PMP® Practice Quiz - 16
Sign in to Google to save your progress. Learn more
When entering into a procurement, it is BEST to assume there will be disputes about the performance of the work as specified, and to: *
1 point
A project has the following risks: 20 percent probability of a 14 day delay in the receipt of customer requirements; 10 percent probability of a 21 day delay in the procurement process; 50 percent probability the integration will take 14 days longer. What is the expected monetary value of these events? *
1 point
While planning a project, you are defining activities. Which of the following is not a result of that process? *
1 point
Which is NOT a type of project review meeting? *
1 point
Your project is being carried out under a contract. There have been some changes in the project scope and you want to determine the cause of variance with respect to the scope baseline. This will help you decide whether corrective action is required. This should be done as part of: *
1 point
A project manager discovers that a project problem has occurred. The problem was never discussed during risk planning activities or added to the risk register, and it will now cost the project money. What is the BEST response? *
1 point
You have always been asked by your management to cut your project estimate by 10 percent after you have given it to them. The scope of your new project is unclear and there are over 30 stakeholders. Management expects a 25 percent reduction in downtime as a result of the project. Which of the following is the BEST course of action in this situation? *
1 point
Who should be responsible for defining project objectives? *
1 point
During a project Earned Value Analysis is performed and gives the following numbers: EV: 523,000; PV: 623,000; AC: 643,000. Which results are correct? *
1 point
The project has been challenging to manage. Everyone has been on edge due to pressure to complete the project on time. Unfortunately, the tension has grown to the point where team meetings have become shouting matches and little work is accomplished during the meetings. One team member asks to be excused from future team meetings, as all the shouting upsets him. Meanwhile, the sponsor has asked to attend team meetings in order to better understand how the project is going and the issues involved in completing the project, and the customer has started discussions about adding scope to the project. In this situation, it would be BEST for the project manager to: *
1 point
You could obtain measuring equipment with very high accuracy and precision. You used it to make a sequence of measurements directly at a production process output and depicted the results on the following Control chart. Which statement is the best conclusion from these results? *
1 point
Captionless Image
A difference between a Statement of work and a Scope statement is: *
1 point
The line in the middle of a control chart is called the: *
1 point
In your project, you estimate the cost of individual activities or work packages, and then roll up the individual estimates for subsequent reporting and tracking purposes. This can be done using: *
1 point
A control chart indicates the last 12 weights produced were outside the upper control limit. What should the project manager do? *
1 point
Your project work has generally been finished and you want to commence a solid closing process for the project. What must have been attained to begin this process? *
1 point
A stakeholder wants to make a change to the work breakdown structure that does NOT affect the time or cost of the project. What is the BEST thing to do? *
1 point
A project manager new to project management is taking on a new project. When is the BEST time to help build the people working on the project into a team? *
1 point
You found the following Earned Value Analysis information for a recently closed out project: SPI = 0.7, CPI = 1.0 *
1 point
You are in the process of obtaining seller responses to select a seller. In this context, you conduct a bidder conference, where your primary objective is to: *
1 point
Activities in the Define Activities process should meet: *
1 point
Which of the following is a KEY output of the Verify Scope process? *
1 point
As part of decomposing, you break down the project work that needs to be accomplished in the near term at a low level of WBS. However, the work planned in the future is broken down at a relatively high level of WBS. This technique is called : *
1 point
You are a project manager for a large electrical system implementation. One of your key people has started to miss deadlines and work quality is beginning to suffer as well. This person has participated in project planning, and in fine-tuning the earned value estimating, and developing the reward systems for the project. You are confident that this person is well aware of the work deadlines and required quality specifications. What action should you take? *
1 point
What is the Internal Rate of Return (IRR) of a project? *
1 point
In your project, the seller is worried that the CPIF contract is reaching the point of total assumption. What is meant by the point of total assumption? *
1 point
Which of the following is the MOST likely cause of poor risk management? *
1 point
A project has a team member assigned to the project full time. What is the MOST likely effect on the project if that resource completes her activity sooner than planned? *
1 point
For which of the following actions could a project manager incur a fine and be jailed? *
