PMP® Practice Quiz - 18
Sign in to Google to save your progress. Learn more
Which statement is TRUE of quality planning? *
1 point
Which of the following is generally not regarded as an element of active listening: *
1 point
A project manager is using a cause and effect diagram with the team to determine how various factors might be linked to potential problems. In what part of the quality management process is the project manager involved? *
1 point
You have just been assigned as project manager for a large manufacturing project. This one-year project is about halfway done. It involves five different sellers and 20 members of your company on the project team. You want to quickly review where the project now stands. Which of the following reports would be the MOST helpful in finding such information? *
1 point
All of the following are parts of the team's stakeholder management effort EXCEPT: *
1 point
Your company is in competition to win a major project for the government of a country. Your contacts in that country inform you that you must make a large payment to the foreign minister to be considered for the project. What should you do? *
1 point
The project manager is making sure that the product of the project has been completed according to the project management plan. What part of the project management process is he in? *
1 point
ABC company has recently launched a new model of their car in the market and the market response has been overwhelming. Sales have gone up to a level much higher than what the company anticipated. To cater to the increased market demand, the company plans to start a project to create a new assembly line for the cars. Who, according to you, is the user for this project? *
1 point
Your project sponsor recently attended a project management conference, where it was stated that Management by Objectives helps in all of the following EXCEPT: *
1 point
A team member is showing up late to work and leaving early, and it is affecting the project. The project manager decides that the team member must be reprimanded. Which of the following is the BEST way to handle this situation? *
1 point
After a great deal of effort, the project team has finally determined the specifications for a major scope change to the project. In light of this, what should the project manager do FIRST? *
1 point
All of the following result from quality audits EXCEPT: *
1 point
One of your team members informs you that he does not know which of the many projects he is working on is the most important. Who should determine the priorities among projects in a company? *
1 point
All of following should be done by the project manager during the project monitoring and controlling process group EXCEPT: *
1 point
While making presentations, the difference between a milestone chart and a bar chart is that unlike bar charts, milestone charts: *
1 point
In your project, you are collecting baseline data and distributing it to appropriate stakeholders as required. The information provided includes how resources are used to achieve project objectives. This is done through: *
1 point
During project execution you found out that work is often not performed at the right time and in the right order. Deliverables are made by one team member that cannot be processed by another one. This already leads to timely rework and bad morale among team members. Which project management tool is most appropriate to deal with problems like this? *
1 point
You're a project manager working in a weak matrix organization. Which of the following is NOT true? *
1 point
In your project, you would like to identify logical groupings based on natural relationships. Which one of the following techniques would you use? *
1 point
The project budget is proving to be inaccurate. The SPI is 1.1. The team has had negative deviation from the activity attributes, and the sponsor has inserted herself on the change control board. What is the BEST thing for the project manager to do? *
1 point
During the execution of a project to build a complex defense system, your team has run into a deep crisis. The project's goal and objectives have been challenging right from the start, but now you have discovered that your team members have become increasingly unaware of them. Being busy solving detail problems, they often fail to understand the overall requirements. Then they develop solutions which resolve issues in their area of limited responsibility, while causing new problems at the interfaces with other system components. Meanwhile, the team members show signs of growing frustration, and time is running away. How can you help your team in this situation? *
1 point
You're managing a software project. Your team has discovered a problem, and as a result you've requested a change. The change will cost the project an extra three weeks, but without it several stakeholders might have problems with the final product. What's the NEXT thing that you should do? *
1 point
In your project, you are documenting project purchasing decisions, specifying the approach and identifying potential sellers. Some tools you can use include all the following EXCEPT: *
1 point
Free float is the amount of time an activity can be delayed without delaying the: *
1 point
An output of the Close Project or Phase process is the creation of: *
1 point
You are preparing a quality management plan for your project. Which of the following will you NOT use in this process? *
1 point
Which of the following is NOT one of the most common sources of project conflict? *
1 point
