You are managing a project with a BAC of $93,000, EV (BCWP) of $51,840, PV (BCWS) of $64,800, and AC (ACWP) of $43,200. What is the CPI? *
1 point
During project executing, the forecasted remaining hours exceed planned remaining hours. Consequently, the project takes on a negative variance. Which analysis method is the project manager likely to use as a measurement tool to validate this information? *
1 point
Using the chart, in order to handle some resource changes on your project, activity H is going to be done concurrently with activity G instead of after it. What impact will this have on the project? *
1 point
Captionless Image
You are monitoring and controlling your project, when your team members ask for some corrective action and preventive actions for errors. Some defects should also be handled through defect repair. You will include all this as part of: *
1 point
As a project manager, you are presented with the following information on the payback period for several possible projects. Which project is your BEST choice? *
1 point
What is a trigger in project risk management? *
1 point
You are managing a software engineering project, when two team members come to you with a conflict. The lead developer has identified an important project risk: you have a subcontractor that may not deliver on time. Another developer doesn't believe that the risk is likely to happen; however, you consult the lessons learned from previous projects and discover that subcontractors failed to deliver their work on two previous projects. You decide that the risk is too big; you terminate the contract with the subcontractor, and instead hire additional developers to build the component. Both team members agree that this has eliminated the risk. Which of the following BEST describes this scenario? *
1 point
What is the meaning of a concept called the "Journey to Abilene"? *
1 point
You evaluate your critical path and determine the project will be completed two weeks ahead of management's expected due date. What should you do? *
1 point
In Conduct Procurements process, you award a contract to the selected seller. In this context, all the following describe Conduct Procurements process EXCEPT *
1 point
During the Define Activities process, a team member identifies an activity that needs to be accomplished. However, another team member believes that the activity is not part of the project as he interprets the project scope statement. What is the BEST thing for the project manager to do?
1 point
Clear selection
Product verification is different than scope verification in that product verification: *
1 point
You are working as a project manager in an automobile company. Recently the government has amended the regulations to enforce stricter emission requirements for automobiles. As a project manager, you are concerned that your project quality norms may not satisfy the revised quality standards. So, you do an audit and try to remedy this problem through: *
1 point
The project is NOT completed until: *
1 point
During what part of the project management process is MOST of a project's budget expended? *
1 point
You are holding a formal, approved document that defines how the project is executed, monitored, and controlled. You are holding: *
1 point
Which of the following is included in a project charter? *
1 point
What is the LAST thing to do in project closure? *
1 point
Which of the following would be the MOST appropriate thing to do during the executing process group? *
1 point
An activity has an early start (ES) of day 3, a late start (LS) of day 13, an early finish (EF) of day 9 and a late finish (LF) of day 19. What is the activity's float? *
1 point
Which of the following is NOT a measure that determines if a business practice used by another country is an unfair business practice? *
1 point
A seller is working on a cost reimbursable (CR) contract when the buyer decides he would like to expand the scope of services and change to a fixed price (FP) contract. All of the following are the seller's options EXCEPT: *
1 point
A project manager is working with management to create the project estimate. During the initiating process group, what level of accuracy should the estimate have? *
1 point
How does MOST communication occur? *
1 point
You are the project manager in a company where you have maximum authority. To which organizational structure does your company belong? *
1 point
The project manager is looking at the project's resource needs and lessons learned from past projects. This information causes the project manager to be concerned about the ability to acquire enough resources for the project in six months. Which of the following would be the LEAST effective preventive action? *
1 point
You scheduled a kick-off meeting in order to announce the start of your project, present the plan and develop consensus on it. Another topic will be explanation of each team member's role. In addition, you planned some time for discussions. You published the agenda of the kick-off meeting some weeks ago to all invited attendees. Now, short term before the event, you receive various cancellations by team members, who say that they cannot join the meeting. But they will be with you when project work will start. *
1 point
Which risk analysis tool is used to model your risks by running simulations that calculate random outcomes and probabilities? *