1 point
Which of the following represents the value of work we have actually completed? *
1 point
All of the following are outputs of the Estimate Costs process EXCEPT: *
1 point
Which of the following should NOT be in the risk register? *
1 point
A project has a tight budget when you begin negotiating with a seller for a piece of equipment. The seller has told you that the equipment price is fixed. Your manager has told you to negotiate the cost with the seller. What is your BEST course of action? *
1 point
You are managing a software engineering project, when two team members come to you with a conflict. The lead developer has identified an important project risk: you have a subcontractor that may not deliver on time. Another developer doesn't believe that the risk is likely to happen; however, you consult the lessons learned from previous projects and discover that subcontractors failed to deliver their work on two previous projects. The lead developer suggests that you have two team members take three weeks to research the component being built by the subcontractor, and come up some initial work that you can fall back on in case that subcontractor does not deliver. You decide to follow the lead developer's advice over the objections of the other team member. Which of the following BEST describes this scenario? *
1 point
You have recently been assigned as a project manager to a new B-O-T (Build, Operate, Transfer) capital project. Reviewing the initial documentation you found out that it has been calculated with a very small margin during operations of its product for the shareholders. What should you do? *
1 point
A definitive estimate is: *
1 point
The stakeholders identified a major project risk of more than 2 centimeters of rain falling in any 24 hour period. With a little effort, contingency plans and fallback plans were put in place for this risk and risk response owners said they were ready to take action. One day during the project it started to rain. The risk response owner was not even near the project location to know it was raining and so the contingency plan was not implemented. Which of the following BEST describes why this occurred? *
1 point
Project Team A has been hired to manage a transportation project very similar to dozens of projects the team has managed successfully in the past. The team has determined that the probability of achieving project objectives is 94 percent. What part of the risk process is the team in? *
1 point
Which of the following items is not included in schedule data? *
1 point
Your new project to outsource work has been going badly. The project deliverables have changed three times, the functional managers keep removing people from the team, and the project schedule baseline has been adjusted four times in the first week. This is MOST likely due to a lack of: *
1 point
A project manager has a large team consisting of people from many functional areas of the company. The BEST method to get the team's cooperation is to use _____ power. *
1 point
You are taking over a project and determine the following: Activity B has an early finish (EF) of day 3, a late finish (LF) of day 6, and an early start (ES) of day 2. Activity L is being done by a hard-to-get resource. The cost performance index (CPI) is 1.1 and the schedule performance index (SPI) is 0.8. Based on this information what would you be more concerned about? *
1 point
A frequent complaint about matrix organizations is that communications are: *
1 point
A junior project manager is studying for her PMP exam, and asks you for advice. She's learning about Earned Value Management, and wants to know which of the variables represents the difference between what you expect to spend on the project and what you've actually spent so far. What should you tell her? *
1 point
The project is completed and the final deliverable has been sent to the customer, but the customer refuses to give final acceptance of the project. It is MOST important for the project manager to: *
1 point
If the optimistic estimate for an activity is 12 days, and the pessimistic estimate is 18 days, what is the standard deviation of this activity? *
1 point
There are four people on the project team and the project manager adds three more. How many channels of communication are there now? *
1 point
Define Activities, Sequence Activities, and Estimate Activity Durations all occur before: *
1 point
The sponsor and the project manager are discussing what type of contract the project manager plans to use on the project. The buyer points out that the performing organization spent a lot of money hiring a design team to come up with the design. The project manager is concerned that the risk for the buyer be as small as possible. An advantage of a fixed price contract is: *
1 point
Outputs of the Develop Human Resource Plan process are: *
1 point
The project customer and project sponsor have requested for the addition of a new feature to your project deliverable. This request is approved by the change control board. The change will result in delay of project by 2 months and a cost increase of $ 1 million. What should you do NEXT? *
1 point
What does estimate at completion (EAC) mean? *
1 point
A project manager is running into problems with the team. People are repeatedly running into trouble over seemingly small problems: who takes notes at meetings, what dress is appropriate for the office, who people need to notify when they take a day off. The problems started out small, but as more people run into more problems the situation is rapidly escalating. This situation is most likely caused by a lack of: *
