of the process improvement plan. The use of process configuration advances this objective through: *
1 point
After completing Define Scope process, the management has asked you to coordinate the activities related to work breakdown structures (WBS) in your project. When using decomposition as a tool, what should you do FIRST? *
1 point
In the project, the sponsor has provided a budget of $20 million. This is an example of a/an: *
1 point
Payment for any decision made or encouraged by a foreign official with respect to whether a company will be awarded business is BEST described as: *
1 point
You're a project manager planning a project that requires that you hire a contractor. Before you can find sellers, you need to develop a document defines the portion of the work that the contractor will do. Which of the following is NOT true about this document? *
1 point
The project charter is typically approved by the project sponsor, although some charters can be approved by key stakeholders instead. Which of the following BEST describes the role of the project sponsor on the project? *
1 point
A project manager is reporting the final status of the closed contract to the stakeholders. Which form of communication is appropriate? *
1 point
You have used estimates made by your team members and applied the Critical path method to compute a Network logic diagram for your project. Then you found out that it cannot be sufficiently optimized for scarce resources and fast progress towards a given deadline. What should you do next? *
1 point
Your quality process did not meet the four sigma requirements desired by your customer. So, some of your products were rejected and there is a possibility that you would not receive repeat business from the customer. From a quality perspective, the costs associated with the rejected products can also be categorized as: *
1 point
Risks will be identified during which risk management process(es)? *
1 point
You are working on a construction project. You gather data regularly on the productivity of several employees and tasks (e.g., concrete poured per hour, length of electrical wiring done by a person per day, etc.). You compare this with that of similar projects embodied in your organizational process assets. This is a real life example of: *
1 point
You are reviewing performance goals to figure out how much bonus to pay to your team members. What document would you consult to find your team's bonus plan? *
1 point
In your project, you are in the process of identifying and documenting relationships among the project activities. These details will be included in which of the following processes? *
1 point
Project information has been distributed according to the communications management plan. Some project deliverables have been changed in accordance with the project management plan. One stakeholder expressed surprise to the project manager upon hearing of a previously published change to a project deliverable. All stakeholders received the communication containing notification of the change. What should the project manager do? *
1 point
A routine audit of a cost reimbursable (CR) contract determines that overcharges are being made. If the contract does not specify corrective action, the buyer should: *
1 point
Which of the following BEST describes formal acceptance of a project? *
1 point
Which of the following is the MOST likely outcome if you decide to crash the project? *
1 point
You have been assigned as the project manager for a construction project that has had two previous project managers, when you discover that a deliverable will be late. Your analysis shows that the item can be purchased from another seller at a higher price without affecting the schedule. What is the BEST thing to do? *
1 point
You are negotiating with a seller. Time is of the essence but you have a limited budget, and the seller knows this. What is your BEST negotiating strategy under these circumstances? *
1 point
A project manager may use ______ to make sure the team members clearly know what work is included in each of their work packages. *
1 point
Joe is an excellent programmer. He was promoted to a role of Project Manager because he understands technology better than anyone else in the company. Unfortunately, he is having trouble doing the project management job and his projects are failing. What is this an example of? *
1 point
________ is typically NOT referred to as a buffer type in Critical Chain project management. *
1 point
Managing conflicts is essential for successful implementation of a project. The conflict resolution techniques that are most frequently used in project management practice are: *
1 point
Your contract is nearing completion when the buyer mentions that there are some outstanding issues - this can be a potential dispute or conflict situation. In this context, what is the best way to deal with a dispute in a contract? *
1 point
Once a risk response is created, which of the following statements BEST describes the project manager's role regarding risks while the project work is being completed? *
1 point
Workarounds are determined during which risk management process? *
1 point
Which of the following are all related? *
1 point
All the following statements relating to communications management are correct EXCEPT: *
1 point
Submit
Clear form