Originally a project had four team members. The scope of work has expanded and now requires more complex programming skills than any of the current team members possess. Rather than providing training for the existing team members, a decision is made to add a couple of highly skilled programmers to the team. With the new additions, there are a total of six people on the project team. How many communication channels does the project have? *
1 分
Inputs to the Plan Communications Management process include all the following except: *
1 分
A team member has been late to several recent team meetings, and the last two deliverables he submitted were not acceptable. The project manager decides he can no longer wait for things to improve, and must address the issue with the team member. What is the best form of communication for addressing this problem? *
1 分
A major construction project has been having a lot of schedule changes due to unanticipated weather problems. The weather issues are likely to result in cost overruns if they persist beyond the current week. If the weather improves within the next few days, the team will be able to make up for lost time without having to work overtime. Avoiding overtime will allow the project manager to control against cost overruns. Who is it best to notify of these changes? *
1 分
You are managing a complex project for a large company. Company executives are planning a quarterly meeting. They would like you and other project managers within the company to prepare reports that predict future status on your projects. What report will you submit for the quarterly meeting? *
1 分