Scope management
Scope management
Sign in to Google to save your progress. Learn more
Email *
1. A project has a number of deliverables that are complex and have to be assembled. As the project manager, you know the work breakdown structure will help stakeholders to see interim deliverables that will be integrated into the final project deliverables. To help manage the individual elements, you have used a work breakdown numbering system. This numbering system allows the project team to: *
1 point
2. The work breakdown structure can best be thought of as an effective aid for________________communications *
1 point
3. The product of the project has been completed and delivered to the customer by the team. They are informed by the customer that several of the deliverables are not acceptable, as they do not meet the requirements specified early in the project. The project manager and team review the requirements documentation, and are in agreement that the product deliverables meet the customer s requirements as they understand them. The project manager, who is new to the organization, seeks the advice of the project management office in determining what went wrong. After some discussion, the PMO realizes that the Validate Scope process was not performed appropriately by the project manager. Which of the following is a key output of the Validate Scope process? *
1 point
4. During project executing, a team member comes to the project manager because he is not sure what work he needs to accomplish on the project. Which of the following documents contains detailed descriptions of work packages? *
1 point
5. During which part of the project management process is the project scope statement created? *
1 point
6. The program was planned years ago, before there was a massive introduction of new technology. Whileplanning the next project in this program, the project manager has expanded the scope managementplan because as a project becomes more complex, the level of uncertainty in the scope: *
1 point
7. During a meeting with some of the project stakeholders, the project manager is asked to add work tothe project scope. The project manager had access to correspondence about the project before theproject charter was signed and remembers that the project sponsor specifically denied funding for thescope mentioned by these stakeholders. The best thing for the project manager to do is to: *
1 point
8. A new project manager is being mentored by a more experienced PMP-certified project manager. Thenew project manager is having difficulty finding enough time to manage the project because the projectscope is being progressively elaborated. The PMP-certified project manager advises that the basic toolsfor project management, such as a work breakdown structure, can be used during project executing toassist the project manager. For which of the following can a work breakdown structure be used? *
1 point
9. During a project team meeting, a team member suggests an enhancement to the scope that is beyondthe scope of the project charter. The project manager points out that the team needs to concentrate oncompleting all the work and only the work required. This is an example of: *
1 point
10. A project has just started the second phase, in which work packages are being created. A new teammember has completed his work packages for this phase and has asked the project manager to validatethe scope of his work packages. The team member is anxious to have the customer see his workpackages. The project manager, although confident in this new team member, wants the team memberto gain confidence after the customer sees his work packages. When should the Validate Scope processbe done? *
1 point
11. The project is mostly complete. The project has a schedule variance of300 and a cost variance of -900. All but one of the quality control inspections have been completed, and all have met the quality requirements. All items in the issue log have been resolved. Many of the resources have been released. The sponsor is about to call a meeting to obtain product validation when the customer notifies the project manager that they want to make a major change to the scope. The project manager should: *
1 point
12. You have just joined the project management office after five years of working on projects. One of the things you want to introduce to your company is the value of creating and utilizing work breakdown structures. Some of the project managers are angry that you are asking them to do “extra work.” Which of the following is the best thing you could tell the project managers to convince them to use work breakdown structures? *
1 point
13. A new project manager has asked you for advice on creating a work breakdown structure. After you explain the process to her, she asks you what software she should use to create the WBS and what she should do with it when it is completed. You might respond that the picture is not the most valuable result of creating a WBS. The most valuable result of a WBS is: *
1 point
14. To manage a project effectively, work should be broken down into small pieces. Which of the following does not describe how far to decompose the work? *
1 point
15. A project manager may use__________to make sure the team members clearly know what is includedin each of their work packages. *
1 point
16. On an agile software development project, the project manager asks business stakeholders to create user stories, which will be used in the development and testing of the new application. The main purpose of a user story is: *
1 point
17. The development phase of a new software product is near completion. A number of quality issues have increased the cost of building the product, but the project manager and team feel these costs will be inconsequential once the project gets to market. The next phases are testing and implementation. The project is two weeks ahead of schedule. Which of the following processes should the project manager be most concerned with before moving into the next phase? *
1 point
18. You are managing a six-month project and have held biweekly meetings with your project stakeholders. After five-and-a-half months of work, the project is on schedule and budget, but the stakeholders are not satisfied with the deliverables. This situation will delay the project completion by one month. The most important process that could have prevented this situation is: *
1 point
19. All of the following are parts of the scope baseline except the: *
1 point
20. One of the stakeholders on the project contacts the project manager to discuss some additional scope they would like to add to the project. The project manager asks for details in writing and then works through the Control Scope process. What should the project manager do next when the evaluation of the requested scope is complete? *
1 point
21. During the completion of project work, the sponsor asks the project manager to report on how the project is going. In order to prepare the report, the project manager asks each of the team members what percent complete their work is. There is one team member who has been hard to manage from the beginning. In response to being asked what percent complete he is, the team member asks, “Percent complete of what?” Tired of such comments, the project manager reports to the team member’s boss that the team member is not cooperating. Which of the following is most likely the real problem? *
1 point
22. Being prepared to do a complete job of developing and finalizing the scope baseline requires that you have done a thorough and timely job of identifying and analyzing stakeholders, and of collecting requirements. The development of the scope baseline can best be described as involving: *
1 point
23. Which of the following is an output of the Collect Requirements process? *
1 point
24. The cost performance index (CPI) on the project is 1.13, and the benefit-cost ratio is 1.2. The project scope was created by the team and stakeholders. Requirements have been changing throughout the project. No matter what the project manager has tried to accomplish in managing the project, which of the following is he most likely to face in the future? *
1 point
25. Validate Scope is closely related to *
1 point
26. A highway renewal project you are managing appears to have some missing scope. Your understanding of the scope was that the highway was to be resurfaced. Now, one of the construction foremen has come to ask why he finds no mention of repainting the lines on the repaved road. He also wants to know if there are any guard rail replacement work packages in the project. You have seen some of the resurfaced road that is completed, with the new lines painted on them. Which of the following is most likely to have caused the misinterpretation of the project scope statement? *
1 point
27. Which of the following is correct in regard to the Control Scope process? *
1 point
28. Which of the following best describes the Validate Scope process? *
1 point
29. Which of the following best describes product analysis? *
1 point
30. Which of the following best describes the difference between the Control Scope process and the Perform Integrated Change Control process? *
1 point
31. The project was tasked to develop a new software to be used by three sales channels of an auto parts company. The project was consistently on time and within budget, and the stakeholders approved prototypes of the software. However, when the completed software was installed and beta tested, a problem was discovered. Although the software performed as expected on in-store and call center- assisted purchases, it was found to be incompatible with other software necessary to complete online transactions. Therefore, the customer refused to accept the final deliverable, and the team was left to find a new software package that would accommodate all the customer s needs.Which of the following did the team not do? *
1 point