1 point
You have recently taken over a new project. While studying the project information, you find out that cost variances are very severe. To provide a realistic basis for performance measurement, what should you recommend? *
1 point
You are a project manager for a major information systems project. Someone from the quality department comes to see you about beginning a quality audit of your project. The team, already under pressure to complete the project as soon as possible, objects to the audit. You should explain to the team that the purpose of a quality audit is: *
1 point
The project schedule constraints have just been determined. What project management process group are you in? *
1 point
You just completed a cost estimate on the project, and you're assuming there is a 15 percent chance you will exceed this estimate. You are: *
1 point
You are managing a team consisting of members from four different countries; you realize that some cultural differences among your team members are hampering the progress of your project. In this context, what should you do? *
1 point
Your company has decided to outsource one of its IT product developments to ABC IT Services through a contract. You clarify the structure and requirements of the contract so that mutual agreement can be reached prior to signing the contract. All the following statements on procurement negotiations are correct EXCEPT: *
1 point
A project manager you are mentoring comes to you for help because he is about to face his first procurement audit. You might explain that he should NOT worry about such an audit because it: *
1 point
Which of the following includes all of the relationships represented on an activity-on-node diagram? *
1 point
You recently assigned staff members to activities, estimated work and scheduled your project. You then created the following resource histogram for your staff. What does this diagram tell you? *
1 point
Captionless Image
You're working at a major conglomerate. You have a 24-person team working for you on a project with five major sponsors. The company announces layoffs, and your team is reduced to half its size. How many lines of communication are on your new, smaller team? *
1 point
Which of the following is not true about the Project Charter? *
1 point
You are the project manager of a $ 20 million project, and you are struggling to manage the needs of all the stakeholders. So, you decide to classify the stakeholders, which will enable you to focus on the relationships necessary to ensure the success of the project. All the following are valid ways to classify stakeholders EXCEPT: *
1 point
You monitored figures on cost and planned/earned value for each individual project week until the data date at the end of the sixth week. What is the status of this project at this date? *
1 point
Captionless Image
Which of the following activities occurs during the Plan Procurements process? *
1 point
In Configuration management, which of the following is necessary to maintain the integrity of Baselines? *
1 point
All of the following are tools used in the Verify Scope process EXCEPT: *
1 point
An equipment seller provided a buyer with all the operations and maintenance manual information on their equipment in electronic disc format, compatible with the computer hardware/software used by the buyer. The buyer's project manager demanded that written copies of these manuals be provided. The seller refused, stating that the information had been supplied in the "useable & complete" format required in the contract. This disagreement is an example of an oversight made during which stage of the project's development? *
1 point
After the project schedule is created, a project manager should use schedule control for all of the following EXCEPT: *
1 point
The main purpose of the Manage Project Team process is to: *
1 point
Which of the following BEST describes when a project phase is generally concluded? *
1 point
In an informal discussion you had with another PMP certificant, he mentioned how he was able to sit for the PMP Certification exam three years ago using false contact hour certificates. You should: *
1 point
Who is responsible for determining appropriate project management processes to use for a specific project? *
1 point
Three students from another country are working as interns on a project. The project manager has arranged for some games to play as team building activities to help create a close knit sense of team with the group members. At the event where the activities are taking place, the three students refuse to participate claiming the behavior involved is unacceptable in their country and they would be very uncomfortable participating. What should the project manager do? *
1 point
Which of the following is the BEST thing to do at a bidder conference? *
1 point
A contract obligates the seller to provide the specified product and obligates the buyer to pay for it. In this context, which of the following is a mandatory feature of a contract? *
1 point
You are the program level manager with several project activities underway. In the executing process group, you begin to become concerned about the accuracy of progress reports from the projects. What would BEST support your opinion that there is a problem? *
1 point