1 point
Which of the following should be determined during the Plan Quality process, so the cost of quality will include the number of tests, expected scrap, etc.? *
1 point
When your company buys computers from Dell, you also pay extra for a three year warranty which ensures that any manufacturing defects will be taken care of by Dell. The risk response strategy used is: *
1 point
Over the last few weeks, the team has made three changes to the activities on the project. The project manager must be MOST careful to: *
1 point
Performance requirements describe: *
1 point
You have identified an opportunity to potentially increase the project's value. Which of the following is an example of enhancing that opportunity? *
1 point
You are developing the project charter for a new project. Which of the following is NOT part of the enterprise environmental factors? *
1 point
Statistical sampling involves choosing part of a population of interest for inspection. In this context, all the following statements on attribute sampling and variables sampling are accurate EXCEPT: *
1 point
If the optimistic estimate is one, the pessimistic estimate is nine, and the most likely estimate is eight, what is the PERT estimate? *
1 point
A detailed project schedule can be created only after creating the: *
1 point
Since you know the importance of risk management, you always include it as an agenda item in your weekly status meetings and spend ten minutes discussing the risks. Some of your project team members complain that since none of the risks are actually happening, discussing risk management issues in status meetings is a waste of time. What should you do? *
1 point
Your project team has completed the project work. All of the following must be done before the project can be closed EXCEPT: *
1 point
You are closing out a minor contract on a major project when you discover that a deliverable has not been received. Your manager wants the problem resolved as soon as possible without much trouble. What should you do? *
1 point
You are the project manager for a seller. A parking lot fencing project was bid at US $11 per foot. The parking lot has four equal sides of 125 feet and requires installing a six-foot diameter culvert on one side. Fencing should take 100 feet per day, and the culvert installation will cost US $500 and take one day to complete. The culvert must be installed before work can begin on that side of the fence. After three days of work, one side is complete, another side has 75 feet installed, and the culvert is completely installed. At this point, the client tells you that the culvert needs to be increased to a seven-foot diameter. You determine that this will cost US $1,000 and require two additional days. What should you do FIRST? *
1 point
A cost management plan contains a description of: *
1 point
A project manager needs a certain number of identical valve housings for a power station project. He starts with 100 raw items which are made as metal castings. Out of this batch, 15 are found leaking from micro-porosities in a subsequent pressure test. 6 of these housings can be recovered by a special sealing process for raw castings. The 91 housings are then being machined. After this process step 10 machined castings are found leaking. 3 of these items can also be saved using another sealing process for machined castings. The remaining 84 housings are getting mounted to the power plant pipe work. During a pressure test after this process step it is found that 12 valves are leaking. Out of these a number of 6 valves can be saved by replacing the sealing rings used. Finally the project manager has 78 valves which he can use. What is true? *
1 point
When all the requirements specified by the customer for a product are satisfied, *
1 point
The project manager is involved in the Develop Schedule process for the project. He has analyzed the project, compressed the schedule, and completed a Monte Carlo analysis. Which of the following is an output of Develop Schedule? *
1 point
A team member is visiting the manufacturing plant of one of the suppliers. Which of the following is the MOST important thing to be done in any telephone calls the project manager might make to the team member? *
1 point
Why is reverse resource allocation scheduling done? *
1 point
There have been several rounds of layoffs at your company. Now your project team is worried about their job security, and you've noticed that their performance has decreased significantly because of it. This is predicted by which motivational theory? *
1 point
A new project manager has been appointed to manage a project which was terminated six months earlier because of funding related issues. The project manager wants to find out the exact reasons for the termination of the project. He also wants to know which deliverables were produced from the terminated project. Which of the following document(s) should the project manager refer to? *
1 point
An estimate at completion (EAC) is an output of which of the following? *
1 point
Where should a new project manager look to determine resource requirements? *
1 point
The MOST common causes of conflict on a project are schedules, project priorities, and: *
1 point