In your project, there have been several changes in the cost and schedule estimates, and the original estimating assumptions are no longer valid. Calculate the estimate at completion (EAC) for your project based on the following data? BAC = $ 300,000; AC = $ 100,000; EV = $ 150,000; CPI = 1.2; ETC = $ 120,000 *
1 point
A project manager is planning a project when he discovers that the project has many different work products which must be completed in a sequence, with each dependent on starting after the previous work product is completed. What is the BEST thing the project manager can do? *
1 point
You have recently joined as a project manager in a company where they follow a projectized organizational structure. All your team members work in the same office where you have a lot of independence and authority. All the following are advantages of a projectized organizational structure EXCEPT: *
1 point
The project management office is worried about the quality of the company's various projects. They want to know which projects are having problems and which ones are doing well. If the PMO receives the following information, which project should they be the MOST concerned about? *
1 point
A team member determines that the scope for her activity is no longer valid. She comes to you for advice on making the change. To which of the following documents should the project manager refer to make this change? *
1 point
Your project exceeded costs in the past caused by an underestimation of resource costs in the cost baseline: PV: $1,200,000; EV: $1,000,000; AC: $1,200,000. You expect the underestimation to influence the future as much as it did in the past. If the value of the remaining work (BAC - EV) is at $1,000,000, what should be your new EAC (Estimate at Completion)? *
1 point
What is true for the process of Scope verification? *
1 point
A project is considered closed when the: *
1 point
You are the project manager of a project, which has the objective of producing bearings with a margin of error of .002 mm according to Six Sigma specifications used in your company. You have been asked to create documents that can help you apply technical and administrative direction to audit the bearings and ensure that they conform to requirements. You should use: *
1 point
You are the project manager for the seller and are in the process of having work crews dig a trench to lay fiber for a high-speed internet connection. All of the work permits have been obtained and funding has been approved. There have been several weather-related delays, but due to perseverance of the entire team, the project is on time. It is the customer's responsibility to provide entrance facilities so the connection into the building can be made. You discover the customer does not have adequate facilities and will not have them in time. What should you do? *
1 point
You are creating a cost management plan for your Six-Sigma project. In this context, all the following statements relating to creation of cost management plan are accurate EXCEPT: *
1 point
You are a project manager leading a cross-functional project team in a weak matrix environment. None of your project team members report to you functionally and you do not have the ability to directly reward their performance. The project is difficult, involving tight date constraints and challenging quality standards. Which of the following types of project management power will likely be the MOST effective in this circumstance? *
1 point
Recently you joined ABC bank as a project manager. Although the project is within budget and doing well, recently there have been several change requests. The outgoing project manager was using twelve project management processes during the project execution. Given this information, which of the following could be the most likely cause of frequent change requests? *
1 point
The customer on a project tells the project manager he has run out of money to pay for the project. What should the project manager do FIRST? *
1 point
You have assumed responsibility for a complex, business-critical project involving new technology and approaches. All of the project's stakeholders have emphasized to you that this is a high-risk effort, and that you are responsible for effectively identifying and addressing the project's risks. There are a number of risk management tools and approaches you have been encouraged to use, but there is no agreement from the stakeholders as to which is the superior approach. The organization sponsoring the project has recommended risk management methodologies and templates, but does not consistently or effectively use them. In addressing risk management planning for this project, what is the MOST important consideration you should keep in mind? *
1 point
You are in the process of planning a project and found that stakeholders often have varying objectives and requirements, which makes it hard to some up a plan in such way that all objectives will be met. What is probably most helpful to ensure common understanding? *
1 point
Which of the following is NOT true about overlapping phases? *
1 point
You are defining evaluation criteria for your project. The procurement item is readily available from a number of acceptable sellers. Which criterion can you focus on in such a situation? *
1 point
In the project execution phase, deliverables are produced. While monitoring and controlling project work, you track, review, and regulate the progress to meet the performance objectives. In this context, what is NOT performed in the Monitor and Control Project Work process? *
1 point
Which of the following is a basic rule or guideline for creating a work breakdown structure? *
1 point