Your contract states that the maximum charge for services from the seller will be US $50,000/month. However, the actual invoices have been US $100,000 for the past three months. Stopping the seller's service will impact the project schedule. Under these circumstances, the BEST thing to do is to review the: *
1 point
You have just discovered that one of the sellers on your project has not submitted the weekly status report, as is required in the contract, for the last four weeks. What is the BEST thing to do? *
1 point
During project planning, you are presented with the following diagram that depicts a cumulative likelihood distribution for the duration of a project. What kind of conclusion can you draw from the information depicted in it? *
1 point
Captionless Image
A project team member tells you that she went to her project manager with a good idea for a useful change to the project. Instead of giving her approval to make the change, the project manager asked her to write a report describing the benefits of the change. What is the MOST appropriate advice for the situation? *
1 point
During the implementation of a contingency plan, a team member notices that the plan worked only marginally. There were three similar contingency plans developed for other risks that have not yet happened. He should recommend which of the following? *
1 point
Which process group focuses on completing the requirements of the project? *
1 point
Project Risk Management includes all the processes concerned with conducting risk management planning, identification, analysis, response planning, and monitoring and control on a project. In this context, all the following statements about risk are accurate EXCEPT: *
1 point
A project is in the middle of the executing processes when a stakeholder suggests a major new change. This change will cause the third major overhaul of the project. At the same time, the project manager discovers that a major work package was not completed because a team member's boss moved him to another project that had a higher priority. Which of the following is the BEST person for the project manager to address these issues with? *
1 point
Estimate at completion (EAC) is a periodic evaluation of: *
1 point
A trend report was given to the project manager, who reacted to the report by investigating what activity or activities had not been done, but should have been done, to date. What did the report show? *
1 point
Customer satisfaction should be measured at the end of the project to maintain long-term relationships. Which of the following is NOT always an aspect of customer satisfaction? *
1 point
In Plan Risk Management, you define how to conduct risk management activities for a project because careful and explicit planning enhances the probability of success for the subsequent risk management processes. In this context, what will you NOT do when you Plan Risk Management? *
1 point
A project manager has been instructed to use the project charter to help identify risks on the project. This does not make sense to him. If you were asked to explain the reason the project charter is used in this way, what is the BEST explanation? *
1 point
Which is typically NOT specified in a document referred to as Activity attributes? *
1 point
A project manager has completed a detailed WBS and cost estimates for each work package. To create a cost baseline from this data, the project manager would: *
1 point
One of the stakeholders on the project contacts the project manager to discuss some additional scope he would like to add to the project. The project manager asks for details in writing and then works through the Control Scope process. What should the project manager do NEXT when the evaluation of the requested scope is complete? *
1 point
In a fixed price contract, the buyer decides to increase the scope of work to make the product better. In this case, which of the following can the buyer NOT do? *
1 point
While reviewing a land purchase agreement with the government, the project manager thought that some clauses in the agreement were not in order. She consulted the company lawyer, who advised her that all the legal formalities and procedures were properly followed as per the state laws. However, the project manager was not satisfied with the explanation given by the company lawyer. To find out a solution to this issue, she should: *
1 point
The network expansion project you just took over is said to be doing pretty well. The previous project manager only used variances to tell the current project status. In the last report you find SV = US $50,000, CV = US $10,000, PV = US $500,000. You know the rate of spending and schedule progress are important as well. Based on the details you have been given what are the SPI and CPI? *
1 point
The sponsor of the project you are managing asks you to compress the schedule. Which of the following is CORRECT? *
1 point
You finished your project for a customer to implement a business software solution. All deliverables have been handed over and are already in use by the company. There is a minor last payment to be made by the customer on contract closure. You believe that it is now getting time to finally close the contract with the customer and then administratively close down the project. You approached the customer this morning and found that they are reluctant to finally close the contract. But you do not exactly understand why. What should you NOT do? *
1 point
Submit
Clear form
This content is neither created nor endorsed by Google. Report Abuse - Terms of Service - Privacy Policy