Probability distributions are popular tools of Perform Quantitative Risk Analysis process. In this context, all the following statements on probability distributions are accurate EXCEPT: *
1 point
The purpose of status meetings is to: *
1 point
You're working on a IT project to set up a development environment, including designing and building a computer room, installing the operating systems and software, and performing a security evaluation. Your team comes up with a best-case scenario for the activity that involves ordering and installing the equipment. If everything goes perfectly, they feel it will take five weeks. However, they think it's much more likely to take nine. A team member points out that on his last project, there was a major equipment delivery delay that cost the project an extra four weeks, and the rest of the team agrees that this is a possibility in a worst-case scenario. Use PERT analysis to calculate how long you should expect this activity to take. *
1 point
Which of the following takes place during monitoring and controlling in the project management process? *
1 point
After analyzing the status of your project, you determine that the earned value (EV) is lower than the planned value (PV). What should you expect as an outcome if this trend continues? *
1 point
Your project has limited budget and you would like to determine how to complete the project at lower costs. This can be done using: *
1 point
You have a signed project charter, and are in the process of creating a project scope statement. You have asked the team for input to ensure that the project scope statement is complete. However, the team is struggling with defining the scope. Which of the following BEST describes the problem? *
1 point
Which of the following is an output of Direct and Manage Project Execution? *
1 point
Kyle is the project manager of a project that has teams distributed in many different places. In order to make sure that they all get the right message, he needs to make sure that his project plan is translated into Spanish, Hindi, French, and German. What is Kyle doing when he has his communications translated? *
1 point
You are working on a project with an SPI of .72 and a CPI of 1.1. Which of the following BEST describes your project? *
1 point
Stakeholders, including consultants, customers, sponsors, and professional and technical associations, are some of the sources of: *
1 point
You are a project manager. During the quality audit, you find out that the team members have committed a number of minor mistakes. To determine whether the process is in control, the most helpful tool you use is: *
1 point
As a project manager, you are creating a risk management plan to describe how risk management will be structured and performed on the project. The risk management plan can include all of the following EXCEPT: *
1 point
You are asked to prepare a budget for completing a project that was started last year and then shelved for six months. All the following would be included in the budget EXCEPT: *
1 point
A project is facing the following risks: 20 percent chance a part is not available, creating an additional fee of US $30,000; 10 percent chance the team requires additional training for a cost of US $12,000; 25 percent chance the second planned quality test costing US $8,000 is unnecessary. What is the expected monetary value of these risks? *
1 point
The project manager is in charge of all the following aspects of the project EXCEPT: *
1 point
There are over 30 stakeholders on your project. The project is being done in another country with people from three countries as team members. Which of the following is the MOST important thing to keep in mind? *
1 point
The six-month project has 300 work packages and a US $600,000 budget. Three months into the project 150 work packages are complete and US $300,000 has been spent. Which of the following is CORRECT? *
1 point
Being assigned as a project manager, you noticed during executing that conflicts arise in the team on both, technical and interpersonal level. What is an appropriate way of handling conflicts? *
1 point
Over half of conflicts on projects are caused by: *
1 point
Which of the following is the BEST method of completing "what-if" scenarios to determine what combination of resources and interdependencies will produce the best schedule? *
1 point
A project may be selected based on all of the following EXCEPT: *
1 point
You are having difficulty estimating the cost of a project. Which of the following BEST describes the most probable cause of your difficulty? *
1 point
Work on a project is ongoing when the project manager overhears two workers arguing over what a set of instructions means. The project manager investigates and discovers that the instructions for the construction of the concrete footings currently being poured were poorly translated between the different languages in use on the project. Which of the following is the BEST thing for the project manager to do FIRST? *
1 point
Which of the following is true in regard to the Code of Accounts? *
1 point
You, as the project manager, are planning to document relevant information on interest, involvement, and impact of the stakeholders on the project success. Which of the following communication processes should you follow? *
1 point
