PMP® Practice Quiz - 23
Sign in to Google to save your progress. Learn more
In an automobile company in which you are the project manager, the allowable standard deviation for a product to be delivered by the contractor is less than 0.002 inches. However, product testing has revealed that the actual deviation is slightly more than 0.002 inches. You believe that the variation from the permissible deviation is negligible. In this case, you must: *
1 point
You are nearing project completion and want to get feedback about the overall project performance. From project management perspective, a project is considered to be successful when: *
1 point
Which of the following elements of the organizational process assets is not necessary to be updated in the Administer Procurements process? *
1 point
You are in the build phase of your project, when you realize that because of a design error, the product will not meet the performance parameters specified by the customer. In this context, you should: *
1 point
Which of the following BEST describes when the baseline can be changed? *
1 point
All of the following are tools of Perform Quality Control EXCEPT: *
1 point
An example of the contract price in a cost plus fixed fee (CPFF) contract is: *
1 point
You are managing a software engineering project. Your team is having trouble completing their object design tasks. One of your team members tells you that her friend at another company sent her a copy of a software package they own that will help your team meet its deadline. Without that software package, your project will probably be late. But you don't have enough money in the budget to purchase it. What's the BEST way to handle this situation? *
1 point
Which of the following regarding performance reporting is CORRECT? *
1 point
Your project will most likely be completed in 10 weeks. At the worst, the project will require 19 weeks, and if everything goes well, the project will be completed in 7 weeks. What is the PERT estimate for the project? *
1 point
In your project, probabilities are estimated and the alternatives are expected to be as follows: 25% probability for $ 25,000 profit; 50% probability for $ 40,000 profit; 25% probability for $ 100,000 profit. What is the expected profit in your project? *
1 point
During project executing, a project team member informs the project manager that based on her observations, the project cannot meet the quality standards set for it. What would be the LEAST effective thing for the project manager to do? *
1 point
A seller on your project tells you that he no longer thinks the project will provide the benefits he wanted when he signed the contract. Because of this, he no longer thinks it is in his best interest to continue. What should you do FIRST? *
1 point
You are the seller for a procurement contract and your team is receiving bids or proposals for evaluation. These will be evaluated during: *
1 point
Which of the following is NOT correct about network diagrams? *
1 point
You're managing a highway construction project. The foreman of your building team alerts you to a problem that the inspection team found with one of the pylons, so you use an Ishikawa diagram to try to figure out the root cause of the defect. What process is being performed? *
1 point
You are managing a software engineering project, when two team members come to you with a conflict. The lead developer has identified an important project risk: you have a subcontractor that may not deliver on time. The team estimates that there is a 40% chance that the subcontractor will fail to deliver. If that happens, it will cost an additional $15,250 to pay your engineers to rewrite the work, and the delay will cost the company $20,000 in lost business. Another team member points out an opportunity to save money another area to offset the risk: if an existing component can be adapted, it will save the project $4,500 in engineering costs. There is a 65% probability that the team can take advantage of that opportunity. What is the expected monetary value (EMV) of these two things? *
1 point
When your project is nearing completion, the customer requests you to include an additional feature in the final product. You realize that this feature was discussed with the project sponsor in an earlier meeting and he was against having this feature. What will be the BEST course of action? *
1 point
All of the following are parts of the Perform Quality Control process EXCEPT: *
1 point
A project has a schedule reserve of 28 days when the customer adds scope not previously planned for. The change has a 40 percent chance of delaying the project by an additional 14 days. What should be done? *
1 point
Which of the following is the MOST beneficial result of the project manager knowing the critical path? *
1 point
In the executing phase of your project, you lose some key resources. Some new people have joined, and you (the project manager) set up a meeting to get the team together. What should be the most important agenda item for this meeting? *
1 point
You've been contracted by an industrial design firm to manage their contracting. Your client asks you to take over the negotiations for an important contract to design a new lighting remote control system. You've narrowed it down to one seller, and now you're working with the legal department at the buyer to negotiate the terms of the contract. Which of the following BEST describes your goal? *
1 point
Which enterprise environmental factor defines how work is assigned to people? *
1 point
Which of the following is NOT a tool or technique used in Estimate Activity Durations? *
1 point
The project manager is trying to manage conflicting stakeholder requirements. The IT manager wants a new management information system. To lower costs, the system architect emphasizes technical excellence, and the programming contractor wants to maximize profits. To balance the needs of several stakeholders and achieve lasting resolution of conflicts, the most desirable conflict resolution technique is: *
1 point
A project team member informs you that a particular task is taking much more time than what was budgeted. You are surprised because you, as a project manager, had not anticipated this delay, and you ask for status reports and forecasts from all project team members. Which process group are you in? *
1 point
Which statement on conflicts is true? *
1 point
A team meeting during project executing is the BEST format to: *
1 point
During the executing process group of the project, you realize the subcontractors are working with incomplete and different project scope statements. As the project manager, what should you do FIRST? *
1 point
