In your project, you are reviewing and maintaining realistic start and finish dates for project activities. This should be done as part of: *
1 point
The policies, methodologies, and templates for managing projects within the organization should be supplied by the: *
1 point
Your project just completed, and one of your subcontractors has sent you floor seats to the next big hockey game to thank you for your business. What is the BEST way to respond? *
1 point
Performance reports should address all the needs of: *
1 point
The float of an activity is determined by: *
1 point
All of the following are inputs to the Develop Schedule process EXCEPT: *
1 point
Which of the following represents information presented in its order of priority and helps focus on the MOST difficult issues? *
1 point
In which process do you create the Risk Breakdown Structure? *
1 point
A project has just begun when one of the stakeholders asks the project manager about making a change to the format of the deliverable for activity Y. She wants to know how to go about submitting the change for review. The project manager should direct her to: *
1 point
During its first winter, a multi-year construction project experienced weather-related schedule delays that all the local parties involved described as typical for this area. What should the project manager do to integrate this information into the project schedule? *
1 point
Resource calendars provide information on a specific resource or a category of resources. They show how a project team member might be unavailable (on vacation or in a training program) or how a labor contract can limit certain workers to certain days of the week. Resource calendars are valuable inputs to: *
1 point
In Plan Quality process, you are using benchmarking as a tool to facilitate quality planning. In this context, all the following statements about benchmarking are accurate EXCEPT: *
1 point
Management wants the project completed in 40 days. The cost performance index (CPI) is 1.1, the project critical path duration is 38 days with a standard deviation of two days. What is the maximum project float? *
1 point
Based on past estimates, there is a 25% probability for a particular event to occur every year. If a project lasts for three years, what is the probability of the event happening in the third year? *
1 point
Perform Integrated Change Control process requires coordinating changes across knowledge areas. A proposed schedule change control must often be integrated with all the following EXCEPT: *
1 point
A person who has been working as a project expeditor for the past three years has just been named as project manager for a construction project in a neighboring state. The construction crew has worked together for a number of years. One of the project manager's responsibilities is to pursue all of the historical risk information available, but he doesn't have enough time to access all available sources. The project manager would be best served by relying LEAST on which of these sources? *
1 point
The processes used in Project Communications Management are: *
1 point
You are asked to select tools and techniques to implement a quality assurance program to supplement existing quality control activities. Which of the following would NOT be appropriate for this purpose? *
1 point
In your project, you can use all the following tools and techniques for Plan Risk Responses process EXCEPT: *
1 point
The project manager must identify _________, determine their requirements, and then manage and influence those requirements to ensure a successful project. *
1 point
You are reviewing the expense reports for one of your team members when you notice a payment he made in another country. You think the payment is a bribe. What is your FIRST course of action? *
1 point
As you complete each deliverable for your project, you check that it is correct along with your stakeholders and sponsors. Which process are you performing? *
1 point
During project executing, the project manager determines that a change is needed to material purchased for the project. The project manager calls a meeting of the team to plan how to make the change. This is an example of: *
1 point
In order to decrease the risk on the project, the project manager decides during project executing to change resources on a near-critical path activity. If she is unsure whether such a change must be formally done on the project, she should look at the: *
1 point
People associated with the organization in which you are working with have been complaining about the lack of information regarding upcoming changes and want to get information now. Some of them feel what they have heard about your project means they will lose their job or be forced to find a difference position within the company. Luckily for you, the SPI is at 1.08 and the CPI is at.99, so you feel confident of success. What is the BEST way to deal with this situation? *
1 point
Your software project team informs you that another team working at the company built a tool that will save three weeks on the project. You ask the other team's project manager to have his team members share the tool with your team members. Which BEST describes this strategy? *
1 point
Your project is now in the executing stage. You are continuously monitoring and controlling risks to minimize negative risks and to take timely action. Risk audits are helpful in this context because they: *
1 point
While doing a cost-benefit analysis, you determine that a new project has 60% probability of earning a profit of $ 1,000,000 or 30% probability of incurring a loss of $ 500,000. What is the Expected monetary value of the decision? *
1 point
A company uses a management technique that employs quality assurance techniques to continuously improve all processes. This is called: *
1 point
In your project, the procurement statement of work (SOW) describes the procurement item in sufficient detail to allow prospective sellers to determine if they are capable of providing the product. In this context, the details of the procurement items' descriptions: *
1 point
A contract where the buyer reimburses the seller the costs incurred by her, and also provides for fixed amount of profit is also called: *
1 point
Lessons learned are BEST completed by: *
1 point
In your project, you have just conducted a risk data quality assessment to evaluate the degree to which the data about risks is useful for risk management. What is your next step? *