You are a project manager for one of many projects in a large and important program. At a high-level status meeting, you note that another project manager has reported her project on schedule. Looking back on your project over the last few weeks, you remember many deliverables from the other project that arrived late. What should you do? *
1 point
As part of Project Communications Management, you are collecting and disseminating information to stakeholders about resources used to achieve project objectives. This is done as part of: *
1 point
During project executing, a new project manager is assigned to the project and finds that the activity cost estimates for the project have rarely been accurate. Which of the following was MOST probably not done? *
1 point
During project executing, you find that the customer has requested a change to the scope of work even though it was previously not approved. There are no objections to the cost of the change. What should you do FIRST? *
1 point
As a project manager, you are estimating the costs required to complete the project activities. All the following tools can be used EXCEPT: *
1 point
You are a project manager for a large consulting firm. Your superior has just asked for your input on a decision about which project your company should pursue. Project A has an internal rate of return (IRR) of 12 percent. Project B has a predicted benefit cost ratio (BCR) of 1.3. Project C has an opportunity cost of US $75,000. Project D has a payback period of six months. If you had to choose based on this data, which project would you select? *
1 point
Two team members are having a big disagreement about how to accomplish an activity. The project is low risk and is taking place in a strong matrix environment with 34 team members. To resolve this dispute, the project manager should: *
1 point
Which of the following is CORRECT? *
1 point
While planning the project, you discover that an expert resource might be available to work on your project. However, the resource manager will not commit to the resource being on your team at the present time. The BEST thing to do would be to estimate the activity: *
1 point
A new testing center is going to be constructed over the next two years. The project sponsor and project manager have been identified and high-level estimates begun. It is expected that the project can be completed within budget and on schedule. The only difficulty is in acquiring the number of resources with the correct expertise to complete the work. Under these circumstances, the project manager should spend more time creating a: *
1 point
Your project management team includes two external consultants each from a different company. You found that repeated conflicts between the two consultants already slow down project progress and jeopardize achievement of objectives. Which stage of team development can be difficult to overcome in such a situation? *
1 point
In the Executing phase of a project, a project manager should ideally be: *
1 point
A change control system should be created: *
1 point
You provide a project cost estimate for the project to the project sponsor. He is unhappy with the estimate, because he thinks the price should be lower. He asks you to cut 15 percent off the project estimate. What should you do? *
1 point
Management wants to look at how a project is doing, as compared to past projects. To make a valid judgment, management should compare this project to: *
1 point
Company A is developing a project similar to one it delivered nearly 12 months earlier. What is the MOST likely approach to defining project activities? *
1 point
Liquidated damages (LDs) are contractually agreed payments in order to… *
1 point
The project manager on a large software installation project is working with her team on a critical set of activities. They are working late on Saturday night. Circumstances create the situation wherein the project manager must decide to change the schedule that will push the end date of the project out two weeks. What has MOST likely happened? *
1 point
What does "resource leveling" mean in project management? *
1 point
You're managing a construction project to install several hundred air conditioner panels in a new office building. Every floor has identical panels. The customer, a construction contracting company, has provided specifications for the installations. The team is using a process to install and verify each panel. As the team completes each panel, your team's quality control inspector measures it and identifies defects. The root cause of each defect is identified. You want to identify the ongoing trends of defective installations. Which is the BEST tool to use for this? *
1 point
You have created an Excel spreadsheet that shows cumulative cost at any particular point of time in the project duration. Your director wants to review the project costs and you decide to make a presentation. Cumulative costs plotted against time is shown in the slide as a: *
1 point
The human resources department wants to hire a new project manager from within the company. They can choose from the following candidates: Candidate A has good management knowledge; Candidate B has good project management knowledge; Candidate C has solid technical knowledge; Candidate D has general management, project management, and technical skills. Who is the BEST candidate? *
1 point