You are working as a project manager in a company; you get to know that a person managing another project of your company has furnished false reports about his PMP experience and credentials. What should you do in this context? *
1 point
In your project, you have been sub-contracting your IT development work to four consultancy firms. In this context, all the following statements relating to transferring of risk to a contractor are true EXCEPT: *
1 point
After identifying a risk to your project, you determine that there is a high probability of the risk occurring with a low consequence. What mitigation strategy is BEST to adopt? *
1 point
Which of the following is NOT an input to the Develop Project Management Plan process? *
1 point
A project manager is working on a large construction project. His plan says that the project should end up costing $1.5 million, but he's concerned that he's not going come in under budget. He's spent $950,000 of the budget so far, and he calculates that he's 57% done with the work, and he doesn't think he can improve his CPI above 1.05. Which of the following BEST describes the current state of the project? *
1 point
You are in the process of procuring nuts and bolts for a car manufacturing company. This is a readily available product for which there are several acceptable sellers. In this context, which of the following would serve as the most important selection criterion/criteria? *
1 point
At a critical milestone in a development project, it is determined that implementation is two months behind schedule. The project manager is concerned that the root cause is lack of conformance to requirements in the design of the new billing system. More extensive measurements are taken to see if this is, in fact, the problem. Such measurements are: *
1 point
Which of the following is NOT true about portfolio management? *
1 point
You note that the ability to influence the cost of a project is: *
1 point
The director (information systems) in your company is in the process of creating a project charter to formally authorize a new project in your company. In this context, what should be done FIRST? *
1 point
A project team is in the design stage of a new mountain bicycle prototype. The team is in the process of identifying which type of frame and material will provide high performance at a low cost. Which of the following is the MOST likely technique used to determine these variables? *
1 point
The customer and project manager need to verify the scope of the deliverables. This will help to: *
1 point
While completing work for your project, the seller's subcontractor suffers a major fire. The fire destroys the heating system they were building for your project. What is the BEST thing to do? *
1 point
The Cost baseline is developed during which process? *
1 point
Theory X postulates that people: *
1 point
Earned value measurement is an example of: *
1 point
The project work is underway when you discover that your specifications are incomplete. However, you are not sure of the extent of the problem. Unfortunately, the project has a very tight timeline for your review of the seller's submittals and for completing the project. What should you do FIRST? *
1 point
Which of the following is NOT a part of the project management plan? *
1 point
Who has the MOST power in a projectized organization? *
1 point
Which of the following is NOT found in a project charter? *
1 point
The CEO of ABC bank is concerned about the increase in "call answering time" in the bank's call center (i.e., customers have to wait longer for their calls to be answered by an operator). She wants to improve call center processes to decrease the "call answering time." What should the CEO do to address the situation? *
1 point
Tom is the project manager of an accounting project. He has just finished defining the scope for the project and is creating the WBS. He goes to his organizational process asset library and finds a WBS from a past project to use as a jumping off point. Which of the following is the tool of the Create WBS process is he using? *
1 point
You will use the Conduct Procurements process to receive bids or proposals and apply the selection criteria for selecting a provider. Which of the following tools and techniques can be used for the Conduct Procurements process? *
1 point
All of the following are found on a control chart EXCEPT: *
1 point
You work for a seller that is bidding on a contract. Which type of contract has the MOST risk for your company? *
1 point
Project integration management includes the processes and activities needed to identify, define, combine, unify, and coordinate the various processes and project management activities. For successful project integration management, you definitely need(select the best answer): *
1 point
You're creating source selection criteria for your contract. What process are you in? *
1 point
The requirements of many stakeholders were not approved for inclusion in your project. Therefore, you had a difficult time receiving formal approval of the project management plan for this project. The stakeholders argued and held up the project while they held meeting after meeting about their requirements. The project was finally approved and work was begun six months ago. All of the following would be good preventive actions to implement EXCEPT: *
1 point
A manager has responsibility for a project that has the support of a senior manager. From the beginning, you have disagreed with the manager as to how the project should proceed and what the deliverables should be. You and she have disagreed over many issues in the past. Your department has been tasked with providing some key work packages for the project. What should you do? *
1 point
Three items from the issue log have been assigned to a team member. However, no action has been taken by the agreed-upon due date. After three calls to the team member, the work is finally completed. Which of the following is the BEST preventive action to take NOW? *
1 point
Two people are arguing about what needs to be done to complete a work package. If the project manager wants to know what is going on, she should pay MOST attention to: *
1 point
You are starting to write your project charter with your project sponsor when the senior managers ask for a time and cost estimate for the project. You have not yet gathered many of the project details. What kind of estimate can you give? *
1 point
Who should always issue the project charter? *
1 point
All of the following are NOT parts of a project management plan EXCEPT: *
1 point
An obstacle to team building in a matrix organization is that the: *
1 point
Which of the following is NOT an output of the Close Project process? *