The project manager is allocating overall cost estimates to individual activities to establish a baseline for measuring project performance. What process is this? *
1 point
The term Baseline is used in both disciplines Project management and Configuration management. Which statement is not true? *
1 point
Items at the lowest level of a Work Breakdown Structure are also called: *
1 point
While project work is being done, conflicts can arise between the procurement officer and the project manager because the procurement officer: *
1 point
Bidder conferences are part of: *
1 point
What is the LAST thing that occurs in the Close Project or Phase process? *
1 point
As a project manager, you are aware that changes are bound to occur in the projects. While you are monitoring and controlling changes, you use the term project scope creep. What does the term refer to? *
1 point
Which of the following would BEST prevent cultural problems on your international project? *
1 point
The carpeting subcontractor has, without prior approval, installed carpet that is a slightly different pattern from the pattern selected for the project. The difference in cost per square yard saves the buyer approximately US $10,000. Upon learning of the change, the BEST course of action for the project manager is to: *
1 point
During critical negotiations on outstanding issues arising out of a contract, you should pay close attention to which form of communication? *
1 point
In order to complete the project initiating processes, a project manager needs the project charter and: *
1 point
Which part of the risk management process receives input from risk response owners? *
1 point
A change has occurred on your project. You've documented the change, filled out a change request, and submitted that request to the change control board (CCB). What's the NEXT thing that must happen on the project? *
1 point
You work for a company which executes heavy engineering contracts. While performing risk response planning for your project, you determine a risk that there is a "Possibility of getting new orders in the future which are beyond the current capacity of our production facilities." What should you do? *
1 point
Your employee is three days late with a report. Five minutes before the meeting where the topic of the report is to be discussed, she hands you the report. You notice some serious errors in it. What should you do? *
1 point
A project manager working for a construction company works closely with a design firm. Part of his responsibility is to negotiate and approve bid documents with the design firm. The design firm offers the project manager a job with the firm, which he accepts. When the project manager gives his two weeks' notice to the construction company, he is not asked nor does he mention that the design firm will employ him. For the next two weeks, the project manager continues to negotiate and approve bids and designs submitted by the design firm. In this situation: *
1 point
You are assigned a US $2 million project with the standard deviation of the estimated costs of US $200,000. What type of contract do you recommend? *
1 point
What is best used to calculate the profit from an internal project? *
1 point
You are managing a project for a company that has previously done three projects that were similar to it. You consult with the cost performance baselines, lessons learned, and project managers from those projects, and use that information to come up with your cost estimate. What technique are you using? *
1 point
Instead of celebrating the end of the project, the stakeholders are breathing a sigh of relief. None of them were confident the project would meet the end date. Which of the following is NOT one of the reasons this project had difficulty? *
1 point
A parking lot fencing project was bid at US $11 per foot, and one company is doing all the work. The parking lot has four equal sides of 125 feet and requires the installation of a six-foot diameter culvert on one side. Fencing should be installed at a rate of 100 feet per day. The culvert installation will cost US $500 and take one day to complete. The culvert must be installed before work can begin on that side of the fence. After three days of work, one side is complete, another has 75 feet installed, and the culvert is completely installed. Acutal cost is $2,700. What is the current status of the project? *
1 point
You're managing a software project. You've created the schedule, and you need to figure out which activities absolutely cannot slip. You've done critical path analysis, identifying the critical path and calculating the early start and early finish for each activity. Which activities cannot slip without making the project late? *
1 point
You are given the following four projects. Which project will you select? *
1 point
In managing project communications, what should the project manager keep in mind? *
1 point
Which of the following is NOT an example of a deliverable? *
1 point
Of the following documents, all of which are updated during Control Schedule process, which is NOT a part of the project management plan? *
1 point
The results of another project have just been posted. Substantial rework will be required in order to meet the project requirements. Because the cost is so high, effective immediately, the project management office will be requiring all projects to do statistical sampling. What is the project management office concentrating its efforts on improving? *
1 point
A project manager is trying to settle a dispute between two team members. One says the systems should be integrated before testing, and the other maintains each system should be tested before integration. The project involves over 30 people, and 12 systems need to be integrated. The sponsor is demanding that integration happens on time. What is the BEST statement the project manager can make to resolve the conflict? *
1 point
All of the following are forms of power derived from the project manager's position EXCEPT: *
1 point
The project manager for a construction project discovers that a new water line is being created in the neighborhood where he's managing a project. Company policy requires that a series of forms for city environmental changes need to be filled out before his team can continue work on the project. This is an example of: *
1 point
Your manager asks you where to find a list of projects that should be managed together. What is the BEST place to find this information? *
1 point
You are managing a construction project to install wiring in an office building. You discover that one of your team members has taken a box of cable from the job site so he can wire his attic. What is the BEST way to respond? *
1 point
In your project, you are in the process of performing the work as defined in the project management plan to achieve the project's objectives. This is done during: *
1 point
Which of the following is NOT a characteristic of the Project Management Plan? *
1 point
Utility function is a commonly used technique to find out the project manager's risk tolerance levels. Some project managers are more averse to risk than others. All of the following are classifications of risk tolerance EXCEPT: *
1 point
You have been working on a nine-month project for six months. The project is ahead of schedule when one of the functional managers tells you that the resources committed to the project are no longer available. After checking further, you discover that the company has just started another project and is using the resources committed to your project. You believe that the new project is not critical, but the project manager is the son of a board member. What is the BEST course of action in this situation? *
1 point
You have a cost plus fee (CPF) contract with the customer and an arrangement with your manager whereby you will receive 10 percent of the contract amount as your payment for services. While completing the project, you discover that the actual cost will be lower than expected, thus decreasing your fee. What should you do? *
1 point
To manage a project effectively, work should be broken down into small pieces. Which of the following does NOT describe how far to decompose the work? *
1 point
You are in the middle of a complex negotiation when the other party says, "We need to finish in one hour because I have to catch my plane." That person is using which of the following negotiation strategies? *
1 point
Which of the following processes is in the Initiating process group? *
1 point
Bob and Sue are stakeholders in your project. Sue is in the high-power, low-interest quadrant of the Power/Interest grid. Bob is in the low-power, high-interest quadrant. Which of the following BEST describes the approach you should take? *
1 point
Your project has a virtual team. Half of your team members are located in another country, where they are working for a subcontractor. The subcontractor's team members speak a different dialect of English than your team does. After a conference call, two of your team members make jokes about the way your subcontractor's team members speak. What is the BEST way to handle this situation? *
1 point
All of the following are true EXCEPT: *
1 point
A project manager is finalizing a project that has had repeated problems with cost conformance. He is concerned about what management will say. Which of the following types of information would be BEST for the project manager to use to evaluate performance? *
1 point
You are a project manager working on a large software integration project involving multiple sellers. One of your key sellers has informally requested a change to her procurement statement of work to account for some requirements she neglected to address. You are relatively certain that the change requests will add time and cost to the project. What should you do in response to the seller's request? *
1 point
Which of the following BEST describes when you perform the Monitor and Control Project Work process? *
1 point
In a recent job interview, you are asked to define the most important characteristic of a project manager. Which of the following will be the best answer? *
1 point
The company is considering three projects: Project A has an NPV of $ 500,000; Project B has an NPV of $ 300,000; Project C has an NPV of $ 200,000; What is the opportunity cost if project A is selected? *
1 point
Following the cultural approach of the corporation for which you are starting to manage a project, you are guiding your project team through the first life-cycle phase of conceptualization. Your next step is to call for a team meeting to let ideas emerge in an unrestricted creative process. What exactly should that look like? *
1 point
You are the project manager responsible for developing a software application based on customer requirements. Which technique do you use in order to consider the customer's change request? *
1 point
Quality management complements project management, as both recognize the importance of: *
1 point
A request, demand or assertion of a contract partner for consideration, compensation or payment under a legally binding contract, such as a disputed change, is often referred to as a ____ *
1 point
Given this portion of the network diagram to the right, what's the LF of activity F? *
1 point
Captionless Image
Submit
Clear form