1 point
Please refer to the table. What is the slack of task 5? *
1 point
Captionless Image
In your project, you are reviewing and maintaining realistic start and finish dates for project activities. This should be done as part of: *
1 point
The policies, methodologies, and templates for managing projects within the organization should be supplied by the: *
1 point
Your project just completed, and one of your subcontractors has sent you floor seats to the next big hockey game to thank you for your business. What is the BEST way to respond? *
1 point
Performance reports should address all the needs of: *
1 point
The float of an activity is determined by: *
1 point
All of the following are inputs to the Develop Schedule process EXCEPT: *
1 point
Which of the following represents information presented in its order of priority and helps focus on the MOST difficult issues? *
1 point
In which process do you create the Risk Breakdown Structure? *
1 point
A project has just begun when one of the stakeholders asks the project manager about making a change to the format of the deliverable for activity Y. She wants to know how to go about submitting the change for review. The project manager should direct her to: *
1 point
During its first winter, a multi-year construction project experienced weather-related schedule delays that all the local parties involved described as typical for this area. What should the project manager do to integrate this information into the project schedule? *
1 point
Resource calendars provide information on a specific resource or a category of resources. They show how a project team member might be unavailable (on vacation or in a training program) or how a labor contract can limit certain workers to certain days of the week. Resource calendars are valuable inputs to: *
1 point
In Plan Quality process, you are using benchmarking as a tool to facilitate quality planning. In this context, all the following statements about benchmarking are accurate EXCEPT: *
1 point
Management wants the project completed in 40 days. The cost performance index (CPI) is 1.1, the project critical path duration is 38 days with a standard deviation of two days. What is the maximum project float? *
1 point
Based on past estimates, there is a 25% probability for a particular event to occur every year. If a project lasts for three years, what is the probability of the event happening in the third year? *
1 point
Perform Integrated Change Control process requires coordinating changes across knowledge areas. A proposed schedule change control must often be integrated with all the following EXCEPT: *
1 point
A person who has been working as a project expeditor for the past three years has just been named as project manager for a construction project in a neighboring state. The construction crew has worked together for a number of years. One of the project manager's responsibilities is to pursue all of the historical risk information available, but he doesn't have enough time to access all available sources. The project manager would be best served by relying LEAST on which of these sources? *
1 point
The processes used in Project Communications Management are: *
1 point
You are asked to select tools and techniques to implement a quality assurance program to supplement existing quality control activities. Which of the following would NOT be appropriate for this purpose? *
1 point
In your project, you can use all the following tools and techniques for Plan Risk Responses process EXCEPT: *
1 point
The project manager must identify _________, determine their requirements, and then manage and influence those requirements to ensure a successful project. *
1 point
You are reviewing the expense reports for one of your team members when you notice a payment he made in another country. You think the payment is a bribe. What is your FIRST course of action? *
1 point
As you complete each deliverable for your project, you check that it is correct along with your stakeholders and sponsors. Which process are you performing? *
1 point
During project executing, the project manager determines that a change is needed to material purchased for the project. The project manager calls a meeting of the team to plan how to make the change. This is an example of: *
1 point
In order to decrease the risk on the project, the project manager decides during project executing to change resources on a near-critical path activity. If she is unsure whether such a change must be formally done on the project, she should look at the: *
1 point
People associated with the organization in which you are working with have been complaining about the lack of information regarding upcoming changes and want to get information now. Some of them feel what they have heard about your project means they will lose their job or be forced to find a difference position within the company. Luckily for you, the SPI is at 1.08 and the CPI is at.99, so you feel confident of success. What is the BEST way to deal with this situation? *
1 point
Your software project team informs you that another team working at the company built a tool that will save three weeks on the project. You ask the other team's project manager to have his team members share the tool with your team members. Which BEST describes this strategy? *
1 point
Your project is now in the executing stage. You are continuously monitoring and controlling risks to minimize negative risks and to take timely action. Risk audits are helpful in this context because they: *
1 point
While doing a cost-benefit analysis, you determine that a new project has 60% probability of earning a profit of $ 1,000,000 or 30% probability of incurring a loss of $ 500,000. What is the Expected monetary value of the decision? *
1 point
A company uses a management technique that employs quality assurance techniques to continuously improve all processes. This is called: *
1 point
In your project, the procurement statement of work (SOW) describes the procurement item in sufficient detail to allow prospective sellers to determine if they are capable of providing the product. In this context, the details of the procurement items' descriptions: *
1 point
A contract where the buyer reimburses the seller the costs incurred by her, and also provides for fixed amount of profit is also called: *
1 point
Lessons learned are BEST completed by: *
1 point
In your project, you have just conducted a risk data quality assessment to evaluate the degree to which the data about risks is useful for risk management. What is your next step? *
1 point
Submit
Clear form
This content is neither created nor endorsed by Google. Report Abuse - Terms of Service - Privacy Policy